Documente online.
Zona de administrare documente. Fisierele tale
Am uitat parola x Creaza cont nou
 HomeExploreaza
upload
Upload




MODEC INTERNATIONAL LLC

books




MODEC INTERNATIONAL LLC

MODEC Project #:

Document #:

1072-MI20-OPM1-0000

CNR Project #:

C537-CNC-14461

Baobab Field Development

Document Title:

VOLUME 01 - SUBSEA SYSTEMS,FLOWLINES & RISERS

FINAL ISSUE

PD

SKG

RJW/PL

Rev.

Status

Date

Origin.

Checker

Approved

THIS DOCUMENT INCLUDING, DRAWINGS, PROCEDURES, SPECIFICATIONS, AND ITS CONTENTS IS THE EXCLUSIVE PROPERTY OF MODEC INTERNATIONAL LLC AND IS FURNISHED ON A CONFIDENTIAL BASIS, AND WITH THE EXPRESS AGREEMENT THAT IT WILL NEITHER BE USED, SOLD, TRANSFERRED, COPIED, TRACED, PHOTOGRAPHED, NOR REPRODUCED IN ANY MANNER WHATSOEVER IN WHOLE OR IN PART, NOR ANY ITEM HERIN BE SOLD, MANUFACTURED OR ASSEMBLED WITHOUT THE WRITTEN AGREEMENT OF MODEC INTERNATIONAL LLC THE RECIPIENT OF THIS DOCUMENT AGREES NOT TO DISCLOSE TO ANY OTHER PARTY INFORMATION CONTAINED HEREIN, OR NOT TO USE SUCH INFORMATION, EXCEPT FOR THE SPECIFIC PURPOSE INTENDED AT THE TIME OF RELEASE OF THIS DOCUMENT.

Distribution

Total

Status

Quantity

CHANGE CONTROL SHEET

REVISION INFORMATION

REV

DATE

SIGNATURE OF REVISION AUTHOR

DATE

SUBSEA SYSTEMS,FLOWLINES & RISERS

TABLE OF CONTENTS

Section-Page

Purpose

Scope

References

Definitions

Responsibility

Safety and Environmental CONSIDERATIONS

Process Overview

Major SUBSEA FLOWLINE Summary

System Summary

SUBSEA SYSTEM

Production Risers

Gas Import/Export Riser

WATER INJECTION RISER

GAS LIFT RISER

UMBILICAL

START UP, OPERATING & SHUTDOWN PROCEDURES - SUBSEA RISERs

Cold Start-up Procedure Following a Planned Shutdown.

Hot Start-up Procedure Following a Process Trip

Normal Operational Checks:

Planned Shutdown procedure

Emergency Controlled Shutdown Procedure

Alarm, Trip and PSV Settings

Valve List

Acknowledgements

Tables

Table 1 Production Riser size & Design Pressure

Table 2 Pressure Monitoring

Table 3 Temperature Monitoring

Table 4 Operating and Design Conditions for TU-FAT-0130

Table 5 Pressure Monitoring

Table 6 Temperature Monitoring

Table 7 Flow Monitoring

Table 8 Operating and Design Conditions for TU-FAS-0230

Table 9 Pressure Monitoring

Table 10 Temperature Monitoring

Table 11 Flow Monitoring

Table 12 Umbilical Summary

Table 13 Cold Start-up Valve Checklist

Table 14 Cold Start-up Overrides (Production Wells)

Table 15 Cold Start-up Overrides (Gas Lift)

Table 16 Cold Start-up Overrides (Water Injection)

Table 17 Cold Start-up Procedure Following a Planned Shutdown (Production Wells)

Table 18 Cold Start-up Procedure Following a Planned Shutdown (Gas LIft)

Table 19 Cold Start-up Procedure Following a Planned Shutdown (Water Injection)

Table 20 Hot Start-up Procedure Following a System Trip (Production Wells)

Table 21 Hot Start-up Procedure Following a System Trip (Gas Lift)

Table 22 Hot Start-up Procedure Following a System Trip (Water Injection)

Table 23 Planned Shutdown Procedure (Production Wells)

Table 24 Planned Shutdown Procedure (Gas LIft)

Table 25 Planned Shutdown Procedure (Water Injection)

Table 26 Emergency Controlled Shutdown Procedure

Table 27 Alarm, Trip & Settings (Production Wells)

Table 28 Alarm, Trip & Settings (Gas Lift)

Table 29 Alarm, Trip & Settings (Water Injection)

Table 30 Valve List

figure

Figure 1 Process Flow Diagram of the Subsea System.


