ALTE DOCUMENTE
|
||||||||||
| |||||||||||||||||
MODEC INTERNATIONAL LLC |
|||||||||||||||||
MODEC Project #: |
Document #: | ||||||||||||||||
1072-MI20-OPM1-0000 |
|||||||||||||||||
CNR Project #: C537-CNC-14461 |
Baobab Field Development | ||||||||||||||||
Document Title: | |||||||||||||||||
VOLUME 01 - SUBSEA SYSTEMS,FLOWLINES & RISERS |
|||||||||||||||||
FINAL ISSUE |
PD |
SKG |
RJW/PL |
||||||||||||||
Rev. |
Status |
Date |
Origin. |
Checker |
Approved |
||||||||||||
THIS DOCUMENT INCLUDING, DRAWINGS, PROCEDURES, SPECIFICATIONS, AND ITS CONTENTS IS THE EXCLUSIVE PROPERTY OF MODEC INTERNATIONAL LLC AND IS FURNISHED ON A CONFIDENTIAL BASIS, AND WITH THE EXPRESS AGREEMENT THAT IT WILL NEITHER BE USED, SOLD, TRANSFERRED, COPIED, TRACED, PHOTOGRAPHED, NOR REPRODUCED IN ANY MANNER WHATSOEVER IN WHOLE OR IN PART, NOR ANY ITEM HERIN BE SOLD, MANUFACTURED OR ASSEMBLED WITHOUT THE WRITTEN AGREEMENT OF MODEC INTERNATIONAL LLC THE RECIPIENT OF THIS DOCUMENT AGREES NOT TO DISCLOSE TO ANY OTHER PARTY INFORMATION CONTAINED HEREIN, OR NOT TO USE SUCH INFORMATION, EXCEPT FOR THE SPECIFIC PURPOSE INTENDED AT THE TIME OF RELEASE OF THIS DOCUMENT. |
|||||||||||||||||
Distribution |
Total |
||||||||||||||||
Status | |||||||||||||||||
Quantity | |||||||||||||||||
CHANGE CONTROL SHEET
REVISION INFORMATION |
|||
REV |
DATE |
SIGNATURE OF REVISION AUTHOR |
DATE |
SUBSEA SYSTEMS,FLOWLINES & RISERS
TABLE OF CONTENTS
Section-Page
Purpose
Scope
References
Definitions
Responsibility
Safety and Environmental CONSIDERATIONS
Process Overview
Major SUBSEA FLOWLINE Summary
System Summary
SUBSEA SYSTEM
Production Risers
Gas Import/Export Riser
WATER INJECTION RISER
GAS LIFT RISER
UMBILICAL
START UP, OPERATING & SHUTDOWN PROCEDURES - SUBSEA RISERs
Cold Start-up Procedure Following a Planned Shutdown.
Hot Start-up Procedure Following a Process Trip
Normal Operational Checks:
Planned Shutdown procedure
Emergency Controlled Shutdown Procedure
Alarm, Trip and PSV Settings
Valve List
Acknowledgements
Tables
Table 1 Production Riser size & Design Pressure
Table 2 Pressure Monitoring
Table 3 Temperature Monitoring
Table 4 Operating and Design Conditions for TU-FAT-0130
Table 5 Pressure Monitoring
Table 6 Temperature Monitoring
Table 7 Flow Monitoring
Table 8 Operating and Design Conditions for TU-FAS-0230
Table 9 Pressure Monitoring
Table 10 Temperature Monitoring
Table 11 Flow Monitoring
Table 12 Umbilical Summary
Table 13 Cold Start-up Valve Checklist
Table 14 Cold Start-up Overrides (Production Wells)
Table 15 Cold Start-up Overrides (Gas Lift)
Table 16 Cold Start-up Overrides (Water Injection)
Table 17 Cold Start-up Procedure Following a Planned Shutdown (Production Wells)
Table 18 Cold Start-up Procedure Following a Planned Shutdown (Gas LIft)
Table 19 Cold Start-up Procedure Following a Planned Shutdown (Water Injection)
Table 20 Hot Start-up Procedure Following a System Trip (Production Wells)
Table 21 Hot Start-up Procedure Following a System Trip (Gas Lift)
Table 22 Hot Start-up Procedure Following a System Trip (Water Injection)
Table 23 Planned Shutdown Procedure (Production Wells)
Table 24 Planned Shutdown Procedure (Gas LIft)
Table 25 Planned Shutdown Procedure (Water Injection)
Table 26 Emergency Controlled Shutdown Procedure
Table 27 Alarm, Trip & Settings (Production Wells)
Table 28 Alarm, Trip & Settings (Gas Lift)
Table 29 Alarm, Trip & Settings (Water Injection)
Table 30 Valve List
figure
Figure 1 Process Flow Diagram of the Subsea System.
INTRODUCTION
This document is part of the Operating Manual, which covers the Subsea Systems Flowlines & Risers . The Subsea System operations manual together with other manuals and related documents comprise the Facility Management System or FMS. The Subsea System is a controlled document maintained by MODEC INTERNATIONAL LLC, the Contract Operator of the Baobab Field. Any question concerning this document or its contents should be addressed to the Contract Operator.
This document gives a general description of and the task lists for the operation of the Subsea system. Its purpose is to educate those who are unfamiliar with the system in how it works and the way in which the system is to be started, stopped and operated safely. This document can be used as a reference document in formulating maintenance isolation procedures.
Information contained in this document applies only to the Subsea System on the Baobab Field Development project. The information contained gives general design information, alarm settings and trip points for the various components as well as the start up, shut down and normal operating procedures for the Subsea System.
Refer P&IDs 6220-PD-20-01-00001,6202-PD-02-05-00173,6219-PD-19-01-00001,1072-MI20-9020-0118,1072-MI20-9020-0146,6202-PD-02-01-00169,6202-PD-02-03-00171,6202-PD-02-02-00170,BAO-CNR-SU-PID-00187-04,BAO-CNR-SU-PID-00187-06,BA0-CNR-SU-PID-00187-01,BAO-CNR-SU-PID-00187-02,BAO-CNR-SU-PID-00186-02,BAO-CNR-SU-PID-00186-01 AND Alarm List (PT REF : 1072-CNR20-0002-0002)
See the Definitions Document of the FMS.
Every plant system covered by the Subsea System has been assigned to a single position title in the permanent offshore crew. The person filling the named position is jointly responsible with his off-duty relief for the integrity and the safe operation of the assigned system. In like manner it is that person's responsibility to verify the accuracy of the information contained in this document. Any confirmed inaccuracy shall be tracked by the Offshore Installation Manager (OIM) until formally corrected.
The job title of the position responsible for this system can be found in the System Responsibility Matrix in the Safety Management System (SMS) Manual (Doc No. 1072-MI20-15ST-0170).
In the execution of the subsequent procedures all permit to work, PPE and isolation procedures required by the Baobab SMS (Doc No. 1072-MI20-15ST-0170) shall be followed. If any doubt exists as to the correctness of valve positions or sequence of operations then they should be discussed with the supervisor and approval sought from the Facility Manager to change the procedure. These changes shall then be captured on a permanent basis by submitting them through the required document control procedures. Specific requirements for HSE are given in each section of the procedures.
Shut down overrides for this system can be invoked only when the system is continuously monitored. Proper procedures and systems should be followed while testing the trips. Where overrides are put in place for testing, these shall be removed at the end of testing so as not to inhibit shutdown functions.
The main Flowlines within the Subsea facilities are as follows:
Three Production Risers (Riser No. 1,3 & 5)
One Gas Import/Export Riser
One Water Injectio 24524m125y n Riser
One Gas Lift Riser
One Umbilical
Provision for additional five future risers
Initially seven Risers (three production, one gas import/export, one water injection, one gas lift and one Umbilical) are installed / connected at the external turret on the FPSO. In addition ,provision has been made for a total of five future risers (two production, one gas lift, one water injection and one umbilical). Flexible risers are used to link production and service functions in the subsea manifolds with processing facilities and controls on the FPSO. The turret is the mooring point for the FPSO as well as the interface between the subsea system and the topside modules. It serves as a connection point between the FPSO and the subsea system and is the pathway for getting oil from the reservoir into the vessel through subsea risers. The swivel stack is mounted on top of the turret, which itself is capable of rotating by means of upper and lower bearing allowing the vessel to weather vane around the turret. Flexible hose carry the well fluids from well manifolds, DCN and DCS, transporting it through the turret to the swivel stack. The swivel stack has a collection of the couplings for well fluids ,water injection, gas export, gas lift, hydraulic & electrical control signals. Production fluids shall be transported to the FPSO moored some 4-5 km from the drill center north (six well heads no. 11,12,13,14,15 and 16) and from drill center south (Six well heads No. 21,22,23,24,25 and 26) via production manifolds through three production risers. Provision has been made at DCN for additional wells to be tied in using the daisy-chain approach. The production wells have been drilled from two subsea manifolds on the western shoulder of the sub-sea canyon while the water injection wells have been drilled from two sub-sea manifold system tied back to the FPSO. The control system for subsea manifold is electro-hydraulic. Control is carried out by a multiplexed hydraulic control system ,where connections between the surface and subsea are via an umbilical. The main umbilical is provided with power/communication signal quads, HP &LP hydraulic control lines and chemicals. Physical separation between the umbilical and production pipeline shall be maintained at a nominal 15 m, where possible, to avoid excessive thermal effects on the umbilical.
Figure Process Flow Diagram of the Subsea System.
The main function of the subsea system is to connect the FPSO (top side processing unit) with the well heads to receive well fluids from well heads to the FPSO. The system also provides water injection for pressurization of the field, gas lift facility, chemical injection (Methanol, Scale Inhibitor, De-emulsifier, Wax Inhibitor & Corrosion Inhibitor) and hydraulic control of subsea valves and subsea instrument signal transmission to SCU (Subsea Control Unit) and DCS for monitoring and control the subsea process variables. Operator control and monitoring of the subsea system is via the FPSO DCS. DCS connected with Subsea Control Unit (SCU). SCU and SPCU (Subsea Control & Communication Unit) are the main control unit for subsea system connected with UPS (Uninterruptible Power Supply),HPU (Hydraulic Power Unit),DCS and topside ESD. The SCU is comprises of a number of modular units containing signal board computers. Operation and monitoring of subsea equipment is carryied out via Subsea Control Modules (SCM) which are connected to SCU. Electrical power and communications are provided between the surface and subsea on a combined communication and power system. I,e the same electrical conductors are used to provide both power and communications signals. Each SCM has two Subsea Electronic Modules (SEMs) to maintain the redundancy into the SCM. The SCM contains a set of solenoid operated directional control valves (DCVs) . These are used to switch hydraulic pressure to the particular function (e.g. tree or manifold valve). The solenoid operated DCVs have two dual wound solenoids, such that a valve open signal is directed to the open solenoid and a valve close signal is directed to the close solenoid. The solenoids are dual wound to allow the signal to be presented by either SEM. Design is such that the solenoid operated DCV is fail stay put on loss of electrical/ power/communications and fail closed on loss of hydraulic power.
There are twelve well heads, six from drill center north (DCN) and six from drill center south (DCN) connected through flexible hose to three production risers (riser no. 1,3 & 5). The well heads from DCN are connected with production riser no.1 & 3 and the well heads from DCS are connected with production risers no.3 & 5. Each production line from the well head has a subsurface safety valve (SSSV), one Production Master Valve (PMV), one Production Wing Valve (PWV), one production Choke Valve (PCV) two Manifold Production Valves (MPV) on the lines connecting the two production risers and a Manifold Test Valve (MTV) connected to the line with multi-phase flow-meters (2 off). Each production line from the wellhead has a gas lift line with associated valves and instruments connected with the annulus of the respective production well. In the annulus line of each production well head there are Annulus Access Valve (AAV), Annulus Insert Valve (AIV), Annulus Master Valve (AMV) and gas lift line with associated valves and instruments is connected with the annulus line. Each well head provided with demulsifier, methanol and scale inhibitor injection line. Each wellhead is production riser provided with methanol, scale, wax and corrosion inhibitor injection line and at the inlet of multi-phase flowmeters, demulsifier injection line also provided.
There are three off 11" ID production risers coming from the DCN and DCS manifolds ,connected to swivel manifold and finally, after passing through the turret, connect to the topside production manifold.
Table Production Riser size & Design Pressure
Manifold DCN/DCS |
Design Pressure |
Production Header |
345 barg |
Production Branch |
345 barg |
Production Test Line |
345 barg |
Pressure Monitoring, Control and ESD Instruments:
Drill center north manifold (six well head with tree no. 11,12,13,14,15 & 16) and Drill center south manifold (six well head with tree no. 21,22,23,24,25 & 26) combined in three production risers (Riser no. 1, 3 & 5) are provided with the following pressure transmitter to alert the operator.
