Project title: Optimization of corn seed DS-bulk realization in the Sinesti Monsanto Plant, Romania

IDENTIFICATION

Black Belt Student: Liviu Galateanu

Master Black Belt: Jorgelina Carcova Issue Date: March 1, 2007

Champion: Mihai Haraga Revision no: 1

Other Team Members: Crin Popescu and all the Seed Plant Team

Ioan Moraru and all the rest of the Field Team

Florina Ionita and Florentina Georgescu (Quality Lead and Quality Lab Supervizor)

Project Start Date: March 10, 2007

Organization / Location: Sinesti, Romanian Monsanto Seed Plant;

Planned Completion Date: May, 2008 (first stage)

DESCRIPTION

Product / Process: Corn seed DS-bulk optimization in the Romanian plant, Sinesti.

__________ ______ ____ __________ ______ ____ __________ ______ ____ ____________

Problem Description:

Starting with 2007, in Sinesti (Romania) started a Monsanto Seed Plant. We'll collect seed samples from each processing stage in order to build a database regarding the seed quality. A detailed analysis will most likely reveal the process steps that have a negative impact on the quality of the processed corn. During the FY08 season we'll focus on those areas in the plant where the data shows that we can improve the seed quality.

Projected Business Benefits (include customer/supplier impact): In FY08 we'll be able to run some numbers.

__________ ______ ____ __________ ______ ____ __________ ______ ____ ____________

Goal/Objective: The goals are to build a database with the seed quality from each seed processing stage, to identify the processing stages where the seed quality decrease and to find solutions for that processing stage in order to improve the seed quality.

__________ ______ ____ __________ ______ ____ __________ ______ ____ ____________

Projected Business Benefits:

METRICS

Metric

Unit of Measure

Data Available?

Baseline

Target

$/yr Savings at Target

time/cost/quality/other

hours/$$/scrap/%

_Yes __No

Now it is __?

Goal is__?

$/yr/ha

WT%, CT%, Culls, Broken kernels

%

No

*extra due to MON 13900 operation

FINANCIAL


Project Costs Estimated Original Savings

Capital Increm. Expense Working Cap. Annualized: Capital Avoidance: NPV

 

 
 

1000

 
$
 
  $ $ $ $ $

AUTHORITY

Title

Name

Signature

Date

Master Black Belt

Jorgelina Carcova

Black Belt Student

Liviu Galateanu

Champion

Mihai Haraga

Seed Plant Manager (Process Owner)

Crin Popescu

DISTRIBUTION

- TEAM MEMBERS

- COORDINATOR

- PROJECT FOLDER


Document Info


Accesari: 1219
Apreciat: hand-up

Comenteaza documentul:

Nu esti inregistrat
Trebuie sa fii utilizator inregistrat pentru a putea comenta


Creaza cont nou

A fost util?

Daca documentul a fost util si crezi ca merita
sa adaugi un link catre el la tine in site


in pagina web a site-ului tau.




eCoduri.com - coduri postale, contabile, CAEN sau bancare

Politica de confidentialitate | Termenii si conditii de utilizare




Copyright © Contact (SCRIGROUP Int. 2024 )