INTRODUCTION

This document is part of the Operating Manual, which covers the Subsea Systems Flowlines & Risers . The Subsea System operations manual together with other manuals and related documents comprise the Facility Management System or FMS. The Subsea System is a controlled document maintained by MODEC INTERNATIONAL LLC, the Contract Operator of the Baobab Field. Any question concerning this document or its contents should be addressed to the Contract Operator.

Purpose

This document gives a general description of and the task lists for the operation of the Subsea system. Its purpose is to educate those who are unfamiliar with the system in how it works and the way in which the system is to be started, stopped and operated safely. This document can be used as a reference document in formulating maintenance isolation procedures.

Scope

Information contained in this document applies only to the Subsea System on the Baobab Field Development project. The information contained gives general design information, alarm settings and trip points for the various components as well as the start up, shut down and normal operating procedures for the Subsea System.

References

Refer P&IDs 6220-PD-20-01-00001,6202-PD-02-05-00173,6219-PD-19-01-00001,1072-MI20-9020-0118,1072-MI20-9020-0146,6202-PD-02-01-00169,6202-PD-02-03-00171,6202-PD-02-02-00170,BAO-CNR-SU-PID-00187-04,BAO-CNR-SU-PID-00187-06,BA0-CNR-SU-PID-00187-01,BAO-CNR-SU-PID-00187-02,BAO-CNR-SU-PID-00186-02,BAO-CNR-SU-PID-00186-01 AND Alarm List (PT REF : 1072-CNR20-0002-0002)

Definitions

See the Definitions Document of the FMS.

Responsibility

Every plant system covered by the Subsea System has been assigned to a single position title in the permanent offshore crew. The person filling the named position is jointly responsible with his off-duty relief for the integrity and the safe operation of the assigned system. In like manner it is that person's responsibility to verify the accuracy of the information contained in this document. Any confirmed inaccuracy shall be tracked by the Offshore Installation Manager (OIM) until formally corrected.

The job title of the position responsible for this system can be found in the System Responsibility Matrix in the Safety Management System (SMS) Manual (Doc No. 1072-MI20-15ST-0170).

Safety and Environmental CONSIDERATIONS

In the execution of the subsequent procedures all permit to work, PPE and isolation procedures required by the Baobab SMS (Doc No. 1072-MI20-15ST-0170) shall be followed. If any doubt exists as to the correctness of valve positions or sequence of operations then they should be discussed with the supervisor and approval sought from the Facility Manager to change the procedure. These changes shall then be captured on a permanent basis by submitting them through the required document control procedures. Specific requirements for HSE are given in each section of the procedures.

Shut down overrides for this system can be invoked only when the system is continuously monitored. Proper procedures and systems should be followed while testing the trips. Where overrides are put in place for testing, these shall be removed at the end of testing so as not to inhibit shutdown functions.

Process Overview

Major SUBSEA FLOWLINE Summary

The main Flowlines within the Subsea facilities are as follows:

Three Production Risers (Riser No. 1,3 & 5)

One Gas Import/Export Riser

One Water Injectio 24524m125y n Riser

One Gas Lift Riser

One Umbilical

Provision for additional five future risers

System Summary

Initially seven Risers (three production, one gas import/export, one water injection, one gas lift and one Umbilical) are installed / connected at the external turret on the FPSO. In addition ,provision has been made for a total of five future risers (two production, one gas lift, one water injection and one umbilical). Flexible risers are used to link production and service functions in the subsea manifolds with processing facilities and controls on the FPSO. The turret is the mooring point for the FPSO as well as the interface between the subsea system and the topside modules. It serves as a connection point between the FPSO and the subsea system and is the pathway for getting oil from the reservoir into the vessel through subsea risers. The swivel stack is mounted on top of the turret, which itself is capable of rotating by means of upper and lower bearing allowing the vessel to weather vane around the turret. Flexible hose carry the well fluids from well manifolds, DCN and DCS, transporting it through the turret to the swivel stack. The swivel stack has a collection of the couplings for well fluids ,water injection, gas export, gas lift, hydraulic & electrical control signals. Production fluids shall be transported to the FPSO moored some 4-5 km from the drill center north (six well heads no. 11,12,13,14,15 and 16) and from drill center south (Six well heads No. 21,22,23,24,25 and 26) via production manifolds through three production risers. Provision has been made at DCN for additional wells to be tied in using the daisy-chain approach. The production wells have been drilled from two subsea manifolds on the western shoulder of the sub-sea canyon while the water injection wells have been drilled from two sub-sea manifold system tied back to the FPSO. The control system for subsea manifold is electro-hydraulic. Control is carried out by a multiplexed hydraulic control system ,where connections between the surface and subsea are via an umbilical. The main umbilical is provided with power/communication signal quads, HP &LP hydraulic control lines and chemicals. Physical separation between the umbilical and production pipeline shall be maintained at a nominal 15 m, where possible, to avoid excessive thermal effects on the umbilical.