Table Pressure Monitoring
Instrumentation Tag |
Description |
SS-PT-1131 |
Pressure Transmitter - Upstream of SS-XV-1112 Tree No. 11 |
SS-PT-1132 |
Pressure Transmitter - Upstream of SS-XV-1112 Tree No. 11 |
SS-PT-1121 |
Pressure Transmitter - Upstream Production Choke Press.1 Tree No. 11 |
SS-PT-1122 |
Pressure Transmitter - Upstream Production Choke Press.2 Tree No. 11 |
SS-PT-1123 |
Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 11 |
SS-PT-1124 |
Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 11 |
SS-PT-1231 |
Pressure Transmitter -Upstream of SS-XV-1212 Tree No. 12 |
SS-PT-1232 |
Pressure Transmitter -Upstream of SS-XV-1212 Tree No. 12 |
SS-PT-1221 |
Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 12 |
SS-PT-1222 |
Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 12 |
SS-PT-1223 |
Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 12 |
SS-PT-1224 |
Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 12 |
SS-PT-1331 |
Pressure Transmitter -Upstream of SS-XV-1312 Tree No. 13 |
SS-PT-1332 |
Pressure Transmitter -Upstream of SS-XV-1312 Tree No. 13 |
SS-PT-1321 |
Pressure Transmitter- Upstream Production Choke Press.1 Tree No. 13 |
SS-PT-1322 |
Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 13 |
SS-PT-1323 |
Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 13 |
SS-PT-1324 |
Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 13 |
SS-PT-1431 |
Pressure Transmitter -Upstream of SS-XV-1412 Tree No. 14 |
SS-PT-1432 |
Pressure Transmitter -Upstream of SS-XV-1412 Tree No. 14 |
SS-PT-1421 |
Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 14 |
SS-PT-1422 |
Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 14 |
SS-PT-1423 |
Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 14 |
SS-PT-1424 |
Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 14 |
SS-PT-1531 |
Pressure Transmitter -Upstream of SS-XV-1512 Tree No. 15 |
SS-PT-1532 |
Pressure Transmitter -Upstream of SS-XV-1512 Tree No. 15 |
SS-PT-1521 |
Pressure Transmitter- Upstream Production Choke Press.1 Tree No. 15 |
SS-PT-1522 |
Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 15 |
SS-PT-1523 |
Pressure Transmitter- Downstream Production Choke Press.1 Tree No. 15 |
SS-PT-1524 |
Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 15 |
SS-PT-1631 |
Pressure Transmitter -Upstream of SS-XV-1612 Tree No. 16 |
SS-PT-1632 |
Pressure Transmitter- Upstream of SS-XV-1612 Tree No. 16 |
SS-PT-1621 |
Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 16 |
SS-PT-1622 |
Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 16 |
SS-PT-1623 |
Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 16 |
SS-PT-1624 |
Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 16 |
SS-PT-2131 |
Pressure Transmitter- Upstream of SS-XV-2112 Tree No. 21 |
SS-PT-2132 |
Pressure Transmitter -Upstream of SS-XV-2112 Tree No. 21 |
SS-PT-2121 |
Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 21 |
SS-PT-2122 |
Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 21 |
SS-PT-2123 |
Pressure Transmitter- Downstream Production Choke Press.1 Tree No. 21 |
SS-PT-2124 |
Pressure Transmitter- Downstream Production Choke Press.2 Tree No. 21 |
SS-PT-2231 |
Pressure Transmitter- Upstream of SS-XV-2212 Tree No. 22 |
SS-PT-2232 |
Pressure Transmitter- Upstream of SS-XV-2212 Tree No. 22 |
SS-PT-2221 |
Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 22 |
SS-PT-2222 |
Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 22 |
SS-PT-2223 |
Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 22 |
SS-PT-2224 |
Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 22 |
SS-PT-2331 |
Pressure Transmitter -Upstream of SS-XV-2312 Tree No. 23 |
SS-PT-2332 |
Pressure Transmitter -Upstream of SS-XV-2312 Tree No. 23 |
SS-PT-2321 |
Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 23 |
SS-PT-2322 |
Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 23 |
SS-PT-2323 |
Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 23 |
SS-PT-2324 |
Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 23 |
SS-PT-2431 |
Pressure Transmitter -Upstream of SS-XV-2412 Tree No. 24 |
SS-PT-2432 |
Pressure Transmitter -Upstream of SS-XV-2412 Tree No. 24 |
SS-PT-2421 |
Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 24 |
SS-PT-2422 |
Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 24 |
SS-PT-2423 |
Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 24 |
SS-PT-2424 |
Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 24 |
SS-PT-2531 |
Pressure Transmitter -Upstream of SS-XV-2512 Tree No. 25 |
SS-PT-2532 |
Pressure Transmitter -Upstream of SS-XV-2512 Tree No. 25 |
SS-PT-2521 |
Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 25 |
SS-PT-2522 |
Pressure Transmitter- Upstream Production Choke Press.2 Tree No. 25 |
SS-PT-2523 |
Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 25 |
SS-PT-2524 |
Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 25 |
SS-PT-2631 |
Pressure Transmitter- Upstream of SS-XV-2612 Tree No. 26 |
SS-PT-2632 |
Pressure Transmitter -Upstream of SS-XV-2612 Tree No. 26 |
SS-PT-2621 |
Pressure Transmitter- Upstream Production Choke Press.1 Tree No. 26 |
SS-PT-2622 |
Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 26 |
SS-PT-2623 |
Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 26 |
SS-PT-2624 |
Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 26 |
SS-PT-1021 |
Pressure Transmitter -Production Riser No. 3 |
SS-PT-1022 |
Pressure Transmitter -Production Riser No. 1 |
SS-PT-2021 |
Pressure Transmitter -Production Riser No. 5 |
SS-PT-2022 |
Pressure Transmitter -Production Riser No. 3 |
Process variable from pressure transmitter is transmitted to the Subsea Control Unit (SCU) and Distributed Control System (DCS) with high and low alarm. Refer to section 6.0 for the alarm settings.
Temperature Monitoring, Control and ESD Instruments:
Drill center north manifold (six well head with tree no. 11,12,13,14,15 & 16) and Drill center south manifold (six well head with tree no. 21,22,23,24,25 & 26) combined in three production risers (Riser no. 1, 3 & 5) are provided with the following temperature transmitter to alert the operator.
Table Temperature Monitoring
Instrumentation Tag |
Description |
SS-TT-1131 |
Temperature Transmitter - Upstream of SS-XV-1112 Tree No. 11 |
SS-TT-1132 |
Temperature Transmitter - Upstream of SS-XV-1112 Tree No. 11 |
SS-TT-1121 |
Temperature Transmitter- Upstream Production Choke Temp.1 Tree No. 11 |
SS-TT-1122 |
Temperature Transmitter - Upstream Production Choke Temp.2 Tree No. 11 |
SS-TT-1123 |
Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 11 |
SS-TT-1124 |
Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 11 |
SS-TT-1231 |
Temperature Transmitter -Upstream of SS-XV-1212 Tree No. 12 |
SS-TT-1232 |
Temperature Transmitter -Upstream of SS-XV-1212 Tree No. 12 |
SS-TT-1221 |
Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 12 |
SS-TT-1222 |
Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 12 |
SS-TT-1223 |
Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 12 |
SS-TT-1224 |
Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 12 |
SS-TT-1331 |
Temperature Transmitter -Upstream of SS-XV-1312 Tree No. 13 |
SS-TT-1332 |
Temperature Transmitter -Upstream of SS-XV-1312 Tree No. 13 |
SS-TT-1321 |
Temperature Transmitter- Upstream Production Choke Temp.1 Tree No. 13 |
SS-TT-1322 |
Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 13 |
SS-TT-1323 |
Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 13 |
SS-TT-1324 |
Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 13 |
SS-TT-1431 |
Temperature Transmitter -Upstream of SS-XV-1412 Tree No. 14 |
SS-TT-1432 |
Temperature Transmitter -Upstream of SS-XV-1412 Tree No. 14 |
SS-TT-1421 |
Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 14 |
SS-TT-1422 |
Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 14 |
SS-TT-1423 |
Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 14 |
SS-TT-1424 |
Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 14 |
SS-TT-1531 |
Temperature Transmitter -Upstream of SS-XV-1512 Tree No. 15 |
SS-TT-1532 |
Temperature Transmitter -Upstream of SS-XV-1512 Tree No. 15 |
SS-TT-1521 |
Temperature Transmitter- Upstream Production Choke Temp.1 Tree No. 15 |
SS-TT-1522 |
Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 15 |
SS-TT-1523 |
Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 15 |
SS-TT-1524 |
Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 15 |
SS-TT-1631 |
Temperature Transmitter -Upstream of SS-XV-1612 Tree No. 16 |
SS-TT-1632 |
Temperature Transmitter- Upstream of SS-XV-1612 Tree No. 16 |
SS-TT-1621 |
Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 16 |
SS-TT-1622 |
Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 16 |
SS-TT-1623 |
Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 16 |
SS-TT-1624 |
Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 16 |
SS-TT-2131 |
Temperature Transmitter- Upstream of SS-XV-2112 Tree No. 21 |
SS-TT-2132 |
Temperature Transmitter -Upstream of SS-XV-2112 Tree No. 21 |
SS-TT-2121 |
Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 21 |
SS-TT-2122 |
Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 21 |
SS-TT-2123 |
Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 21 |
SS-TT-2124 |
Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 21 |
SS-TT-2231 |
Temperature Transmitter- Upstream of SS-XV-2212 Tree No. 22 |
SS-TT-2232 |
Temperature Transmitter- Upstream of SS-XV-2212 Tree No. 22 |
SS-TT-2221 |
Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 22 |
SS-TT-2222 |
Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 22 |
SS-TT-2223 |
Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 22 |
SS-TT-2224 |
Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 22 |
SS-TT-2331 |
Temperature Transmitter -Upstream of SS-XV-2312 Tree No. 23 |
SS-TT-2332 |
Temperature Transmitter -Upstream of SS-XV-2312 Tree No. 23 |
SS-TT-2321 |
Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 23 |
SS-TT-2322 |
Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 23 |
SS-TT-2323 |
Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 23 |
SS-TT-2324 |
Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 23 |
SS-TT-2431 |
Temperature Transmitter -Upstream of SS-XV-2412 Tree No. 24 |
SS-TT-2432 |
Temperature Transmitter -Upstream of SS-XV-2412 Tree No. 24 |
SS-TT-2421 |
Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 24 |
SS-TT-2422 |
Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 24 |
SS-TT-2423 |
Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 24 |
SS-TT-2424 |
Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 24 |
SS-TT-2531 |
Temperature Transmitter -Upstream of SS-XV-2512 Tree No. 25 |
SS-TT-2532 |
Temperature Transmitter -Upstream of SS-XV-2512 Tree No. 25 |
SS-TT-2521 |
Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 25 |
SS-TT-2522 |
Temperature Transmitter- Upstream Production Choke Temp.2 Tree No. 25 |
SS-TT-2523 |
Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 25 |
SS-TT-2524 |
Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 25 |
SS-TT-2631 |
Temperature Transmitter- Upstream of SS-XV-2612 Tree No. 26 |
SS-TT-2632 |
Temperature Transmitter -Upstream of SS-XV-2612 Tree No. 26 |
SS-TT-2621 |
Temperature Transmitter- Upstream Production Choke Temp.1 Tree No. 26 |
SS-TT-2622 |
Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 26 |
SS-TT-2623 |
Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 26 |
SS-TT-2624 |
Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 26 |
SS-TT-1021 |
Temperature Transmitter -Production Riser No. 3 |
SS-TT-1022 |
Temperature Transmitter -Production Riser No. 1 |
SS-TT-2021 |
Temperature Transmitter -Production Riser No. 5 |
SS-TT-2022 |
Temperature Transmitter -Production Riser No. 3 |
Process variable from temperature transmitter is transmitted to the Subsea Control Unit (SCU) and Distributed Control System (DCS) with high and low alarm. Refer to section 6.0 for the alarm settings.
Flow Monitoring :
From each wellhead, one line connected to the Multi-phase Flow meters (MP) through a manifold test valve (MTV) for measuring individual well production mass flow rate located in the DCN & DCS. SS-MFM-2051/2071 are the multi phase flow meters for Drill Center South (DCS) and SS-MFM-1051/1071 are the multi phase flow meters for Drill Center North (DCN).
From the third stage Booster Gas Compressor one six inch Gas Import/export line connected to the turret and on the subsea system. This line is finally connected to gas export line from FPSO Espoir and then to the 10" pipeline to shore. For details refer Doc. No. 1072-MI20-OPM1-05 for gas export system.
Sea water injection pump (09M-PAT-3020A/B/C/D/E/F) discharge connected to a 12" water injection header, which connected to water injection Swivel (TU-FAT-0818) in the turret area. The water injection riser termed as Riser No. 12 going to the subsea for water injection. Sea water is injected into the reservoir to enhance the recovery of oil by maintaining the reservoir pressure as the oil is taken out, hence improving oil production and prolonging the useful life of the field. Water injection riser no. 12 connected to the two water injection manifold North & South by flexible hose. In the water injection north and south manifold there are four injection wells (tree no. 31,32,33 and 34 for north and tree no. 41,42,43, & 44 for the south) for each manifold. In the water injection X-Mas tree there is a venturi flowmeter in the water injection line upstream of choke valve. Downstream of choke valve there are Injection Wing Valve (IWV) and Injection Master Valve (IMV) connecting the line to the injection well. Pressure and temperature transmitters are provided upstream and downstream of the choke valve for monitoring the process variable from SCU & DCS. Annulus Access Valve (AAV), Annulus Insert Valve (AIV), Annulus Master Valve (AMV) are provided in each annulus line connected to the water injection wells.
Water injection line from the topside is connected to the water injection swivel (TU-FAT-0818) has the operating pressure 172.4 barg @ 48° C and design pressure 248.2 barg @ 38° C. From water injection swivel the water injection riser No. 12 is connected to the subsea water injection manifold North & South. The water injection riser has the following operating & design conditions.
Table Operating and Design Conditions for TU-FAT-0130
Parameter |
Value |
Internal Diameter |
280 mm (11") |
Design Pressure |
248.2 barg @ 38oC |
Operating Pressure |
172.4 barg |
Flow Rate |
15900 M3/D (100000 BWPD) |
Pressure Monitoring, Control and ESD Instruments:
Water Injection North manifold (four injection well with tree no. 31,32,33 & 34) and Water Injection South manifold (four injection well with tree no. 41,42,43 & 44) combined in one water injection riser no. 12 are provided with the following pressure transmitter to alert the operator.
Table Pressure Monitoring
Instrumentation Tag |
Description |
SS-PT-3121 |
Pressure Transmitter - Downstream Choke Pressure 1 Tree No.31 |
SS-PT-3122 |
Pressure Transmitter - Downstream Choke Pressure 2 Tree No.31 |
SS-PT-3123 |
Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 31 |
SS-PT-3124 |
Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 31 |
SS-PT-3125 |
Pressure Transmitter - Annulus Pressure Tree No. 31 |
SS-PT-3221 |
Pressure Transmitter - Downstream Choke Pressure 1 Tree No.32 |
SS-PT-3222 |
Pressure Transmitter - Downstream Choke Pressure 2 Tree No.32 |
SS-PT-3223 |
Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 32 |
SS-PT-3224 |
Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 32 |
SS-PT-3225 |
Pressure Transmitter - Annulus Pressure Tree No. 32 |
SS-PT-3321 |
Pressure Transmitter - Downstream Choke Pressure 1 Tree No.33 |
SS-PT-3322 |
Pressure Transmitter - Downstream Choke Pressure 2 Tree No.33 |
SS-PT-3323 |
Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 33 |
SS-PT-3324 |
Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 33 |
SS-PT-3325 |
Pressure Transmitter - Annulus Pressure Tree No. 33 |
SS-PT-3421 |
Pressure Transmitter - Downstream Choke Pressure 1 Tree No.34 |
SS-PT-3422 |
Pressure Transmitter - Downstream Choke Pressure 2 Tree No.34 |
SS-PT-3423 |
Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 34 |
SS-PT-3424 |
Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 34 |
SS-PT-3425 |
Pressure Transmitter - Annulus Pressure Tree No. 34 |
SS-PT- 4121 |
Pressure Transmitter - Downstream Choke Pressure 1 Tree No.41 |
SS-PT- 4122 |
Pressure Transmitter - Downstream Choke Pressure 2 Tree No.41 |
SS-PT- 4123 |
Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 41 |
SS-PT- 4124 |
Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 41 |
SS-PT- 4125 |
Pressure Transmitter - Annulus Pressure Tree No. 41 |
SS-PT- 4221 |
Pressure Transmitter - Downstream Choke Pressure 1 Tree No.42 |
SS-PT- 4222 |
Pressure Transmitter - Downstream Choke Pressure 2 Tree No.42 |
SS-PT- 4223 |
Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 42 |
SS-PT- 4224 |
Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 42 |
SS-PT- 4225 |
Pressure Transmitter - Annulus Pressure Tree No. 42 |
SS-PT- 4321 |
Pressure Transmitter - Downstream Choke Pressure 1 Tree No.43 |
SS-PT- 4322 |
Pressure Transmitter - Downstream Choke Pressure 2 Tree No.43 |
SS-PT- 4323 |
Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 43 |
SS-PT- 4324 |
Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 43 |
SS-PT- 4325 |
Pressure Transmitter - Annulus Pressure Tree No. 43 |
SS-PT- 4421 |
Pressure Transmitter - Downstream Choke Pressure 1 Tree No.44 |
SS-PT- 4422 |
Pressure Transmitter - Downstream Choke Pressure 2 Tree No.44 |
SS-PT- 4423 |
Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 44 |
SS-PT- 4424 |
Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 44 |
SS-PT- 4425 |
Pressure Transmitter - Annulus Pressure Tree No. 44 |
Process variable from pressure transmitter is transmitted to the Subsea Control Unit (SCU) and Distributed Control System (DCS) with high and low alarm. Refer to section 6.0 for the alarm settings.