Figure Process Flow Diagram of the Subsea System.

SUBSEA SYSTEM

The main function of the subsea system is to connect the FPSO (top side processing unit) with the well heads to receive well fluids from well heads to the FPSO. The system also provides water injection for pressurization of the field, gas lift facility, chemical injection (Methanol, Scale Inhibitor, De-emulsifier, Wax Inhibitor & Corrosion Inhibitor) and hydraulic control of subsea valves and subsea instrument signal transmission to SCU (Subsea Control Unit) and DCS for monitoring and control the subsea process variables. Operator control and monitoring of the subsea system is via the FPSO DCS. DCS connected with Subsea Control Unit (SCU). SCU and SPCU (Subsea Control & Communication Unit) are the main control unit for subsea system connected with UPS (Uninterruptible Power Supply),HPU (Hydraulic Power Unit),DCS and topside ESD. The SCU is comprises of a number of modular units containing signal board computers. Operation and monitoring of subsea equipment is carryied out via Subsea Control Modules (SCM) which are connected to SCU. Electrical power and communications are provided between the surface and subsea on a combined communication and power system. I,e the same electrical conductors are used to provide both power and communications signals. Each SCM has two Subsea Electronic Modules (SEMs) to maintain the redundancy into the SCM. The SCM contains a set of solenoid operated directional control valves (DCVs) . These are used to switch hydraulic pressure to the particular function (e.g. tree or manifold valve). The solenoid operated DCVs have two dual wound solenoids, such that a valve open signal is directed to the open solenoid and a valve close signal is directed to the close solenoid. The solenoids are dual wound to allow the signal to be presented by either SEM. Design is such that the solenoid operated DCV is fail stay put on loss of electrical/ power/communications and fail closed on loss of hydraulic power.

Production Risers

There are twelve well heads, six from drill center north (DCN) and six from drill center south (DCN) connected through flexible hose to three production risers (riser no. 1,3 & 5). The well heads from DCN are connected with production riser no.1 & 3 and the well heads from DCS are connected with production risers no.3 & 5. Each production line from the well head has a subsurface safety valve (SSSV), one Production Master Valve (PMV), one Production Wing Valve (PWV), one production Choke Valve (PCV) two Manifold Production Valves (MPV) on the lines connecting the two production risers and a Manifold Test Valve (MTV) connected to the line with multi-phase flow-meters (2 off). Each production line from the wellhead has a gas lift line with associated valves and instruments connected with the annulus of the respective production well. In the annulus line of each production well head there are Annulus Access Valve (AAV), Annulus Insert Valve (AIV), Annulus Master Valve (AMV) and gas lift line with associated valves and instruments is connected with the annulus line. Each well head provided with demulsifier, methanol and scale inhibitor injection line. Each wellhead is production riser provided with methanol, scale, wax and corrosion inhibitor injection line and at the inlet of multi-phase flowmeters, demulsifier injection line also provided.

Production Riser Description and Control

There are three off 11" ID production risers coming from the DCN and DCS manifolds ,connected to swivel manifold and finally, after passing through the turret, connect to the topside production manifold.

Table Production Riser size & Design Pressure

Manifold DCN/DCS

Design Pressure

Production Header

345 barg

Production Branch

345 barg

Production Test Line

345 barg

Pressure Monitoring, Control and ESD Instruments:

Drill center north manifold (six well head with tree no. 11,12,13,14,15 & 16) and Drill center south manifold (six well head with tree no. 21,22,23,24,25 & 26) combined in three production risers (Riser no. 1, 3 & 5) are provided with the following pressure transmitter to alert the operator.

Table Pressure Monitoring

Instrumentation Tag

Description

SS-PT-1131

Pressure Transmitter - Upstream of SS-XV-1112 Tree No. 11

SS-PT-1132

Pressure Transmitter - Upstream of SS-XV-1112 Tree No. 11

SS-PT-1121

Pressure Transmitter - Upstream Production Choke Press.1 Tree No. 11

SS-PT-1122

Pressure Transmitter - Upstream Production Choke Press.2 Tree No. 11

SS-PT-1123

Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 11

SS-PT-1124

Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 11

SS-PT-1231

Pressure Transmitter -Upstream of SS-XV-1212 Tree No. 12

SS-PT-1232

Pressure Transmitter -Upstream of SS-XV-1212 Tree No. 12

SS-PT-1221

Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 12

SS-PT-1222

Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 12

SS-PT-1223

Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 12

SS-PT-1224

Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 12

SS-PT-1331

Pressure Transmitter -Upstream of SS-XV-1312 Tree No. 13

SS-PT-1332

Pressure Transmitter -Upstream of SS-XV-1312 Tree No. 13

SS-PT-1321

Pressure Transmitter- Upstream Production Choke Press.1 Tree No. 13

SS-PT-1322

Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 13

SS-PT-1323

Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 13

SS-PT-1324

Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 13

SS-PT-1431

Pressure Transmitter -Upstream of SS-XV-1412 Tree No. 14

SS-PT-1432

Pressure Transmitter -Upstream of SS-XV-1412 Tree No. 14

SS-PT-1421

Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 14

SS-PT-1422

Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 14

SS-PT-1423

Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 14

SS-PT-1424

Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 14

SS-PT-1531

Pressure Transmitter -Upstream of SS-XV-1512 Tree No. 15

SS-PT-1532

Pressure Transmitter -Upstream of SS-XV-1512 Tree No. 15

SS-PT-1521

Pressure Transmitter- Upstream Production Choke Press.1 Tree No. 15

SS-PT-1522

Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 15

SS-PT-1523

Pressure Transmitter- Downstream Production Choke Press.1 Tree No. 15

SS-PT-1524

Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 15

SS-PT-1631

Pressure Transmitter -Upstream of SS-XV-1612 Tree No. 16

SS-PT-1632

Pressure Transmitter- Upstream of SS-XV-1612 Tree No. 16

SS-PT-1621

Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 16

SS-PT-1622

Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 16

SS-PT-1623

Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 16

SS-PT-1624

Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 16

SS-PT-2131

Pressure Transmitter- Upstream of SS-XV-2112 Tree No. 21

SS-PT-2132

Pressure Transmitter -Upstream of SS-XV-2112 Tree No. 21

SS-PT-2121

Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 21

SS-PT-2122

Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 21

SS-PT-2123

Pressure Transmitter- Downstream Production Choke Press.1 Tree No. 21

SS-PT-2124

Pressure Transmitter- Downstream Production Choke Press.2 Tree No. 21

SS-PT-2231

Pressure Transmitter- Upstream of SS-XV-2212 Tree No. 22

SS-PT-2232

Pressure Transmitter- Upstream of SS-XV-2212 Tree No. 22

SS-PT-2221

Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 22

SS-PT-2222

Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 22

SS-PT-2223

Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 22

SS-PT-2224

Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 22

SS-PT-2331

Pressure Transmitter -Upstream of SS-XV-2312 Tree No. 23

SS-PT-2332

Pressure Transmitter -Upstream of SS-XV-2312 Tree No. 23

SS-PT-2321

Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 23

SS-PT-2322

Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 23

SS-PT-2323

Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 23

SS-PT-2324

Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 23

SS-PT-2431

Pressure Transmitter -Upstream of SS-XV-2412 Tree No. 24

SS-PT-2432

Pressure Transmitter -Upstream of SS-XV-2412 Tree No. 24

SS-PT-2421

Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 24

SS-PT-2422

Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 24

SS-PT-2423

Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 24

SS-PT-2424

Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 24

SS-PT-2531

Pressure Transmitter -Upstream of SS-XV-2512 Tree No. 25

SS-PT-2532

Pressure Transmitter -Upstream of SS-XV-2512 Tree No. 25

SS-PT-2521

Pressure Transmitter -Upstream Production Choke Press.1 Tree No. 25

SS-PT-2522

Pressure Transmitter- Upstream Production Choke Press.2 Tree No. 25

SS-PT-2523

Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 25

SS-PT-2524

Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 25

SS-PT-2631

Pressure Transmitter- Upstream of SS-XV-2612 Tree No. 26

SS-PT-2632

Pressure Transmitter -Upstream of SS-XV-2612 Tree No. 26

SS-PT-2621

Pressure Transmitter- Upstream Production Choke Press.1 Tree No. 26

SS-PT-2622

Pressure Transmitter -Upstream Production Choke Press.2 Tree No. 26

SS-PT-2623

Pressure Transmitter -Downstream Production Choke Press.1 Tree No. 26

SS-PT-2624

Pressure Transmitter -Downstream Production Choke Press.2 Tree No. 26

SS-PT-1021

Pressure Transmitter -Production Riser No. 3

SS-PT-1022

Pressure Transmitter -Production Riser No. 1

SS-PT-2021

Pressure Transmitter -Production Riser No. 5

SS-PT-2022

Pressure Transmitter -Production Riser No. 3

Process variable from pressure transmitter is transmitted to the Subsea Control Unit (SCU) and Distributed Control System (DCS) with high and low alarm. Refer to section 6.0 for the alarm settings.