Temperature Monitoring
Water Injection North manifold (four injection wells with tree no. 31,32,33 & 34) and Water Injection South manifold (four injection wells with tree no. 41,42,43 & 44) connected to one water injection riser no. 12 are provided with the following temperature transmitter to alert the operator.
Table Temperature Monitoring
Instrumentation Tag |
Description |
SS-TT-3121 |
Temperature Transmitter - Downstream Choke Temperature 1 Tree No.31 |
SS-TT-3122 |
Temperature Transmitter - Downstream Choke Temperature 2 Tree No.31 |
SS-TT-3123 |
Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 31 |
SS-TT-3124 |
Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 31 |
SS-TT-3125 |
Temperature Transmitter - Annulus Temperature Tree No. 31 |
SS-TT-3221 |
Temperature Transmitter - Downstream Choke Temperature 1 Tree No.32 |
SS-TT-3222 |
Temperature Transmitter - Downstream Choke Temperature 2 Tree No.32 |
SS-TT-3223 |
Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 32 |
SS-TT-3224 |
Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 32 |
SS-TT-3225 |
Temperature Transmitter - Annulus Temperature Tree No. 32 |
SS-TT-3321 |
Temperature Transmitter - Downstream Choke Temperature 1 Tree No.33 |
SS-TT-3322 |
Temperature Transmitter - Downstream Choke Temperature 2 Tree No.33 |
SS-TT-3323 |
Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 33 |
SS-TT-3324 |
Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 33 |
SS-TT-3325 |
Temperature Transmitter - Annulus Temperature Tree No. 33 |
SS-TT-3421 |
Temperature Transmitter - Downstream Choke Temperature 1 Tree No.34 |
SS-TT-3422 |
Temperature Transmitter - Downstream Choke Temperature 2 Tree No.34 |
SS-TT-3423 |
Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 34 |
SS-TT-3424 |
Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 34 |
SS-TT-3425 |
Temperature Transmitter - Annulus Temperature Tree No. 34 |
SS-TT- 4121 |
Temperature Transmitter - Downstream Choke Temperature 1 Tree No.41 |
SS-TT- 4122 |
Temperature Transmitter - Downstream Choke Temperature 2 Tree No.41 |
SS-TT- 4123 |
Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 41 |
SS-TT- 4124 |
Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 41 |
SS-TT- 4125 |
Temperature Transmitter - Annulus Temperature Tree No. 41 |
SS-TT- 4221 |
Temperature Transmitter - Downstream Choke Temperature 1 Tree No.42 |
SS-TT- 4222 |
Temperature Transmitter - Downstream Choke Temperature 2 Tree No.42 |
SS-TT- 4223 |
Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 42 |
SS-TT- 4224 |
Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 42 |
SS-TT- 4225 |
Temperature Transmitter - Annulus Temperature Tree No. 42 |
SS-TT- 4321 |
Temperature Transmitter - Downstream Choke Temperature 1 Tree No.43 |
SS-TT- 4322 |
Temperature Transmitter - Downstream Choke Temperature 2 Tree No.43 |
SS-TT- 4323 |
Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 43 |
SS-TT- 4324 |
Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 43 |
SS-TT- 4325 |
Temperature Transmitter - Annulus Temperature Tree No. 43 |
SS-TT- 4421 |
Temperature Transmitter - Downstream Choke Temperature 1 Tree No.44 |
SS-TT- 4422 |
Temperature Transmitter - Downstream Choke Temperature 2 Tree No.44 |
SS-TT- 4423 |
Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 44 |
SS-TT- 4424 |
Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 44 |
SS-TT- 4425 |
Temperature Transmitter - Annulus Temperature Tree No. 44 |
Process variable from temperature transmitter is transmitted to the Subsea Control Unit (SCU) and Distributed Control System (DCS) with high and low alarm. Refer to section 6.0 for the alarm settings.
Flow Monitoring
Each water injection line to the respective injection wells are provided with a venturi flow meter upstream of the choke valve for monitoring the water injection flow rate of individual water injection well. The signal from the flow element transmitted to SCU & DCS for operator visigilence. The tag number of the flow transmitter for each water injection wells are given below:
Table Flow Monitoring
Instrumentation Tag |
Description |
SS-FT-3114A |
Flow Transmitter -1 Water Injection Tree No. 31 |
SS-FT-3114B |
Flow Transmitter -2 Water Injection Tree No. 31 |
SS-FT-3214A |
Flow Transmitter -1 Water Injection Tree No. 32 |
SS-FT-3214B |
Flow Transmitter -2 Water Injection Tree No. 32 |
SS-FT-3314A |
Flow Transmitter -1 Water Injection Tree No. 33 |
SS-FT-3314B |
Flow Transmitter -2 Water Injection Tree No. 33 |
SS-FT-3414A |
Flow Transmitter -1 Water Injection Tree No. 34 |
SS-FT-3414B |
Flow Transmitter -2 Water Injection Tree No. 34 |
SS-FT-4114A |
Flow Transmitter -1 Water Injection Tree No. 41 |
SS-FT-4114B |
Flow Transmitter -2 Water Injection Tree No. 41 |
SS-FT-4214A |
Flow Transmitter -1 Water Injection Tree No. 42 |
SS-FT-4214B |
Flow Transmitter -2 Water Injection Tree No. 42 |
SS-FT-4314A |
Flow Transmitter -1 Water Injection Tree No. 43 |
SS-FT-4314B |
Flow Transmitter -2 Water Injection Tree No. 43 |
SS-FT-4414A |
Flow Transmitter -1 Water Injection Tree No. 44 |
SS-FT-4414B |
Flow Transmitter -2 Water Injection Tree No. 44 |
From the third stage booster gas compressor discharge, one, six-inch gas lift riser is connected to the gas lift swivel (TU-FAS-0816) in the turret area. The gas lift riser No. 4 (TU-FAS-0230) from the gas lift swivels goes to the production well manifolds North & South. The gas lift riser (Riser No. 4) connected by flexible hose to the drill center North and South. In both the production manifolds the gas lift line distributed to each production wellhead is isolated by a Gas Lift Valve (GLV) upstream of the choke valve. When the oil reservoir pressure becomes low the well head pressure is not sufficient to move the well fluid to the topside and the gas injection to the well head through gas lift line introduces the motive force to the well fluid to flow it out from the well head to the topside. There is a venturi flow meter in each gas lift line upstream of the choke valve for gas flow monitoring. Downstream of the choke valve there is an Annulus Master Valve (AMV) through which the gas lift line is connected to the annulus of each production well.
Gas lift line from the topside is connected to the 6" Gas Lift Swivel ( TU-FAS-0816) has the operating pressure 173.7 barg @ 70° C and design pressure 248.2 barg @ 38° C. From Gas Lift Swivel the gas lift riser No. 4 is connected to the subsea gas lift manifold North & South. The gas lift riser have the following operating & design conditions.
Table Operating and Design Conditions for TU-FAS-0230
Parameter |
Value |
Internal Diameter |
152 mm (6") |
Design Pressure |
248.2 barg @ 38oC |
Operating Pressure |
173.4 barg |
Design Flow Rate |
1130000 M3/D (50 MMSCF/D) |
Pressure Monitoring, Control and ESD Instruments:
Gas lift manifold and the gas injection line of each X-Mass Tree of production wells are provided with the following pressure transmitter to alert the operator about the lift gas pressure.
Table Pressure Monitoring
Instrumentation Tag |
Description |
SS-PT-1125 |
Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.11 |
SS-PT-1126 |
Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.11 |
SS-PT-1225 |
Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.12 |
SS-PT-1226 |
Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.12 |
SS-PT-1325 |
Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.13 |
SS-PT-1326 |
Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.13 |
SS-PT-1425 |
Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.14 |
SS-PT-1426 |
Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.14 |
SS-PT-1525 |
Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.15 |
SS-PT-1526 |
Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.15 |
SS-PT-1625 |
Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.16 |
SS-PT-1626 |
Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.16 |
SS-PT-2125 |
Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.21 |
SS-PT-2126 |
Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.21 |
SS-PT-2225 |
Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.22 |
SS-PT-2226 |
Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.22 |
SS-PT-2325 |
Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.23 |
SS-PT-2326 |
Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.23 |
SS-PT-2425 |
Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.24 |
SS-PT-2426 |
Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.24 |
SS-PT-2525 |
Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.25 |
SS-PT-2526 |
Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.25 |
SS-PT-2625 |
Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.26 |
SS-PT-2626 |
Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.26 |
SS-PT-1023 |
Pressure Transmitter - Gas Lift Header Pressure DCN |
SS-PT-2023 |
Pressure Transmitter - Gas Lift Header Pressure DCS |
Process variable from pressure transmitter is transmitted to the Subsea Control Unit (SCU) and Distributed Control System (DCS) with high and low alarm. Refer to section 6.0 for the alarm settings.
Temperature Monitoring
Gas lift manifold and the gas injection line of each X-Mass Tree of production wells are provided with the following temperature transmitter to alert the operator about the lift gas temperature.
Table Temperature Monitoring
Instrumentation Tag |
Description |
SS-TT-1125 |
Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.11 |
SS-TT-1126 |
Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.11 |
SS-TT-1225 |
Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.12 |
SS-TT-1226 |
Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.12 |
SS-TT-1325 |
Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.13 |
SS-TT-1326 |
Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.13 |
SS-TT-1425 |
Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.14 |
SS-TT-1426 |
Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.14 |
SS-TT-1525 |
Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.15 |
SS-TT-1526 |
Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.15 |
SS-TT-1625 |
Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.16 |
SS-TT-1626 |
Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.16 |
SS-TT-2125 |
Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.21 |
SS-TT-2126 |
Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.21 |
SS-TT-2225 |
Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.22 |
SS-TT-2226 |
Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.22 |
SS-TT-2325 |
Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.23 |
SS-TT-2326 |
Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.23 |
SS-TT-2425 |
Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.24 |
SS-TT-2426 |
Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.24 |
SS-TT-2525 |
Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.25 |
SS-TT-2526 |
Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.25 |
SS-TT-2625 |
Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.26 |
SS-TT-2626 |
Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.26 |
SS-TT-1023 |
Temperature Transmitter - Gas Lift Header Temperature DCN |
SS-TT-2023 |
Temperature Transmitter - Gas Lift Header Temperature DCS |
Process variable from temperature transmitter is transmitted to the Subsea Control Unit (SCU) and Distributed Control System (DCS) with high and low alarm. Refer to section 6.0 for the alarm settings.
Flow Monitoring
Each gas lift line is provided with a venturi flow meter upstream of the choke valve for monitoring the gas flow of individual gas lift line into the respective production X-Mass tree. The signal from the flow element transmitted to SCU & DCS for operator visigilence. The tag numbers of the venturi flow meters are listed below.
Table Flow Monitoring
Instrumentation Tag |
Description |
SS-FT-1113A |
Flow Transmitter -1 Gas Lift Tree No. 11 |
SS-FT-1113B |
Flow Transmitter -2 Gas Lift Tree No. 11 |
SS-FT-1213A |
Flow Transmitter -1 Gas Lift Tree No. 12 |
SS-FT-1213B |
Flow Transmitter -2 Gas Lift Tree No. 12 |
SS-FT-1313A |
Flow Transmitter -1 Gas Lift Tree No. 13 |
SS-FT-1313B |
Flow Transmitter -2 Gas Lift Tree No. 13 |
SS-FT-1413A |
Flow Transmitter -1 Gas Lift Tree No. 14 |
SS-FT-1413B |
Flow Transmitter -2 Gas Lift Tree No. 14 |
SS-FT-1513A |
Flow Transmitter -1 Gas Lift Tree No. 15 |
SS-FT-1513B |
Flow Transmitter -2 Gas Lift Tree No. 15 |
SS-FT-1613A |
Flow Transmitter -1 Gas Lift Tree No. 16 |
SS-FT-1613B |
Flow Transmitter -2 Gas Lift Tree No. 16 |
SS-FT-2113A |
Flow Transmitter -1 Gas Lift Tree No. 21 |
SS-FT-2113B |
Flow Transmitter -2 Gas Lift Tree No. 21 |
SS-FT-2213A |
Flow Transmitter -1 Gas Lift Tree No. 22 |
SS-FT-2213B |
Flow Transmitter -2 Gas Lift Tree No. 22 |
SS-FT-2313A |
Flow Transmitter -1 Gas Lift Tree No. 23 |
SS-FT-2313B |
Flow Transmitter -2 Gas Lift Tree No. 23 |
SS-FT-2413A |
Flow Transmitter -1 Gas Lift Tree No. 24 |
SS-FT-2413B |
Flow Transmitter -2 Gas Lift Tree No. 24 |
SS-FT-2513A |
Flow Transmitter -1 Gas Lift Tree No. 25 |
SS-FT-2513B |
Flow Transmitter -2 Gas Lift Tree No. 25 |
SS-FT-2613A |
Flow Transmitter -1 Gas Lift Tree No. 26 |
SS-FT-2613B |
Flow Transmitter -2 Gas Lift Tree No. 26 |
The main umbilical is provided for power/signal, hydraulics and chemicals. The umbilical is routed in a common corridor with the pipelines wherever possible. Physical separation between the umbilical and production pipeline shall be maintained where possible to avoid excessive thermal effects on the umbilical. The riser umbilical is interfaced with the FPSO through the external turret. The umbilical is secured on the external turret and interfaced with the topsides via a Topside Termination Umbilical Unit (TUTU) and Umbilical Junction Boxes.