Temperature Monitoring, Control and ESD Instruments:

Drill center north manifold (six well head with tree no. 11,12,13,14,15 & 16) and Drill center south manifold (six well head with tree no. 21,22,23,24,25 & 26) combined in three production risers (Riser no. 1, 3 & 5) are provided with the following temperature transmitter to alert the operator.

Table Temperature Monitoring

Instrumentation Tag

Description

SS-TT-1131

Temperature Transmitter - Upstream of SS-XV-1112 Tree No. 11

SS-TT-1132

Temperature Transmitter - Upstream of SS-XV-1112 Tree No. 11

SS-TT-1121

Temperature Transmitter- Upstream Production Choke Temp.1 Tree No. 11

SS-TT-1122

Temperature Transmitter - Upstream Production Choke Temp.2 Tree No. 11

SS-TT-1123

Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 11

SS-TT-1124

Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 11

SS-TT-1231

Temperature Transmitter -Upstream of SS-XV-1212 Tree No. 12

SS-TT-1232

Temperature Transmitter -Upstream of SS-XV-1212 Tree No. 12

SS-TT-1221

Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 12

SS-TT-1222

Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 12

SS-TT-1223

Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 12

SS-TT-1224

Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 12

SS-TT-1331

Temperature Transmitter -Upstream of SS-XV-1312 Tree No. 13

SS-TT-1332

Temperature Transmitter -Upstream of SS-XV-1312 Tree No. 13

SS-TT-1321

Temperature Transmitter- Upstream Production Choke Temp.1 Tree No. 13

SS-TT-1322

Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 13

SS-TT-1323

Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 13

SS-TT-1324

Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 13

SS-TT-1431

Temperature Transmitter -Upstream of SS-XV-1412 Tree No. 14

SS-TT-1432

Temperature Transmitter -Upstream of SS-XV-1412 Tree No. 14

SS-TT-1421

Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 14

SS-TT-1422

Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 14

SS-TT-1423

Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 14

SS-TT-1424

Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 14

SS-TT-1531

Temperature Transmitter -Upstream of SS-XV-1512 Tree No. 15

SS-TT-1532

Temperature Transmitter -Upstream of SS-XV-1512 Tree No. 15

SS-TT-1521

Temperature Transmitter- Upstream Production Choke Temp.1 Tree No. 15

SS-TT-1522

Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 15

SS-TT-1523

Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 15

SS-TT-1524

Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 15

SS-TT-1631

Temperature Transmitter -Upstream of SS-XV-1612 Tree No. 16

SS-TT-1632

Temperature Transmitter- Upstream of SS-XV-1612 Tree No. 16

SS-TT-1621

Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 16

SS-TT-1622

Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 16

SS-TT-1623

Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 16

SS-TT-1624

Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 16

SS-TT-2131

Temperature Transmitter- Upstream of SS-XV-2112 Tree No. 21

SS-TT-2132

Temperature Transmitter -Upstream of SS-XV-2112 Tree No. 21

SS-TT-2121

Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 21

SS-TT-2122

Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 21

SS-TT-2123

Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 21

SS-TT-2124

Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 21

SS-TT-2231

Temperature Transmitter- Upstream of SS-XV-2212 Tree No. 22

SS-TT-2232

Temperature Transmitter- Upstream of SS-XV-2212 Tree No. 22

SS-TT-2221

Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 22

SS-TT-2222

Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 22

SS-TT-2223

Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 22

SS-TT-2224

Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 22

SS-TT-2331

Temperature Transmitter -Upstream of SS-XV-2312 Tree No. 23

SS-TT-2332

Temperature Transmitter -Upstream of SS-XV-2312 Tree No. 23

SS-TT-2321

Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 23

SS-TT-2322

Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 23

SS-TT-2323

Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 23

SS-TT-2324

Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 23

SS-TT-2431

Temperature Transmitter -Upstream of SS-XV-2412 Tree No. 24

SS-TT-2432

Temperature Transmitter -Upstream of SS-XV-2412 Tree No. 24

SS-TT-2421

Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 24

SS-TT-2422

Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 24