The 203 mm (8") umbilical has the following items and their respective operating and design conditions are given in the table below :
Table Umbilical Summary
Description |
Number |
Size |
Flow Rate |
Operating Pressure |
Design Pressure |
Hp Hydraulic Control Line |
2 |
3/4" Pipe |
N/A |
HOLD |
690 Barg |
Lp Hydraulic Control Line |
2 |
1/2" Pipe |
N/A |
207 Barg |
228 Barg |
Methanol |
3 |
1" Pipe |
40 M3/D |
310 Barg |
345 Barg |
Hp Scale Inhibitor |
10 |
1/2" Tubing |
0.14 M3/D |
310 Barg |
345 Barg |
Demulsifier |
10 |
1/2" Tubing |
1 M3/D |
310 Barg |
345 Barg |
Wax Inhibitor |
4 |
1/2" Tubing |
0.24 M3/D |
310 Barg |
345 Barg |
Corrosion Inhibitor |
4 |
1/2" Tubing |
0.24 M3/D |
310 Barg |
345 Barg |
The following procedure details the steps to be undertaken to start-up the Subsea System following maintenance activities that may have involved piping intrusion works on part / all of the systems / subsystems.
The following conditions are assumed to exist in executing this procedure: -
No Permits to Work are in force on any part of the system that may prohibit, or hinder, the safe start-up of the equipment.
The Fire and Gas Detection System, ESD Systems and control facilities within the CCR are operational including all alarms, trips and controllers.
All vents, purge points and manual sample points are closed and blanked, or capped off, where necessary.
The following ancillary systems must be available for operation prior to commencement of this procedure: -
Power is available to the skid
Hydraulic power system is operational
Inlet heater and production separator ready to receive well fluid
Water injection system ready for start up as per Doc. No. 1072-MI20-OPM1-30
Heating medium system is operational
Flow line circulation system ready to start as described in Doc. No. 1072-MI20-OPM1-12
The instrument air system must be in operation.
The production separation system should also be ready for start up as described in Doc. No. 1072-MI20-OPM1-10
Refer to the P&ID 's identified as pertaining to the relevant system whilst carrying out this procedure.
The system operator should check the system valves are in the positions detailed below.
Where valves are found to be out of position, the operator must satisfy himself it is safe to move the valve before doing so. This may involve referencing to an Isolation Permit or relevant Permit to Work.
Table Cold Start-up Valve Checklist
Cold start-up Valve Checklist |
||
line # / vALVE spec |
VALVE DESCRIPTION |
POSITION |
Production well heads & manifolds (Refer to P&ID DWG No BAO-CNR-SU-PID-00187-01 , BAO-CNR-SU-PID-00187-02, BAO-CNR-SU-PID-00187-04 & BAO-CNR-SU-PID-00187-06) | ||
XV-1112 |
SSSV on X mass tree no 11 |
open |
XV-1101 |
Production master valve on tree no 11 |
open |
XV-1102 |
Production wing valve on tree no 11 |
open |
PCV-1114 |
Production choke valve on tree no 11 |
closeD |
xv-1109 |
Manifold production valve (MPV-11) to production riser no. 3 |
closed |
xv-1110 |
Manifold production valve (MPV-12) to production riser no. 1 |
open |
xv-1108 |
Manifold test valve (MTV-1) from production well 11. |
closed |
The valve status for other production tree No. 12,13,14,15,16,21,22,23,24,25 & 26 will be same as given above for tree No. 11 |
||
xv-1015 |
Pig valve (PV) on DCN |
closed |
xv-2015 |
Pig valve (PV) on DCS |
closed |
xv-1003 |
Flow meter inlet valve (FIV-1) to multiphase flow meter MFM-1051 at DCN |
closed |
xv-1004 |
Flow meter inlet valve (FIV-2) to multiphase flow meter MFM-1071 at DCN |
closed |
fov-1 |
Flow meter outlet valve (FOV-1) from multiphase flow meter MFM-1051 at DCN |
closed |
fov-2 |
Flow meter outlet valve (FOV-2) from multiphase flow meter MFM-1071 at DCN |
closed |
fov-3 |
Flow meter outlet valve (FOV-3) from multiphase flow meter MFM-1051/1071 to production riser 1 & 3 at DCN |
closed |
xv-1001 |
Manifold test valve (MTV-7) from multiphase flow meters outlet to production riser No. 3 at DCN |
closed |
xv-1002 |
Manifold test valve (MTV-8) from multiphase flow meters outlet to production riser No. 1 AT DCN |
closed |
xv-2003 |
Flow meter inlet valve (FIV-1) to multiphase flow meter MFM-2051 at DCS |
closed |
xv-2004 |
Flow meter inlet valve (FIV-2) to multiphase flow meter MFM-2071 at DCS |
closed |
fov-1 |
Flow meter outlet valve (FOV-1) from multiphase flow meter MFM-2051 at DCS |
closed |
fov-2 |
Flow meter outlet valve (FOV-2) from multiphase flow meter MFM-2071 at DCS |
closed |
fov-3 |
Flow meter outlet valve (FOV-3) from multiphase flow meter MFM-2051/2071 to production riser 1 & 3 at DCS |
closed |
xv-2001 |
Manifold test valve (MTV-7) from multiphase flow meters outlet to production riser No. 5 at DCS |
closed |
xv-2002 |
Manifold test valve (MTV-8) from multiphase flow meters outlet to production riser No. 3 at DCS |
closed |
FTA Valve |
Flow line termination assembly isolation valves (Two No.) on riser no 1 |
open |
FTA Valve |
Flow line termination assembly isolation valves (Two No.) on riser no 3 |
close |
FTA Valve |
Flow line termination assembly isolation valves (Two No.) on riser no 5 |
open |
For the line up rest of the valves from swivel manifold to topside up to IP separator refer section 5.1.2 of Doc. No. 1072-MI20-OPM1-12 |
||
Cold start-up Valve Checklist |
||
Gas Lift System (Refer to P&ID DWG No 1072-MI20-9020-0118,6219-PD-19-01-00001, BAO-CNR-SU-PID-00187-01 , BAO-CNR-SU-PID-00187-02, BAO-CNR-SU-PID-00187-04 & BAO-CNR-SU-PID-00187-06) | ||
6"-pg-f1-1200/ 6" f2jfk |
Upstream isolation valves of FT-2425-1 from 3rd stage booster gas compressor to gas lift header |
CLOSED |
6"-pg-f1-1200/ 6" f2jfk |
Downstream isolation valves of FT-2425-1 from 3rd stage booster gas compressor to gas lift header |
locked open |
3" f2jrdk |
FT-2425-1 bypass valve |
locked close |
1" f2zf |
Bypass valve across the check valve on line no. 6"-PG-F-5801 |
locked close |
6"-PG-F-5801/ SDV-0230-1 |
Shutdown valve downstream of gas lift swivel (TU-FAS-0816) |
OPen |
6"-pg-f-5801 |
Isolation valve downstream of SDV-0230-1 from turret to riser |
open |
fta valve |
Flow termination assembly (FTA) isolation valves (Two No.)on gas lift riser No. 4 |
open |
ISOLATION VALVE |
Isolation valve from 6" subsea gas lift pipe line to DCN manifold |
open |
xv-1111 |
Gas lift valve (GLV-1) to production tree No. 11 |
open |
pcv-1113 |
Choke valve at the inlet of production tree No. 11 |
closed |
xv-1113 |
Annulus wing valve (AWV) down stream of choke valve of tree No.11 |
open |
xv-1103 |
Annulus master valve (AMV) in the annulus line in production tree No. 11 |
open |
xv-1107 |
XOV on tree no 11 |
closed |
aiv,aav |
Annulus insert & access valve on production tree No.11 |
closed |
The valve status for gas lift system for the other production tree No. 12,13,14,15,16,21,22,23,24,25 & 26 will be same as given above for tree No. 11 | ||
Water Injection System (Refer to P&ID DWG No 1072-MI20-9020-0146,6220-PD-20-01-00001, BAO-CNR-SU-PID-00186-01 & BAO-CNR-SU-PID-00186-02) | ||
6"-wi-f-2117/ 6" f2jrd |
Sea water injection pump (PAT-3020A/B/C/D/E/F) discharge isolation valve |
open |
6"-wi-f-2117/ sdv-3020a |
Sea water injection pump (PAT-3020A/B/C/D/E/F) discharge shutdown valve |
open |
12"-wi-f-2804/ 12" f2jfk |
Isolation valve Downstream of water injection swivel (TU-FAT-0818) to water injection riser No. 12 |
open |
pcv-3114 |
Choke valve in water injection line in the injection tree No. 31 |
closed |
xv-3102 |
Injection wing valve (IWV) downstream of choke valve in the injection tree No. 31 |
open |
xv-3101 |
Injection master valve downstream of choke valve in the injection tree No. 31 |
open |
xov-3107 |
Cross over valve on injection tree No. 31 |
closed |
aiv,aav |
Annulus insert and access valve on injection tree no. 31 |
closed |
The valve status for the other water injection tree Nos. 32,33,34,41,42,43 & 44 are the same as given above for tree No. 31 |
During the cold Start-up of the production wells, gas injection and water injection system the following inputs to the shutdown system may require to be overridden at the Shutdown Panel in the Central Control Room until steady operating conditions are established.refer also Doc. No. 1072-MI20-OPM1-10 for topside overrides :
Table Cold Start-up Overrides (Production Wells)
Switch |
Function |
Parent Equipment |
PALL-0030-2 |
Production riser No. 5 pressure Low Low |
TU-FAY-0030 |
PALL-0032-2 |
Production riser No. 3 pressure Low Low |
TU-FAY-0032 |
PALL-0031-2 |
Production riser No. 1 pressure Low Low |
TU-FAY-0031 |
Table Cold Start-up Overrides (Gas Lift)
Switch |
Function |
Parent Equipment |
PALL-2410-3 |
3rd stage booster gas compressor discharge line (Gas import/export line) |
Line No. 8"-PG-F1-1243 |
PALL-0230-2 |
Gas lift riser pressure Low Low |
TU-FAS-0230 |
Table Cold Start-up Overrides (Water Injection)
Switch |
Function |
Parent Equipment |
PALL-3020A/B/C/D/E/F-3 |
Sea water injection pump discharge pressure Low Low |
PAT-3020A/B/C/D/E/F |
Table Cold Start-up Procedure Following a Planned Shutdown (Production Wells)
Cold Start-up Procedure following a Planned Shutdown |
|||
STEP |
DESCRIPTION |
LOCAL |
CCR |
Confirm that all valves are aligned as per the Cold Start-up Valve Checklist and all overrides are on for production wells | |||
Confirm that all controllers are in automatic mode and are set to control the process at the process set point. | |||
Ensure that all control valves are at their process control set points and functional e.g., Instrument air regulators. | |||
Confirm that flare systems are operational | |||
The hydraulic power system is operational | |||
Confirm that H.P. production separator ready to receive well fluids | |||
Heating medium system is ready to supply heating fluid to inlet production heaters (HBG-1055A/B) and crude heater (HZZ-1115) | |||
Fill up the I.P. separator by diesel from diesel storage tank by hose connection | |||
Line up the IP separator to flow line circulation pump (PBE-1210) and start the flow line circulation pump. | |||
The diesel will fill the production riser and subsea flowlines upto the choke valve of production X-Mass Tree. The diesel will circulated back to I.P. separator via H.P. separator | |||
Open the inlet isolation valve of heating medium line to inlet production heater and crude heater and start heating of diesel | |||
Gradually the diesel become hot and the hot diesel will be circulated by flow line circulation pump to fill the enteir subsea production flow lines upto IP separator by hot diesel. This will prevent the enteir pipe network from wax deposit or coagulation of crude due to low temperature may be occure due to crude oil flushing in the subsea lines. | |||
When the hot diesel return temperature reaches around 40°C (maximum is 55°C) then stop the flow line circulation pump and isolate the flowline circulation system. Gradually open the choke valve from subsea control unit (SCU) and the crude from the well head will displace the hot diesel and move forward through the subsea production riser and finally at the H.P. production separator on topside. | |||
When the crude reaches at IP separator the normal line up of IP separator crude to electrostatic treater should be established. | |||
Observe the dry crude quality coming out from the crude/crude exchanger based on that the crude will send to either storage tanker at hull or off spec tank | |||
Remove the overrides listed in cold start-up overrides. | |||
When a stable operation is established, check the temperature and pressure in the subsea system from SCU and DCS | |||
Monitor all temperatures and pressures in the system. |
Table 18 Cold Start-up Procedure Following a Planned Shutdown (Gas LIft)
Cold Start-up Procedure following a Planned Shutdown |
|||
STEP |
DESCRIPTION |
LOCAL |
CCR |
Confirm that there is a requirement of gas lift to the production well. Check all valves are aligned as per the Cold Start-up Valve Checklist and all overrides are on for gas lift system |
|||
Confirm that all controllers are in automatic mode and are set to control the process at the process set point. |
|||
Ensure that all control valves are at their process control set points and functional e.g., Instrument air regulators. |
|||
Confirm that flare systems are operational |
|||
The hydraulic power system is operational |
|||
Confirm that 3rd stage Booster Compressors are in normal operation |
|||
Open the inlet isolation valve of FE-2425-1 |
|||
Observe the pressure developed upstream of choke valve through pressure transmitter in the gas lift line in production tree. If the required pressure is establish open the choke valve on gas lift line and observe the flow from venturi flowmeter upsrteam of choke valve. |
|||
Remove the overrides listed in cold start-up overrides. |
|||
When a stable operation is established, check the temperature, pressure and flow in the gas lift system from SCU and DCS |
|||
Monitor all temperatures and pressures in the system. |
Table 19 Cold Start-up Procedure Following a Planned Shutdown (Water Injection)
Cold Start-up Procedure following a Planned Shutdown |
|||
STEP |
DESCRIPTION |
LOCAL |
CCR |
Confirm that there is a requirement of water injection to the injection well. Check all valves are aligned as per the Cold Start-up Valve Checklist and all overrides are on for water injection system |
|||
Confirm that all controllers are in automatic mode and are set to control the process at the process set point. |
|||
Ensure that all control valves are at their process control set points and functional e.g., Instrument air regulators. |
|||
The hydraulic power system is operational |
|||
Confirm that sea water lift and treatment system are in normal operation. |
|||
Start the sea water injection pump (PAT-3020A/B/C/D/E/F) |
|||
Observe the pressure developed upstream of choke valve through pressure transmitters in the water injection tree. If the required pressure is establish open the choke valve on the water injection line and observe the flow from venturi flowmeter upsrteam of choke valve. |
|||
Remove the overrides listed in cold start-up overrides. |
|||
When a stable operation is established, check the temperature, pressure and flow in the gas lift system from SCU and DCS |
|||
Monitor all temperatures, pressures and flows in the system. |
The following hot start-up procedure details the steps to be taken to re-start the Subsea flow line and riser system facilities following a system trip.