SS-TT-2423

Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 24

SS-TT-2424

Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 24

SS-TT-2531

Temperature Transmitter -Upstream of SS-XV-2512 Tree No. 25

SS-TT-2532

Temperature Transmitter -Upstream of SS-XV-2512 Tree No. 25

SS-TT-2521

Temperature Transmitter -Upstream Production Choke Temp.1 Tree No. 25

SS-TT-2522

Temperature Transmitter- Upstream Production Choke Temp.2 Tree No. 25

SS-TT-2523

Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 25

SS-TT-2524

Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 25

SS-TT-2631

Temperature Transmitter- Upstream of SS-XV-2612 Tree No. 26

SS-TT-2632

Temperature Transmitter -Upstream of SS-XV-2612 Tree No. 26

SS-TT-2621

Temperature Transmitter- Upstream Production Choke Temp.1 Tree No. 26

SS-TT-2622

Temperature Transmitter -Upstream Production Choke Temp.2 Tree No. 26

SS-TT-2623

Temperature Transmitter-Downstream Production Choke Temp.1 Tree No. 26

SS-TT-2624

Temperature Transmitter-Downstream Production Choke Temp.2 Tree No. 26

SS-TT-1021

Temperature Transmitter -Production Riser No. 3

SS-TT-1022

Temperature Transmitter -Production Riser No. 1

SS-TT-2021

Temperature Transmitter -Production Riser No. 5

SS-TT-2022

Temperature Transmitter -Production Riser No. 3

Process variable from temperature transmitter is transmitted to the Subsea Control Unit (SCU) and Distributed Control System (DCS) with high and low alarm. Refer to section 6.0 for the alarm settings.

Flow Monitoring :

From each wellhead, one line connected to the Multi-phase Flow meters (MP) through a manifold test valve (MTV) for measuring individual well production mass flow rate located in the DCN & DCS. SS-MFM-2051/2071 are the multi phase flow meters for Drill Center South (DCS) and SS-MFM-1051/1071 are the multi phase flow meters for Drill Center North (DCN).

Gas Import/Export Riser

From the third stage Booster Gas Compressor one six inch Gas Import/export line connected to the turret and on the subsea system. This line is finally connected to gas export line from FPSO Espoir and then to the 10" pipeline to shore. For details refer Doc. No. 1072-MI20-OPM1-05 for gas export system.

WATER INJECTION RISER

Sea water injection pump (09M-PAT-3020A/B/C/D/E/F) discharge connected to a 12" water injection header, which connected to water injection Swivel (TU-FAT-0818) in the turret area. The water injection riser termed as Riser No. 12 going to the subsea for water injection. Sea water is injected into the reservoir to enhance the recovery of oil by maintaining the reservoir pressure as the oil is taken out, hence improving oil production and prolonging the useful life of the field. Water injection riser no. 12 connected to the two water injection manifold North & South by flexible hose. In the water injection north and south manifold there are four injection wells (tree no. 31,32,33 and 34 for north and tree no. 41,42,43, & 44 for the south) for each manifold. In the water injection X-Mas tree there is a venturi flowmeter in the water injection line upstream of choke valve. Downstream of choke valve there are Injection Wing Valve (IWV) and Injection Master Valve (IMV) connecting the line to the injection well. Pressure and temperature transmitters are provided upstream and downstream of the choke valve for monitoring the process variable from SCU & DCS. Annulus Access Valve (AAV), Annulus Insert Valve (AIV), Annulus Master Valve (AMV) are provided in each annulus line connected to the water injection wells.

Riser Description and Control

Water injection line from the topside is connected to the water injection swivel (TU-FAT-0818) has the operating pressure 172.4 barg @ 48° C and design pressure 248.2 barg @ 38° C. From water injection swivel the water injection riser No. 12 is connected to the subsea water injection manifold North & South. The water injection riser has the following operating & design conditions.

Table Operating and Design Conditions for TU-FAT-0130

Parameter

Value

Internal Diameter

280 mm (11")

Design Pressure

248.2 barg @ 38oC

Operating Pressure

172.4 barg

Flow Rate

15900 M3/D (100000 BWPD)

Pressure Monitoring, Control and ESD Instruments:

Water Injection North manifold (four injection well with tree no. 31,32,33 & 34) and Water Injection South manifold (four injection well with tree no. 41,42,43 & 44) combined in one water injection riser no. 12 are provided with the following pressure transmitter to alert the operator.

Table Pressure Monitoring

Instrumentation Tag

Description

SS-PT-3121

Pressure Transmitter - Downstream Choke Pressure 1 Tree No.31

SS-PT-3122

Pressure Transmitter - Downstream Choke Pressure 2 Tree No.31

SS-PT-3123

Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 31

SS-PT-3124

Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 31

SS-PT-3125

Pressure Transmitter - Annulus Pressure Tree No. 31

SS-PT-3221

Pressure Transmitter - Downstream Choke Pressure 1 Tree No.32

SS-PT-3222

Pressure Transmitter - Downstream Choke Pressure 2 Tree No.32

SS-PT-3223

Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 32

SS-PT-3224

Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 32

SS-PT-3225

Pressure Transmitter - Annulus Pressure Tree No. 32

SS-PT-3321

Pressure Transmitter - Downstream Choke Pressure 1 Tree No.33

SS-PT-3322

Pressure Transmitter - Downstream Choke Pressure 2 Tree No.33

SS-PT-3323

Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 33

SS-PT-3324

Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 33

SS-PT-3325

Pressure Transmitter - Annulus Pressure Tree No. 33

SS-PT-3421

Pressure Transmitter - Downstream Choke Pressure 1 Tree No.34

SS-PT-3422

Pressure Transmitter - Downstream Choke Pressure 2 Tree No.34

SS-PT-3423

Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 34

SS-PT-3424

Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 34

SS-PT-3425

Pressure Transmitter - Annulus Pressure Tree No. 34

SS-PT- 4121

Pressure Transmitter - Downstream Choke Pressure 1 Tree No.41

SS-PT- 4122

Pressure Transmitter - Downstream Choke Pressure 2 Tree No.41

SS-PT- 4123

Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 41

SS-PT- 4124

Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 41

SS-PT- 4125

Pressure Transmitter - Annulus Pressure Tree No. 41

SS-PT- 4221

Pressure Transmitter - Downstream Choke Pressure 1 Tree No.42

SS-PT- 4222

Pressure Transmitter - Downstream Choke Pressure 2 Tree No.42

SS-PT- 4223

Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 42

SS-PT- 4224

Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 42

SS-PT- 4225

Pressure Transmitter - Annulus Pressure Tree No. 42

SS-PT- 4321

Pressure Transmitter - Downstream Choke Pressure 1 Tree No.43

SS-PT- 4322

Pressure Transmitter - Downstream Choke Pressure 2 Tree No.43

SS-PT- 4323

Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 43

SS-PT- 4324

Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 43

SS-PT- 4325

Pressure Transmitter - Annulus Pressure Tree No. 43

SS-PT- 4421

Pressure Transmitter - Downstream Choke Pressure 1 Tree No.44

SS-PT- 4422

Pressure Transmitter - Downstream Choke Pressure 2 Tree No.44

SS-PT- 4423

Pressure Transmitter -Upstream Choke Pressure 1 Tree No. 44

SS-PT- 4424

Pressure Transmitter - Upstream Choke Pressure 2 Tree No. 44

SS-PT- 4425

Pressure Transmitter - Annulus Pressure Tree No. 44

Process variable from pressure transmitter is transmitted to the Subsea Control Unit (SCU) and Distributed Control System (DCS) with high and low alarm. Refer to section 6.0 for the alarm settings.

Temperature Monitoring

Water Injection North manifold (four injection wells with tree no. 31,32,33 & 34) and Water Injection South manifold (four injection wells with tree no. 41,42,43 & 44) connected to one water injection riser no. 12 are provided with the following temperature transmitter to alert the operator.