The procedure assumes all the facilities listed below have been operating normally but have shutdown as a result of a system trip or by manual initiation.
The reason for the shutdown has been investigated and rectified and it is considered safe to re-start the system.
The pressures, temperatures and flow within the Subsea system are at or near normal conditions.
The following conditions are assumed to exist in executing this procedure: -
No Permits to Work are in force on any part of the system that may prohibit, or hinder, the safe start-up of the equipment.
The Fire and Gas Detection System, ESD Systems and control facilities within the CCR are operational including all alarms, trips and controllers.
It is assumed that in a short duration shutdown it is unlikely that spades or blinds would be moved, or drain and vent valves opened unless required to take corrective action on the cause of the shutdown. It is therefore unnecessary to recheck these items other than if they have been disturbed.
All vents, purge points and manual sample points are closed and blanked, or capped off, where necessary.
Communications have been established between all the personnel involved with the start-up procedure.
Safety/Briefing Meetings have been held with all directly concerned parties outlining the workscope and procedures.
The following Utility and Ancillary Systems are available:
Electrical Power Distribution
Instrument Air
Hydraulic power
Booster gas compressors
Sea water lift and treatment
During the Hot Start-up of the Subsea System there should be no requirement to have any input over-ride to the to the shutdown system.
Note-1: This procedure assumes that the temperature of the system has not dropped significantly so there is no requirements to hot oil circulation.
Table Hot Start-up Procedure Following a System Trip (Production Wells)
Hot Start-Up Procedure Following A System Trip |
|||
STEP |
DESCRIPTION |
LOCAL |
cCR |
Confirm that the valves are aligned as per Cold Start-up Valve checklist. | |||
Confirm that all controllers are in automatic mode and are set to control at the process set point. | |||
Start openning of the choke valve at the production tree | |||
Ensure that well fluids are flowing to the HP separator by observing the level increased in HP separator. | |||
Monitor all temperatures, pressures and flows in the system. | |||
Table 21 Hot Start-up Procedure Following a System Trip (Gas Lift)
Hot Start-Up Procedure Following A System Trip |
|||
STEP |
DESCRIPTION |
LOCAL |
cCR |
Confirm that the valves are aligned as per Cold Start-up Valve checklist. |
|||
Confirm that all controllers are in automatic mode and are set to control at the process set point. |
|||
Confirm that Booster Gas Compressor is running |
|||
Observed the required pressure developed upstream of the choke valve through pressure transmitter on the gas lift line up stream of choke valve |
|||
Once the pressure is established start openning of the choke valve at the production tree of gas lift line |
|||
Ensure that gas is flowing to the production well by observing the flow meter upstream of choke valve on the gas lift line. |
|||
Monitor all temperatures, pressures and flows in the system. |
Table 22 Hot Start-up Procedure Following a System Trip (Water Injection)
Hot Start-Up Procedure Following A System Trip |
|||
STEP |
DESCRIPTION |
LOCAL |
cCR |
Confirm that the valves are aligned as per Cold Start-up Valve checklist. |
|||
Confirm that all controllers are in automatic mode and are set to control at the process set point. |
|||
Start the sea water injection pump |
|||
Observed the required pressure developed upstream of the choke valve through pressure transmitter on the water injection line up stream of choke valve |
|||
Start openning of the choke valve at the injection tree |
|||
Ensure that water is injected to the injection well by observing the flow meter upstream of choke valve on the water injection line. |
|||
Monitor all temperatures, pressures and flows in the system. |
The normal operational conditions, together with alarm and trip set points for each item in the Subsea system are provided in section 6.0.
On a regular basis the field operator should conduct the following routine checks:
Check all pressures, temperatures and flows in the subsea system.
The following procedure details the steps to be taken to conduct a planned shutdown of the Subsea System as part of an overall shutdown of the FPSO process facilities in preparation for inspection / maintenance activities.
The following conditions are assumed to exist in executing this procedure: -
Safety / Briefing Meetings have been held with all directly concerned parties outlining the workscope and procedures.
Communications have been established between all persons involved in this procedure.
o No operations or Permits to Work are in force that may prohibit the shutdown of the system.
Table Planned Shutdown Procedure (Production Wells)
Planned Shutdown Procedure |
|||
STEP |
DESCRIPTION |
LOCAL |
CCR |
Ensure that the due to some reason reservoir fluid should not come to the topside for processing | |||
Close the individual choke valve of production tree | |||
Observe that the level is decreasing in the HP separator | |||
Close the inlet isolation valves of the HP separator before the Low Low liquid level achieved in the HP separator | |||
If long term shutdown is required then line up the IP separator to flow line circulation pump. Start the flow line circulation pump and fill the entire subsea flow line with hot oil taking from IP separator. See Doc. No. 1072-MI20-OPM1-12 for flow line operation details | |||
Table 24 Planned Shutdown Procedure (Gas LIft)
Planned Shutdown Procedure |
|||
STEP |
DESCRIPTION |
LOCAL |
CCR |
Ensure that there is no requirement of gas lift system. |
|||
Close the inlet isolation valve of FE-2425-1 on the gas lift line. Now all gas will be exported via gas import / export riser |
* |
||
Depressurised the gas lift header by opening the BDV-2425-4 to HP flare. |
|||
Observe that the gas pressure in the gas lift line decreasing by observing the pressure transmitter upstream of the choke valve in the gas lift line of the production tree. |
|||
Close the choke valve of the individual gas lift line in each production tree. |
|||
If some specific production well required to stop gas lift facility then close those specific choke valve of the gas lift line of the respective production tree and rest remain the same like normal operation. |
|||
Table 25 Planned Shutdown Procedure (Water Injection)
Planned Shutdown Procedure |
|||
STEP |
DESCRIPTION |
LOCAL |
CCR |
Ensure that the water injection need not required for some reason or maintenance work required to do for this system so water injection system required to shut down. |
|||
Stop the sea water injection pumps |
|||
Observe that the pressure is decreasing in the water injection line down stream of choke valve on the injection tree. |
|||
Close the SDV-3020A-19 on the discharge line of the injection pump. |
The following procedure details the steps to be taken to conduct an emergency controlled shutdown of the Gas Dehydration system.
Plant Status -The assumption is that an upset condition has occurred on the process or downstream facilities detected by the automatic shutdown systems, that requires the immediate controlled shutdown of the Gas Dehydration system by the ESD system. There should be no cause for intervention by operators.
Table 26 Emergency Controlled Shutdown Procedure
Emergency Controlled Shutdown Procedure |
|||
STEP |
DESCRIPTION |
LOCAL |
CCR |
The Subsea System is shutdown as part of the process shutdown systems onboard. As per the Cause & Effect listings for ASD, ESD & PSD. |
|||
After a Process trip occurs and the Facility has been confirmed as being in a safe condition, the operator in conjunction with the Control Room should confirm that outputs as listed in the C&E charts have effected as per the shutdown philosophy, prior to production restart. |
Table Alarm, Trip & Settings (Production Wells)
EQUIPMENT |
production well |
|||
TAG NO |
Alarm Type |
DESCRIPTION |
alarm/ TRIP set points |
PSV set points |
Production X-Mass Tree Pressure | ||||
SS-PT-1121 |
PAL |
Pressure Alarm Low -Tree No. 11 |
200 bara | |
SS-PT-1121 |
PAH |
Pressure Alarm High -Tree No. 11 |
250 bara | |
SS-PT-1122 |
PAL |
Pressure Alarm Low -Tree No. 11 |
200 bara | |
SS-PT-1122 |
PAH |
Pressure Alarm High -Tree No. 11 |
250 bara | |
SS-PT-1123 |
PAL |
Pressure Alarm Low -Tree No. 11 |
200 bara | |
SS-PT-1123 |
PAH |
Pressure Alarm High -Tree No. 11 |
250 bara | |
SS-PT-1124 |
PAL |
Pressure Alarm Low -Tree No. 11 |
200 bara | |
SS-PT-1124 |
PAH |
Pressure Alarm High -Tree No. 11 |
250 bara | |
SS-PT-1221 |
PAL |
Pressure Alarm Low -Tree No. 12 |
200 bara | |
SS-PT-1221 |
PAH |
Pressure Alarm High -Tree No. 12 |
250 bara | |
SS-PT-1222 |
PAL |
Pressure Alarm Low -Tree No. 12 |
200 bara | |
SS-PT-1222 |
PAH |
Pressure Alarm High -Tree No. 12 |
250 bara | |
SS-PT-1223 |
PAL |
Pressure Alarm Low -Tree No. 12 |
200 bara | |
SS-PT-1223 |
PAH |
Pressure Alarm High -Tree No. 12 |
250 bara | |
SS-PT-1224 |
PAL |
Pressure Alarm Low -Tree No. 12 |
200 bara | |
SS-PT-1224 |
PAH |
Pressure Alarm High -Tree No. 12 |
250 bara | |
SS-PT-1321 |
PAL |
Pressure Alarm Low -Tree No. 13 |
200 bara | |
SS-PT-1321 |
PAH |
Pressure Alarm High -Tree No. 13 |
250 bara | |
SS-PT-1322 |
PAL |
Pressure Alarm Low -Tree No. 13 |
200 bara | |
SS-PT-1322 |
PAH |
Pressure Alarm High -Tree No. 13 |
250 bara | |
SS-PT-1323 |
PAL |
Pressure Alarm Low -Tree No. 13 |
200 bara | |
SS-PT-1323 |
PAH |
Pressure Alarm High -Tree No. 13 |
250 bara | |
SS-PT-1324 |
PAL |
Pressure Alarm Low -Tree No. 13 |
200 bara | |
SS-PT-1324 |
PAH |
Pressure Alarm High -Tree No. 13 |
250 bara | |
SS-PT-1421 |
PAL |
Pressure Alarm Low -Tree No. 14 |
200 bara | |
SS-PT-1421 |
PAH |
Pressure Alarm High -Tree No. 14 |
250 bara | |
SS-PT-1422 |
PAL |
Pressure Alarm Low -Tree No. 14 |
200 bara | |
SS-PT-1422 |
PAH |
Pressure Alarm High -Tree No. 14 |
250 bara | |
SS-PT-1423 |
PAL |
Pressure Alarm Low -Tree No. 14 |
200 bara | |
SS-PT-1423 |
PAH |
Pressure Alarm High -Tree No. 14 |
250 bara | |
SS-PT-1424 |
PAL |
Pressure Alarm Low -Tree No. 14 |
200 bara | |
SS-PT-1424 |
PAH |
Pressure Alarm High -Tree No. 14 |
250 bara | |
SS-PT-1521 |
PAL |
Pressure Alarm Low -Tree No. 15 |
200 bara | |
SS-PT-1521 |
PAH |
Pressure Alarm High -Tree No. 15 |
250 bara | |
SS-PT-1522 |
PAL |
Pressure Alarm Low -Tree No. 15 |
200 bara | |
SS-PT-1522 |
PAH |
Pressure Alarm High -Tree No. 15 |
250 bara | |
SS-PT-1523 |
PAL |
Pressure Alarm Low -Tree No. 15 |
200 bara | |
SS-PT-1523 |
PAH |
Pressure Alarm High -Tree No. 15 |
250 bara | |
SS-PT-1524 |
PAL |
Pressure Alarm Low -Tree No. 15 |
200 bara | |
SS-PT-1524 |
PAH |
Pressure Alarm High -Tree No. 15 |
250 bara | |
SS-PT-1621 |
PAL |
Pressure Alarm Low -Tree No. 16 |
200 bara | |
SS-PT-1621 |
PAH |
Pressure Alarm High -Tree No. 16 |
250 bara | |
SS-PT-1622 |
PAL |
Pressure Alarm Low -Tree No. 16 |
200 bara | |
SS-PT-1622 |
PAH |
Pressure Alarm High -Tree No. 16 |
250 bara | |
SS-PT-1623 |
PAL |
Pressure Alarm Low -Tree No. 16 |
200 bara | |
SS-PT-1623 |
PAH |
Pressure Alarm High -Tree No. 16 |
250 bara | |
SS-PT-1624 |
PAL |
Pressure Alarm Low -Tree No. 16 |
200 bara | |
SS-PT-1624 |
PAH |
Pressure Alarm High -Tree No. 16 |
250 bara | |
SS-PT-1021 |
PAL |
Pressure Alarm Low -Production Riser No. 3 |
200 bara | |
SS-PT-1021 |
PAH |
Pressure Alarm High - Production Riser No. 3 |
250 bara | |
SS-PT-1022 |
PAL |
Pressure Alarm Low -Production Riser No. 1 |
200 bara | |
SS-PT-1022 |
PAH |
Pressure Alarm High - Production Riser No. 1 |
250 bara | |
SS-PT-2121 |
PAL |
Pressure Alarm Low -Tree No. 21 |
200 bara | |
SS-PT-2121 |
PAH |
Pressure Alarm High -Tree No. 21 |
250 bara | |
SS-PT-2122 |
PAL |
Pressure Alarm Low -Tree No. 21 |
200 bara | |
SS-PT-2122 |
PAH |
Pressure Alarm High -Tree No. 21 |
250 bara | |
SS-PT-2123 |
PAL |
Pressure Alarm Low -Tree No. 21 |
200 bara | |
SS-PT-2123 |
PAH |
Pressure Alarm High -Tree No. 21 |
250 bara | |
SS-PT-2124 |
PAL |
Pressure Alarm Low -Tree No. 21 |
200 bara | |
SS-PT-2124 |
PAH |
Pressure Alarm High -Tree No. 21 |
250 bara | |
SS-PT-2221 |
PAL |
Pressure Alarm Low -Tree No. 22 |
200 bara | |
SS-PT-2221 |
PAH |
Pressure Alarm High -Tree No. 22 |
250 bara | |
SS-PT-2222 |
PAL |
Pressure Alarm Low -Tree No. 22 |
200 bara | |
SS-PT-2222 |
PAH |
Pressure Alarm High -Tree No. 22 |
250 bara | |
SS-PT-2223 |
PAL |
Pressure Alarm Low -Tree No. 22 |
200 bara | |
SS-PT-2223 |
PAH |
Pressure Alarm High -Tree No. 22 |
250 bara | |
SS-PT-2224 |
PAL |
Pressure Alarm Low -Tree No. 22 |
200 bara | |
SS-PT-2224 |
PAH |
Pressure Alarm High -Tree No. 22 |
250 bara | |
SS-PT-2321 |
PAL |
Pressure Alarm Low -Tree No. 23 |
200 bara | |
SS-PT-2321 |
PAH |
Pressure Alarm High -Tree No. 23 |
250 bara | |
SS-PT-2322 |
PAL |
Pressure Alarm Low -Tree No. 23 |
200 bara | |
SS-PT-2322 |
PAH |
Pressure Alarm High -Tree No. 23 |
250 bara | |
SS-PT-2323 |
PAL |
Pressure Alarm Low -Tree No. 23 |
200 bara | |
SS-PT-2323 |
PAH |
Pressure Alarm High -Tree No. 23 |
250 bara | |
SS-PT-2324 |
PAL |
Pressure Alarm Low -Tree No. 23 |
200 bara | |
SS-PT-2324 |
PAH |
Pressure Alarm High -Tree No. 23 |
250 bara | |
SS-PT-2421 |
PAL |
Pressure Alarm Low -Tree No. 24 |
200 bara | |
SS-PT-2421 |
PAH |
Pressure Alarm High -Tree No. 24 |
250 bara | |
SS-PT-2422 |
PAL |
Pressure Alarm Low -Tree No. 24 |
200 bara | |
SS-PT-2422 |
PAH |
Pressure Alarm High -Tree No. 24 |
250 bara | |
SS-PT-2423 |
PAL |
Pressure Alarm Low -Tree No. 24 |
200 bara | |
SS-PT-2423 |
PAH |
Pressure Alarm High -Tree No. 24 |
250 bara | |
SS-PT-2424 |
PAL |
Pressure Alarm Low -Tree No. 24 |
200 bara | |
SS-PT-2424 |
PAH |
Pressure Alarm High -Tree No. 24 |
250 bara | |
SS-PT-2521 |
PAL |
Pressure Alarm Low -Tree No. 25 |
200 bara | |
SS-PT-2521 |
PAH |
Pressure Alarm High -Tree No. 25 |
250 bara | |
SS-PT-2522 |
PAL |
Pressure Alarm Low -Tree No. 25 |
200 bara |
|
SS-PT-2522 |
PAH |
Pressure Alarm High -Tree No. 25 |
250 bara | |
SS-PT-2523 |
PAL |
Pressure Alarm Low -Tree No. 25 |
200 bara | |
SS-PT-2523 |
PAH |
Pressure Alarm High -Tree No. 25 |
250 bara | |
SS-PT-2524 |
PAL |
Pressure Alarm Low -Tree No. 25 |
200 bara | |
SS-PT-2524 |
PAH |
Pressure Alarm High -Tree No. 25 |
250 bara | |
SS-PT-2621 |
PAL |
Pressure Alarm Low -Tree No. 26 |
200 bara | |
SS-PT-2621 |
PAH |
Pressure Alarm High -Tree No. 26 |
250 bara | |
SS-PT-2622 |
PAL |
Pressure Alarm Low -Tree No. 26 |
200 bara | |
SS-PT-2622 |
PAH |
Pressure Alarm High -Tree No. 26 |
250 bara | |
SS-PT-2623 |
PAL |
Pressure Alarm Low -Tree No. 26 |
200 bara | |
SS-PT-2623 |
PAH |
Pressure Alarm High -Tree No. 26 |
250 bara | |
SS-PT-2624 |
PAL |
Pressure Alarm Low -Tree No. 26 |
200 bara | |
SS-PT-2624 |
PAH |
Pressure Alarm High -Tree No. 26 |
250 bara | |
SS-PT-2021 |
PAL |
Pressure Alarm Low -Production Riser No. 5 |
200 bara | |
SS-PT-2021 |
PAH |
Pressure Alarm High - Production Riser No. 5 |
250 bara | |
SS-PT-2022 |
PAL |
Pressure Alarm Low -Production Riser No. 3 |
200 bara | |
SS-PT-2022 |
PAH |
Pressure Alarm High - Production Riser No. 3 |
250 bara | |
TU-PI-0031-2 |
PALL |
Pressure Alarm Low Low - production riser No. 1 |
(HOLD) | |
TU-PI-0031-2 |
PAHH |
Pressure Alarm High High - production riser No. 1 |
(HOLD) | |
TU-PI-0032-2 |
PALL |
Pressure Alarm Low Low - production riser No. 3 |
(HOLD) | |
TU-PI-0032-2 |
PAHH |
Pressure Alarm High High - production riser No. 3 |
(HOLD) | |
TU-PI-0030-2 |
PALL |
Pressure Alarm Low Low - production riser No. 5 |
(HOLD) | |
TU-PI-0030-2 |
PAHH |
Pressure Alarm High High - production riser No. 5 |
(HOLD) | |
TU-PI-0810-1 |
PAH |
Pressure Alarm High-Swivel Manifold Header (20"-PF-F1-5618) |
(HOLD) | |
TU-PI-0810-2 |
PAH |
Pressure Alarm High-Swivel Manifold Header (20"-PF-F1-5618) |
(HOLD) | |
TU-PI-0811-1 |
PAH |
Pressure Alarm High-Swivel Manifold Header (20"-PF-F1-5618) |
(HOLD) | |
TU-PI-0812-1 |
PAH |
Pressure Alarm High-Swivel Manifold Header (20"-PF-F1-5618) |
(HOLD) | |
Production X-Mass Tree Temperature | ||||
SS-TT-1121 |
TAL |
Temperature Alarm Low -Tree No. 11 |
50°C | |
SS-TT-1121 |
TAH |
Temperature Alarm High -Tree No. 11 |
80°C | |
SS-TT-1122 |
TAL |
Temperature Alarm Low -Tree No. 11 |
50°C | |
SS-TT-1122 |
TAH |
Temperature Alarm High -Tree No. 11 |
80°C | |
SS-TT-1123 |
TAL |
Temperature Alarm Low -Tree No. 11 |
50°C | |
SS-TT-1123 |
TAH |
Temperature Alarm High -Tree No. 11 |
80°C | |
SS-TT-1124 |
TAL |
Temperature Alarm Low -Tree No. 11 |
50°C | |
SS-TT-1124 |
TAH |
Temperature Alarm High -Tree No. 11 |
80°C | |
SS-TT-1221 |
TAL |
Temperature Alarm Low -Tree No. 12 |
50°C | |
SS-TT-1221 |
TAH |
Temperature Alarm High -Tree No. 12 |
80°C | |
SS-TT-1222 |
TAL |
Temperature Alarm Low -Tree No. 12 |
50°C | |
SS-TT-1222 |
TAH |
Temperature Alarm High -Tree No. 12 |
80°C | |
SS-TT-1223 |
TAL |
Temperature Alarm Low -Tree No. 12 |
50°C | |
SS-TT-1223 |
TAH |
Temperature Alarm High -Tree No. 12 |
80°C | |
SS-TT-1224 |
TAL |
Temperature Alarm Low -Tree No. 12 |
50°C | |
SS-TT-1224 |
TAH |
Temperature Alarm High -Tree No. 12 |
80°C | |
SS-TT-1321 |
TAL |
Temperature Alarm Low -Tree No. 13 |
50°C | |
SS-TT-1321 |
TAH |
Temperature Alarm High -Tree No. 13 |
80°C | |
SS-TT-1322 |
TAL |
Temperature Alarm Low -Tree No. 13 |
50°C | |
SS-TT-1322 |
TAH |
Temperature Alarm High -Tree No. 13 |
80°C | |
SS-TT-1323 |
TAL |
Temperature Alarm Low -Tree No. 13 |
50°C | |
SS-TT-1323 |
TAH |
Temperature Alarm High -Tree No. 13 |
80°C | |
SS-TT-1324 |
TAL |
Temperature Alarm Low -Tree No. 13 |
50°C | |
SS-TT-1324 |
TAH |
Temperature Alarm High -Tree No. 13 |
80°C | |
SS-TT-1421 |
TAL |
Temperature Alarm Low -Tree No. 14 |
50°C | |
SS-TT-1421 |
TAH |
Temperature Alarm High -Tree No. 14 |
80°C | |
SS-TT-1422 |
TAL |
Temperature Alarm Low -Tree No. 14 |
50°C | |
SS-TT-1422 |
TAH |
Temperature Alarm High -Tree No. 14 |
80°C | |
SS-TT-1423 |
TAL |
Temperature Alarm Low -Tree No. 14 |
50°C | |
SS-TT-1423 |
TAH |
Temperature Alarm High -Tree No. 14 |
80°C | |
SS-TT-1424 |
TAL |
Temperature Alarm Low -Tree No. 14 |
50°C | |
SS-TT-1424 |
TAH |
Temperature Alarm High -Tree No. 14 |
80°C | |
SS-TT-1521 |
TAL |
Temperature Alarm Low -Tree No. 15 |
50°C | |
SS-TT-1521 |
TAH |
Temperature Alarm High -Tree No. 15 |
80°C | |
SS-TT-1522 |
TAL |
Temperature Alarm Low -Tree No. 15 |
50°C | |
SS-TT-1522 |
TAH |
Temperature Alarm High -Tree No. 15 |
80°C | |
SS-TT-1523 |
TAL |
Temperature Alarm Low -Tree No. 15 |
50°C | |
SS-TT-1523 |
TAH |
Temperature Alarm High -Tree No. 15 |
80°C | |
SS-TT-1524 |
TAL |
Temperature Alarm Low -Tree No. 15 |
50°C | |
SS-TT-1524 |
TAH |
Temperature Alarm High -Tree No. 15 |
80°C | |
SS-TT-1621 |
TAL |
Temperature Alarm Low -Tree No. 16 |
50°C | |
SS-TT-1621 |
TAH |
Temperature Alarm High -Tree No. 16 |
80°C | |
SS-TT-1622 |
TAL |
Temperature Alarm Low -Tree No. 16 |
50°C | |
SS-TT-1622 |
TAH |
Temperature Alarm High -Tree No. 16 |
80°C | |
SS-TT-1623 |
TAL |
Temperature Alarm Low -Tree No. 16 |
50°C | |
SS-TT-1623 |
TAH |
Temperature Alarm High -Tree No. 16 |
80°C | |
SS-TT-1624 |
TAL |
Temperature Alarm Low -Tree No. 16 |
50°C | |
SS-TT-1624 |
TAH |
Temperature Alarm High -Tree No. 16 |
80°C | |
SS-TT-1021 |
TAL |
Temperature Alarm Low -Production Riser No. 3 (DCN) |
50°C | |
SS-TT-1021 |
TAH |
Temperature Alarm High - Production Riser No. 3 (DCN) |
80°C | |
SS-TT-1022 |
TAL |
Temperature Alarm Low -Production Riser No. 1 |
50°C | |
SS-TT-1022 |
TAH |
Temperature Alarm High - Production Riser No. 1 |
80°C | |
SS-TT-2121 |
TAL |
Temperature Alarm Low -Tree No. 21 |
50°C | |
SS-TT-2121 |
TAH |
Temperature Alarm High -Tree No. 21 |
80°C | |
SS-TT-2122 |
TAL |
Temperature Alarm Low -Tree No. 21 |
50°C | |
SS-TT-2122 |
TAH |
Temperature Alarm High -Tree No. 21 |
80°C | |
SS-TT-2123 |
TAL |
Temperature Alarm Low -Tree No. 21 |
50°C | |
SS-TT-2123 |
TAH |
Temperature Alarm High -Tree No. 21 |
80°C | |
SS-TT-2124 |
TAL |
Temperature Alarm Low -Tree No. 21 |
50°C | |
SS-TT-2124 |
TAH |
Temperature Alarm High -Tree No. 21 |
80°C | |
SS-TT-2221 |
TAL |
Temperature Alarm Low -Tree No. 22 |
50°C | |
SS-TT-2221 |
TAH |
Temperature Alarm High -Tree No. 22 |
80°C | |
SS-TT-2222 |
TAL |
Temperature Alarm Low -Tree No. 22 |
50°C | |
SS-TT-2222 |
TAH |
Temperature Alarm High -Tree No. 22 |
80°C | |
SS-TT-2223 |
TAL |
Temperature Alarm Low -Tree No. 22 |
50°C | |
SS-TT-2223 |
TAH |
Temperature Alarm High -Tree No. 22 |
80°C | |
SS-TT-2224 |
TAL |
Temperature Alarm Low -Tree No. 22 |
50°C | |
SS-TT-2224 |
TAH |
Temperature Alarm High -Tree No. 22 |
80°C | |
SS-TT-2321 |
TAL |
Temperature Alarm Low -Tree No. 23 |
50°C | |
SS-TT-2321 |
TAH |
Temperature Alarm High -Tree No. 23 |
80°C | |
SS-TT-2322 |
TAL |
Temperature Alarm Low -Tree No. 23 |
50°C | |
SS-TT-2322 |
TAH |
Temperature Alarm High -Tree No. 23 |
80°C | |
SS-TT-2323 |
TAL |
Temperature Alarm Low -Tree No. 23 |
50°C | |
SS-TT-2323 |
TAH |
Temperature Alarm High -Tree No. 23 |
80°C | |
SS-TT-2324 |
TAL |
Temperature Alarm Low -Tree No. 23 |
50°C | |
SS-TT-2324 |
TAH |
Temperature Alarm High -Tree No. 23 |
80°C | |
SS-TT-2421 |
TAL |
Temperature Alarm Low -Tree No. 24 |
50°C | |
SS-TT-2421 |
TAH |
Temperature Alarm High -Tree No. 24 |
80°C | |
SS-TT-2422 |
TAL |
Temperature Alarm Low -Tree No. 24 |
50°C | |
SS-TT-2422 |
TAH |
Temperature Alarm High -Tree No. 24 |
80°C | |
SS-TT-2423 |
TAL |
Temperature Alarm Low -Tree No. 24 |
50°C | |
SS-TT-2423 |
TAH |
Temperature Alarm High -Tree No. 24 |
80°C | |
SS-TT-2424 |
TAL |
Temperature Alarm Low -Tree No. 24 |
50°C | |
SS-TT-2424 |
TAH |
Temperature Alarm High -Tree No. 24 |
80°C | |
SS-TT-2521 |
TAL |
Temperature Alarm Low -Tree No. 25 |
50°C | |
SS-TT-2521 |
TAH |
Temperature Alarm High -Tree No. 25 |
80°C | |
SS-TT-2522 |
TAL |
Temperature Alarm Low -Tree No. 25 |
50°C | |
SS-TT-2522 |
TAH |
Temperature Alarm High -Tree No. 25 |
80°C | |
SS-TT-2523 |
TAL |
Temperature Alarm Low -Tree No. 25 |
50°C | |
SS-TT-2523 |
TAH |
Temperature Alarm High -Tree No. 25 |
80°C | |
SS-TT-2524 |
TAL |
Temperature Alarm Low -Tree No. 25 |
50°C | |
SS-TT-2524 |
TAH |
Temperature Alarm High -Tree No. 25 |
80°C | |
SS-TT-2621 |
TAL |
Temperature Alarm Low -Tree No. 26 |
50°C | |
SS-TT-2621 |
TAH |
Temperature Alarm High -Tree No. 26 |
80°C | |
SS-TT-2622 |
TAL |
Temperature Alarm Low -Tree No. 26 |
50°C | |
SS-TT-2622 |
TAH |
Temperature Alarm High -Tree No. 26 |
80°C | |
SS-TT-2623 |
TAL |
Temperature Alarm Low -Tree No. 26 |
50°C | |
SS-TT-2623 |
TAH |
Temperature Alarm High -Tree No. 26 |
80°C | |
SS-TT-2624 |
TAL |
Temperature Alarm Low -Tree No. 26 |
50°C | |
SS-TT-2624 |
TAH |
Temperature Alarm High -Tree No. 26 |
80°C | |
SS-TT-2021 |
TAL |
Temperature Alarm Low -Production Riser No. 5 |
50°C | |
SS-TT-2021 |
TAH |
Temperature Alarm High - Production Riser No. 5 |
80°C | |
SS-TT-2022 |
TAL |
Temperature Alarm Low -Production Riser No. 3 (DCS) |
50°C | |
SS-TT-2022 |
TAH |
Temperature Alarm High - Production Riser No. 3 (DCS) |
80°C | |
TU-TI-0031-4 |
TAL |
Temperature Alarm Low - production riser No. 1 |
(HOLD) | |
TU-TI-0031-4 |
TAH |
Temperature Alarm High - production riser No. 1 |
(HOLD) | |
TU-TI-0032-4 |
TAL |
Temperature Alarm Low - production riser No. 3 |
(HOLD) | |
TU-TI-0032-4 |
TAH |
Temperature Alarm High - production riser No. 3 |
(HOLD) | |
TU-TI-0030-4 |
TAL |
Temperature Alarm Low - production riser No. 5 |
(HOLD) | |
TU-TI-0030-4 |
TAH |
Temperature Alarm High - production riser No. 5 |
(HOLD) |
Table Alarm, Trip & Settings (Gas Lift)
EQUIPMENT |
production Tree |
|||
TAG NO |
Alarm Type |
DESCRIPTION |
alarm/ TRIP set points |
PSV set points |
Production X-Mass Tree gas Lift Pressure | ||||
SS-PT-1125 |
PAL |
Pressure Alarm Low -Tree No. 11 |
200 bara | |
SS-PT-1125 |
PAH |
Pressure Alarm High -Tree No. 11 |
250 bara | |
SS-PT-1126 |
PAL |
Pressure Alarm Low -Tree No. 11 |
200 bara | |
SS-PT-1126 |
PAH |
Pressure Alarm High -Tree No. 11 |
250 bara | |
SS-PT-1225 |
PAL |
Pressure Alarm Low -Tree No. 12 |
200 bara | |
SS-PT-1225 |
PAH |
Pressure Alarm High -Tree No. 12 |
250 bara | |
SS-PT-1226 |
PAL |
Pressure Alarm Low -Tree No. 12 |
200 bara | |
SS-PT-1226 |
PAH |
Pressure Alarm High -Tree No. 12 |
250 bara | |
SS-PT-1325 |
PAL |
Pressure Alarm Low -Tree No. 13 |
200 bara | |
SS-PT-1325 |
PAH |
Pressure Alarm High -Tree No. 13 |
250 bara | |
SS-PT-1326 |
PAL |
Pressure Alarm Low -Tree No. 13 |
200 bara | |
SS-PT-1326 |
PAH |
Pressure Alarm High -Tree No. 13 |
250 bara | |
SS-PT-1425 |
PAL |
Pressure Alarm Low -Tree No. 14 |
200 bara | |
SS-PT-1425 |
PAH |
Pressure Alarm High -Tree No. 14 |
250 bara | |
SS-PT-1426 |
PAL |
Pressure Alarm Low -Tree No. 14 |
200 bara | |
SS-PT-1426 |
PAH |
Pressure Alarm High -Tree No. 14 |
250 bara | |
SS-PT-1525 |
PAL |
Pressure Alarm Low -Tree No. 15 |
200 bara | |
SS-PT-1525 |
PAH |
Pressure Alarm High -Tree No. 15 |
250 bara | |
SS-PT-1526 |
PAL |
Pressure Alarm Low -Tree No. 15 |
200 bara | |
SS-PT-1526 |
PAH |
Pressure Alarm High -Tree No. 15 |
250 bara | |
SS-PT-1625 |
PAL |
Pressure Alarm Low -Tree No. 16 |
200 bara | |
SS-PT-1625 |
PAH |
Pressure Alarm High -Tree No. 16 |
250 bara | |
SS-PT-1626 |
PAL |
Pressure Alarm Low -Tree No. 16 |
200 bara | |
SS-PT-1626 |
PAH |
Pressure Alarm High -Tree No. 16 |
250 bara | |
SS-PT-1023 |
PAL |
Pressure Alarm Low -Gas lift header DCN |
200 bara | |
SS-PT-1023 |
PAH |
Pressure Alarm High - Gas lift header DCN |
250 bara | |
SS-PT-2125 |
PAL |
Pressure Alarm Low -Tree No. 21 |
200 bara | |
SS-PT-2125 |
PAH |
Pressure Alarm High -Tree No. 21 |
250 bara | |
SS-PT-2126 |
PAL |
Pressure Alarm Low -Tree No. 21 |
200 bara | |
SS-PT-2126 |
PAH |
Pressure Alarm High -Tree No. 21 |
250 bara | |
SS-PT-2225 |
PAL |
Pressure Alarm Low -Tree No. 22 |
200 bara | |
SS-PT-2225 |
PAH |
Pressure Alarm High -Tree No. 22 |
250 bara | |
SS-PT-2226 |
PAL |
Pressure Alarm Low -Tree No. 22 |
200 bara | |
SS-PT-2226 |
PAH |
Pressure Alarm High -Tree No. 22 |
250 bara | |
SS-PT-2325 |
PAL |
Pressure Alarm Low -Tree No. 23 |
200 bara | |
SS-PT-2325 |
PAH |
Pressure Alarm High -Tree No. 23 |
250 bara | |
SS-PT-2326 |
PAL |
Pressure Alarm Low -Tree No. 23 |
200 bara | |
SS-PT-2326 |
PAH |
Pressure Alarm High -Tree No. 23 |
250 bara | |
SS-PT-2425 |
PAL |
Pressure Alarm Low -Tree No. 24 |
200 bara | |
SS-PT-2425 |
PAH |
Pressure Alarm High -Tree No. 24 |
250 bara | |
SS-PT-2426 |
PAL |
Pressure Alarm Low -Tree No. 24 |
200 bara | |
SS-PT-2426 |
PAH |
Pressure Alarm High -Tree No. 24 |
250 bara | |
SS-PT-2525 |
PAL |
Pressure Alarm Low -Tree No. 25 |
200 bara | |
SS-PT-2525 |
PAH |
Pressure Alarm High -Tree No. 25 |
250 bara | |
SS-PT-2526 |
PAL |
Pressure Alarm Low -Tree No. 25 |
200 bara | |
SS-PT-2526 |
PAH |
Pressure Alarm High -Tree No. 25 |
250 bara | |
SS-PT-2625 |
PAL |
Pressure Alarm Low -Tree No. 26 |
200 bara | |
SS-PT-2625 |
PAH |
Pressure Alarm High -Tree No. 26 |
250 bara | |
SS-PT-2626 |
PAL |
Pressure Alarm Low -Tree No. 26 |
200 bara | |
SS-PT-2626 |
PAH |
Pressure Alarm High -Tree No. 26 |
250 bara | |
SS-TT-2023 |
PAH |
Pressure Alarm High -Gas lift header at DCS |
250 bara | |
SS-TT-2023 |
PAL |
Pressure Alarm Low -Gas lift header at DCS |
200 bara | |
TU-PI-0230-2 |
PALL |
Pressure Alarm Low Low - gas lift riser No. 4 |
(HOLD) | |
TU-PI-0230-2 |
PAHH |
Pressure Alarm High High - gas lift riser No. 4 |
(HOLD) | |
10M-PI-2410-3 |
PALL |
Pressure Alarm Low Low - gas lift header |
(HOLD) | |
Production X-Mass Tree gas Lift Temperature | ||||
SS-TT-1125 |
TAL |
Temperature Alarm Low -Tree No. 11 |
50°C | |
SS-TT-1125 |
TAH |
Temperature Alarm High -Tree No. 11 |
80°C | |
SS-TT-1126 |
TAL |
Temperature Alarm Low -Tree No. 11 |
50°C | |
SS-TT-1126 |
TAH |
Temperature Alarm High -Tree No. 11 |
80°C | |
SS-TT-1225 |
TAL |
Temperature Alarm Low -Tree No. 12 |
50°C | |
SS-TT-1225 |
TAH |
Temperature Alarm High -Tree No. 12 |
80°C | |
SS-TT-1226 |
TAL |
Temperature Alarm Low -Tree No. 12 |
50°C | |
SS-TT-1226 |
TAH |
Temperature Alarm High -Tree No. 12 |
80°C | |
SS-TT-1325 |
TAL |
Temperature Alarm Low -Tree No. 13 |
50°C | |
SS-TT-1325 |
TAH |
Temperature Alarm High -Tree No. 13 |
80°C | |
SS-TT-1326 |
TAL |
Temperature Alarm Low -Tree No. 13 |
50°C | |
SS-TT-1326 |
TAH |
Temperature Alarm High -Tree No. 13 |
80°C | |
SS-TT-1425 |
TAL |
Temperature Alarm Low -Tree No. 14 |
50°C | |
SS-TT-1425 |
TAH |
Temperature Alarm High -Tree No. 14 |
80°C | |
SS-TT-1426 |
TAL |
Temperature Alarm Low -Tree No. 14 |
50°C | |
SS-TT-1426 |
TAH |
Temperature Alarm High -Tree No. 14 |
80°C | |
SS-TT-1525 |
TAL |
Temperature Alarm Low -Tree No. 15 |
50°C | |
SS-TT-1525 |
TAH |
Temperature Alarm High -Tree No. 15 |
80°C | |
SS-TT-1526 |
TAL |
Temperature Alarm Low -Tree No. 15 |
50°C | |
SS-TT-1526 |
TAH |
Temperature Alarm High -Tree No. 15 |
80°C | |
SS-TT-1625 |
TAL |
Temperature Alarm Low -Tree No. 16 |
50°C | |
SS-TT-1625 |
TAH |
Temperature Alarm High -Tree No. 16 |
80°C | |
SS-TT-1626 |
TAL |
Temperature Alarm Low -Tree No. 16 |
50°C | |
SS-TT-1626 |
TAH |
Temperature Alarm High -Tree No. 16 |
80°C | |
SS-TT-1023 |
TAL |
Temperature Alarm Low -Gas lift header DCN |
50°C | |
SS-TT-1023 |
TAH |
Temperature Alarm High - Gas lift header DCN |
80°C | |
SS-TT-2125 |
TAL |
Temperature Alarm Low -Tree No. 21 |
50°C | |
SS-TT-2125 |
TAH |
Temperature Alarm High -Tree No. 21 |
80°C | |
SS-TT-2126 |
TAL |
Temperature Alarm Low -Tree No. 21 |
50°C | |
SS-TT-2126 |
TAH |
Temperature Alarm High -Tree No. 21 |
80°C | |
SS-TT-2225 |
TAL |
Temperature Alarm Low -Tree No. 22 |
50°C | |
SS-TT-2225 |
TAH |
Temperature Alarm High -Tree No. 22 |
80°C | |
SS-TT-2226 |
TAL |
Temperature Alarm Low -Tree No. 22 |
50°C | |
SS-TT-2226 |
TAH |
Temperature Alarm High -Tree No. 22 |
80°C | |
SS-TT-2325 |
TAL |
Temperature Alarm Low -Tree No. 23 |
50°C | |
SS-TT-2325 |
TAH |
Temperature Alarm High -Tree No. 23 |
80°C | |
SS-TT-2326 |
TAL |
Temperature Alarm Low -Tree No. 23 |
50°C | |
SS-TT-2326 |
TAH |
Temperature Alarm High -Tree No. 23 |
80°C | |
SS-TT-2425 |
TAL |
Temperature Alarm Low -Tree No. 24 |
50°C | |
SS-TT-2425 |
TAH |
Temperature Alarm High -Tree No. 24 |
80°C | |
SS-TT-2426 |
TAL |
Temperature Alarm Low -Tree No. 24 |
50°C | |
SS-TT-2426 |
TAH |
Temperature Alarm High -Tree No. 24 |
80°C | |
SS-TT-2525 |
TAL |
Temperature Alarm Low -Tree No. 25 |
50°C | |
SS-TT-2525 |
TAH |
Temperature Alarm High -Tree No. 25 |
80°C | |
SS-TT-2526 |
TAL |
Temperature Alarm Low -Tree No. 25 |
50°C | |
SS-TT-2526 |
TAH |
Temperature Alarm High -Tree No. 25 |
80°C | |
SS-TT-2625 |
TAL |
Temperature Alarm Low -Tree No. 26 |
50°C | |
SS-TT-2625 |
TAH |
Temperature Alarm High -Tree No. 26 |
80°C | |
SS-TT-2626 |
TAL |
Temperature Alarm Low -Tree No. 26 |
50°C | |
SS-TT-2626 |
TAH |
Temperature Alarm High -Tree No. 26 |
80°C | |
SS-TT-2023 |
TAL |
Temperature Alarm High -Gas lift header at DCS |
50°C | |
SS-TT-2023 |
TAH |
Temperature Alarm Low -Gas lift header at DCS |
80°C |
Table Alarm, Trip & Settings (Water Injection)
EQUIPMENT |
water injection Tree |
|||
TAG NO |
Alarm Type |
DESCRIPTION |
alarm/ TRIP set points |
PSV set points |
Water Injection X-Mass Tree Pressure | ||||
09M-PI-3020A-3 |
PALL |
Pressure Alarm Low Low-seawater injection pump discharge |
(HOLD) | |
09M-PI-3020A-3 |
PAHH |
Pressure Alarm High High-seawater injection pump discharge |
(HOLD) | |
SS-PT-3121 |
PAL |
Pressure Alarm Low -Tree No. 31 |
250 bara | |
SS-PT-3121 |
PAH |
Pressure Alarm High -Tree No. 31 |
300 bara | |
SS-PT-3122 |
PAL |
Pressure Alarm Low -Tree No. 31 |
250 bara | |
SS-PT-3122 |
PAH |
Pressure Alarm High -Tree No. 31 |
300 bara | |
SS-PT-3123 |
PAL |
Pressure Alarm Low -Tree No. 31 |
250 bara | |
SS-PT-3123 |
PAH |
Pressure Alarm High -Tree No. 31 |
300 bara | |
SS-PT-3124 |
PAL |
Pressure Alarm Low -Tree No. 31 |
250 bara | |
SS-PT-3124 |
PAH |
Pressure Alarm High -Tree No. 31 |
300 bara | |
SS-PT-3221 |
PAL |
Pressure Alarm Low -Tree No. 32 |
250 bara | |
SS-PT-3221 |
PAH |
Pressure Alarm High -Tree No. 32 |
300 bara | |
SS-PT-3222 |
PAL |
Pressure Alarm Low -Tree No. 32 |
250 bara | |
SS-PT-3222 |
PAH |
Pressure Alarm High -Tree No. 32 |
300 bara | |
SS-PT-3223 |
PAL |
Pressure Alarm Low -Tree No. 32 |
250 bara | |
SS-PT-3223 |
PAH |
Pressure Alarm High -Tree No. 32 |
300 bara | |
SS-PT-3224 |
PAL |
Pressure Alarm Low -Tree No. 32 |
250 bara | |
SS-PT-3224 |
PAH |
Pressure Alarm High -Tree No. 32 |
300 bara | |
SS-PT-3321 |
PAL |
Pressure Alarm Low -Tree No. 33 |
250 bara | |
SS-PT-3321 |
PAH |
Pressure Alarm High -Tree No. 33 |
300 bara | |
SS-PT-3322 |
PAL |
Pressure Alarm Low -Tree No. 33 |
250 bara | |
SS-PT-3322 |
PAH |
Pressure Alarm High -Tree No. 33 |
300 bara | |
SS-PT-3323 |
PAL |
Pressure Alarm Low -Tree No. 33 |
250 bara | |
SS-PT-3323 |
PAH |
Pressure Alarm High -Tree No. 33 |
300 bara | |
SS-PT-3324 |
PAL |
Pressure Alarm Low -Tree No. 33 |
250 bara | |
SS-PT-3324 |
PAH |
Pressure Alarm High -Tree No. 33 |
300 bara | |
SS-PT-3421 |
PAL |
Pressure Alarm Low -Tree No. 34 |
250 bara | |
SS-PT-3421 |
PAH |
Pressure Alarm High -Tree No. 34 |
300 bara | |
SS-PT-3422 |
PAL |
Pressure Alarm Low -Tree No. 34 |
250 bara | |
SS-PT-3422 |
PAH |
Pressure Alarm High -Tree No. 34 |
300 bara | |
SS-PT-3423 |
PAL |
Pressure Alarm Low -Tree No. 34 |
250 bara | |
SS-PT-3423 |
PAH |
Pressure Alarm High -Tree No. 34 |
300 bara | |
SS-PT-3424 |
PAL |
Pressure Alarm Low -Tree No. 34 |
250 bara | |
SS-PT-3424 |
PAH |
Pressure Alarm High -Tree No. 34 |
300 bara | |
SS-PT-4121 |
PAL |
Pressure Alarm Low -Tree No. 41 |
250 bara | |
SS-PT-4121 |
PAH |
Pressure Alarm High -Tree No. 41 |
300 bara | |
SS-PT-4122 |
PAL |
Pressure Alarm Low -Tree No. 41 |
250 bara | |
SS-PT-4122 |
PAH |
Pressure Alarm High -Tree No. 41 |
300 bara | |
SS-PT-4123 |
PAL |
Pressure Alarm Low -Tree No. 41 |
250 bara | |
SS-PT-4123 |
PAH |
Pressure Alarm High -Tree No. 41 |
300 bara | |
SS-PT-4124 |
PAL |
Pressure Alarm Low -Tree No. 41 |
250 bara | |
SS-PT-4124 |
PAH |
Pressure Alarm High -Tree No. 41 |
300 bara | |
SS-PT-4221 |
PAL |
Pressure Alarm Low -Tree No. 42 |
250 bara | |
SS-PT-4221 |
PAH |
Pressure Alarm High -Tree No. 42 |
300 bara | |
SS-PT-4222 |
PAL |
Pressure Alarm Low -Tree No. 42 |
250 bara | |
SS-PT-4222 |
PAH |
Pressure Alarm High -Tree No. 42 |
300 bara | |
SS-PT-4223 |
PAL |
Pressure Alarm Low -Tree No. 42 |
250 bara | |
SS-PT-4223 |
PAH |
Pressure Alarm High -Tree No. 42 |
300 bara | |
SS-PT-4224 |
PAL |
Pressure Alarm Low -Tree No. 42 |
250 bara | |
SS-PT-4224 |
PAH |
Pressure Alarm High -Tree No. 42 |
300 bara | |
SS-PT-4321 |
PAL |
Pressure Alarm Low -Tree No. 43 |
250 bara | |
SS-PT-4321 |
PAH |
Pressure Alarm High -Tree No. 43 |
300 bara | |
SS-PT-4322 |
PAL |
Pressure Alarm Low -Tree No. 43 |
250 bara | |
SS-PT-4322 |
PAH |
Pressure Alarm High -Tree No. 43 |
300 bara | |
SS-PT-4323 |
PAL |
Pressure Alarm Low -Tree No. 43 |
250 bara | |
SS-PT-4323 |
PAH |
Pressure Alarm High -Tree No. 43 |
300 bara | |
SS-PT-4324 |
PAL |
Pressure Alarm Low -Tree No. 43 |
250 bara | |
SS-PT-4324 |
PAH |
Pressure Alarm High -Tree No. 43 |
300 bara | |
SS-PT-4421 |
PAL |
Pressure Alarm Low -Tree No. 44 |
250 bara | |
SS-PT-4421 |
PAH |
Pressure Alarm High -Tree No. 44 |
300 bara | |
SS-PT-4422 |
PAL |
Pressure Alarm Low -Tree No. 44 |
250 bara | |
SS-PT-4422 |
PAH |
Pressure Alarm High -Tree No. 44 |
300 bara | |
SS-PT-4423 |
PAL |
Pressure Alarm Low -Tree No. 44 |
250 bara | |
SS-PT-4423 |
PAH |
Pressure Alarm High -Tree No. 44 |
300 bara | |
SS-PT-4424 |
PAL |
Pressure Alarm Low -Tree No. 44 |
250 bara | |
SS-PT-4424 |
PAH |
Pressure Alarm High -Tree No. 44 |
300 bara | |
Water Injection X-Mass Tree Temperature | ||||
09M-TI-3020A-2 |
TAHH |
Temperature Alarm High High - seawater injection pump discharge |
(HOLD) | |
SS-TT-3121 |
TAL |
Temperature Alarm Low -Tree No. 31 |
50°C | |
SS-TT-3121 |
TAH |
Temperature Alarm High -Tree No. 31 |
80°C | |
SS-TT-3122 |
TAL |
Temperature Alarm Low -Tree No. 31 |
50°C | |
SS-TT-3122 |
TAH |
Temperature Alarm High -Tree No. 31 |
80°C | |
SS-TT-3123 |
TAL |
Temperature Alarm Low -Tree No. 31 |
50°C | |
SS-TT-3123 |
TAH |
Temperature Alarm High -Tree No. 31 |
80°C | |
SS-TT-3124 |
TAL |
Temperature Alarm Low -Tree No. 31 |
50°C | |
SS-TT-3124 |
TAH |
Temperature Alarm High -Tree No. 31 |
80°C | |
SS-TT-3221 |
TAL |
Temperature Alarm Low -Tree No. 32 |
50°C | |
SS-TT-3221 |
TAH |
Temperature Alarm High -Tree No. 32 |
80°C | |
SS-TT-3222 |
TAL |
Temperature Alarm Low -Tree No. 32 |
50°C | |
SS-TT-3222 |
TAH |
Temperature Alarm High -Tree No. 32 |
80°C | |
SS-TT-3223 |
TAL |
Temperature Alarm Low -Tree No. 32 |
50°C | |
SS-TT-3223 |
TAH |
Temperature Alarm High -Tree No. 32 |
80°C | |
SS-TT-3224 |
TAL |
Temperature Alarm Low -Tree No. 32 |
50°C | |
SS-TT-3224 |
TAH |
Temperature Alarm High -Tree No. 32 |
80°C | |
SS-TT-3321 |
TAL |
Temperature Alarm Low -Tree No. 33 |
50°C | |
SS-TT-3321 |
TAH |
Temperature Alarm High -Tree No. 33 |
80°C | |
SS-TT-3322 |
TAL |
Temperature Alarm Low -Tree No. 33 |
50°C | |
SS-TT-3322 |
TAH |
Temperature Alarm High -Tree No. 33 |
80°C | |
SS-TT-3323 |
TAL |
Temperature Alarm Low -Tree No. 33 |
50°C | |
SS-TT-3323 |
TAH |
Temperature Alarm High -Tree No. 33 |
80°C | |
SS-TT-3324 |
TAL |
Temperature Alarm Low -Tree No. 33 |
50°C | |
SS-TT-3324 |
TAH |
Temperature Alarm High -Tree No. 33 |
80°C | |
SS-TT-3421 |
TAL |
Temperature Alarm Low -Tree No. 34 |
50°C | |
SS-TT-3421 |
TAH |
Temperature Alarm High -Tree No. 34 |
80°C | |
SS-TT-3422 |
TAL |
Temperature Alarm Low -Tree No. 34 |
50°C | |
SS-TT-3422 |
TAH |
Temperature Alarm High -Tree No. 34 |
80°C | |
SS-TT-3423 |
TAL |
Temperature Alarm Low -Tree No. 34 |
50°C | |
SS-TT-3423 |
TAH |
Temperature Alarm High -Tree No. 34 |
80°C | |
SS-TT-3424 |
TAL |
Temperature Alarm Low -Tree No. 34 |
50°C | |
SS-TT-3424 |
TAH |
Temperature Alarm High -Tree No. 34 |
80°C | |
SS-TT-4121 |
TAL |
Temperature Alarm Low -Tree No. 41 |
50°C | |
SS-TT-4121 |
TAH |
Temperature Alarm High -Tree No. 41 |
80°C | |
SS-TT-4122 |
TAL |
Temperature Alarm Low -Tree No. 41 |
50°C | |
SS-TT-4122 |
TAH |
Temperature Alarm High -Tree No. 41 |
80°C | |
SS-TT-4123 |
TAL |
Temperature Alarm Low -Tree No. 41 |
50°C | |
SS-TT-4123 |
TAH |
Temperature Alarm High -Tree No. 41 |
80°C | |
SS-TT-4124 |
TAL |
Temperature Alarm Low -Tree No. 41 |
50°C | |
SS-TT-4124 |
TAH |
Temperature Alarm High -Tree No. 41 |
80°C | |
SS-TT-4221 |
TAL |
Temperature Alarm Low -Tree No. 42 |
50°C | |
SS-TT-4221 |
TAH |
Temperature Alarm High -Tree No. 42 |
80°C | |
SS-TT-4222 |
TAL |
Temperature Alarm Low -Tree No. 42 |
50°C | |
SS-TT-4222 |
TAH |
Temperature Alarm High -Tree No. 42 |
80°C | |
SS-TT-4223 |
TAL |
Temperature Alarm Low -Tree No. 42 |
50°C | |
SS-TT-4223 |
TAH |
Temperature Alarm High -Tree No. 42 |
80°C | |
SS-TT-4224 |
TAL |
Temperature Alarm Low -Tree No. 42 |
50°C | |
SS-TT-4224 |
TAH |
Temperature Alarm High -Tree No. 42 |
80°C | |
SS-TT-4321 |
TAL |
Temperature Alarm Low -Tree No. 43 |
50°C | |
SS-TT-4321 |
TAH |
Temperature Alarm High -Tree No. 43 |
80°C | |
SS-TT-4322 |
TAL |
Temperature Alarm Low -Tree No. 43 |
50°C | |
SS-TT-4322 |
TAH |
Temperature Alarm High -Tree No. 43 |
80°C | |
SS-TT-4323 |
TAL |
Temperature Alarm Low -Tree No. 43 |
50°C | |
SS-TT-4323 |
TAH |
Temperature Alarm High -Tree No. 43 |
80°C | |
SS-TT-4324 |
TAL |
Temperature Alarm Low -Tree No. 43 |
50°C | |
SS-TT-4324 |
TAH |
Temperature Alarm High -Tree No. 43 |
80°C | |
SS-TT-4421 |
TAL |
Temperature Alarm Low -Tree No. 44 |
50°C | |
SS-TT-4421 |
TAH |
Temperature Alarm High -Tree No. 44 |
80°C | |
SS-TT-4422 |
TAL |
Temperature Alarm Low -Tree No. 44 |
50°C | |
SS-TT-4422 |
TAH |
Temperature Alarm High -Tree No. 44 |
80°C | |
SS-TT-4423 |
TAL |
Temperature Alarm Low -Tree No. 44 |
50°C | |
SS-TT-4423 |
TAH |
Temperature Alarm High -Tree No. 44 |
80°C | |
SS-TT-4424 |
TAL |
Temperature Alarm Low -Tree No. 44 |
50°C | |
SS-TT-4424 |
TAH |
Temperature Alarm High -Tree No. 44 |
80°C |
Table 30 Valve List
PRODUCTION WELL |
Valve |
DESCRIPTION |
Tag Number |
Choke Valve |
PCV-1114 |
Production Wing Valve |
XV-1102 |
Production Master Valve |
XV-1101 |
Subsea Surface Safety Valve |
XV-1112 |
Annulus Access Valve |
AAV |
Annulus Insert Valve |
AIV |
Annulus Master Valve |
XV-1103 |
The above valves are identical for all production X MAS Tree |
|
Manifold Production Valves |
XV-1110 |
XV-1109 |
|
Manifold Test Valve |
XV-1108 |
The above valves are identical for all X MAS Tree to the Drill centre manifold North and South |
|
Pig Valves |
XV-1015 |
XV-2015 |
|
Shutdown Valves |
TU-SDV-0030-1 |
TU-SDV-0032-1 |
|
TU-SDV-0031-1 |
|
GAS LIFT SYSTEM | |
Choke Valve |
PCV-1113 |
Annulus Wing Valve |
XV-1113 |
Cross Over Valve |
XV-1107 |
The above valves are identical for all production X MAS Tree |
|
Gas Lift Valve |
XV-1111 |
The above valves are identical for all X MAS Tree to the Drill centre manifold North and South |
|
Shutdown Valve |
TU-SDV-0230-1 |
WATER INJECTION SYSTEM | |
Choke Valve |
PCV-1114 |
Injection Wing Valve |
XV-1102 |
Injection Master Valve |
XV-1101 |
Annulus Access Valve |
AAV |
Annulus Insert Valve |
AIV |
Annulus Master Valve |
XV-1103 |
Cross Over Valve |
XV-1107 |
The above valves are identical for all water injection X MAS Tree |
|
Shutdown Valve |
09M-SDV-3020A-18 |
With my signature I do hereby acknowledge that I have read and understood the preceding document.
Signature |
Date |
Signature |
Date |
|
|