Table Temperature Monitoring

Instrumentation Tag

Description

SS-TT-3121

Temperature Transmitter - Downstream Choke Temperature 1 Tree No.31

SS-TT-3122

Temperature Transmitter - Downstream Choke Temperature 2 Tree No.31

SS-TT-3123

Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 31

SS-TT-3124

Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 31

SS-TT-3125

Temperature Transmitter - Annulus Temperature Tree No. 31

SS-TT-3221

Temperature Transmitter - Downstream Choke Temperature 1 Tree No.32

SS-TT-3222

Temperature Transmitter - Downstream Choke Temperature 2 Tree No.32

SS-TT-3223

Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 32

SS-TT-3224

Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 32

SS-TT-3225

Temperature Transmitter - Annulus Temperature Tree No. 32

SS-TT-3321

Temperature Transmitter - Downstream Choke Temperature 1 Tree No.33

SS-TT-3322

Temperature Transmitter - Downstream Choke Temperature 2 Tree No.33

SS-TT-3323

Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 33

SS-TT-3324

Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 33

SS-TT-3325

Temperature Transmitter - Annulus Temperature Tree No. 33

SS-TT-3421

Temperature Transmitter - Downstream Choke Temperature 1 Tree No.34

SS-TT-3422

Temperature Transmitter - Downstream Choke Temperature 2 Tree No.34

SS-TT-3423

Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 34

SS-TT-3424

Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 34

SS-TT-3425

Temperature Transmitter - Annulus Temperature Tree No. 34

SS-TT- 4121

Temperature Transmitter - Downstream Choke Temperature 1 Tree No.41

SS-TT- 4122

Temperature Transmitter - Downstream Choke Temperature 2 Tree No.41

SS-TT- 4123

Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 41

SS-TT- 4124

Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 41

SS-TT- 4125

Temperature Transmitter - Annulus Temperature Tree No. 41

SS-TT- 4221

Temperature Transmitter - Downstream Choke Temperature 1 Tree No.42

SS-TT- 4222

Temperature Transmitter - Downstream Choke Temperature 2 Tree No.42

SS-TT- 4223

Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 42

SS-TT- 4224

Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 42

SS-TT- 4225

Temperature Transmitter - Annulus Temperature Tree No. 42

SS-TT- 4321

Temperature Transmitter - Downstream Choke Temperature 1 Tree No.43

SS-TT- 4322

Temperature Transmitter - Downstream Choke Temperature 2 Tree No.43

SS-TT- 4323

Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 43

SS-TT- 4324

Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 43

SS-TT- 4325

Temperature Transmitter - Annulus Temperature Tree No. 43

SS-TT- 4421

Temperature Transmitter - Downstream Choke Temperature 1 Tree No.44

SS-TT- 4422

Temperature Transmitter - Downstream Choke Temperature 2 Tree No.44

SS-TT- 4423

Temperature Transmitter -Upstream Choke Temperature 1 Tree No. 44

SS-TT- 4424

Temperature Transmitter - Upstream Choke Temperature 2 Tree No. 44

SS-TT- 4425

Temperature Transmitter - Annulus Temperature Tree No. 44

Process variable from temperature transmitter is transmitted to the Subsea Control Unit (SCU) and Distributed Control System (DCS) with high and low alarm. Refer to section 6.0 for the alarm settings.

Flow Monitoring

Each water injection line to the respective injection wells are provided with a venturi flow meter upstream of the choke valve for monitoring the water injection flow rate of individual water injection well. The signal from the flow element transmitted to SCU & DCS for operator visigilence. The tag number of the flow transmitter for each water injection wells are given below:

Table Flow Monitoring

Instrumentation Tag

Description

SS-FT-3114A

Flow Transmitter -1 Water Injection Tree No. 31

SS-FT-3114B

Flow Transmitter -2 Water Injection Tree No. 31

SS-FT-3214A

Flow Transmitter -1 Water Injection Tree No. 32

SS-FT-3214B

Flow Transmitter -2 Water Injection Tree No. 32

SS-FT-3314A

Flow Transmitter -1 Water Injection Tree No. 33

SS-FT-3314B

Flow Transmitter -2 Water Injection Tree No. 33

SS-FT-3414A

Flow Transmitter -1 Water Injection Tree No. 34

SS-FT-3414B

Flow Transmitter -2 Water Injection Tree No. 34

SS-FT-4114A

Flow Transmitter -1 Water Injection Tree No. 41

SS-FT-4114B

Flow Transmitter -2 Water Injection Tree No. 41

SS-FT-4214A

Flow Transmitter -1 Water Injection Tree No. 42

SS-FT-4214B

Flow Transmitter -2 Water Injection Tree No. 42

SS-FT-4314A

Flow Transmitter -1 Water Injection Tree No. 43

SS-FT-4314B

Flow Transmitter -2 Water Injection Tree No. 43

SS-FT-4414A

Flow Transmitter -1 Water Injection Tree No. 44

SS-FT-4414B

Flow Transmitter -2 Water Injection Tree No. 44

GAS LIFT RISER

From the third stage booster gas compressor discharge, one, six-inch gas lift riser is connected to the gas lift swivel (TU-FAS-0816) in the turret area. The gas lift riser No. 4 (TU-FAS-0230) from the gas lift swivels goes to the production well manifolds North & South. The gas lift riser (Riser No. 4) connected by flexible hose to the drill center North and South. In both the production manifolds the gas lift line distributed to each production wellhead is isolated by a Gas Lift Valve (GLV) upstream of the choke valve. When the oil reservoir pressure becomes low the well head pressure is not sufficient to move the well fluid to the topside and the gas injection to the well head through gas lift line introduces the motive force to the well fluid to flow it out from the well head to the topside. There is a venturi flow meter in each gas lift line upstream of the choke valve for gas flow monitoring. Downstream of the choke valve there is an Annulus Master Valve (AMV) through which the gas lift line is connected to the annulus of each production well.

Riser Description and Control

Gas lift line from the topside is connected to the 6" Gas Lift Swivel ( TU-FAS-0816) has the operating pressure 173.7 barg @ 70° C and design pressure 248.2 barg @ 38° C. From Gas Lift Swivel the gas lift riser No. 4 is connected to the subsea gas lift manifold North & South. The gas lift riser have the following operating & design conditions.

Table Operating and Design Conditions for TU-FAS-0230

Parameter

Value

Internal Diameter

152 mm (6")

Design Pressure

248.2 barg @ 38oC

Operating Pressure

173.4 barg

Design Flow Rate

1130000 M3/D (50 MMSCF/D)

Pressure Monitoring, Control and ESD Instruments:

Gas lift manifold and the gas injection line of each X-Mass Tree of production wells are provided with the following pressure transmitter to alert the operator about the lift gas pressure.

Table Pressure Monitoring

Instrumentation Tag

Description

SS-PT-1125

Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.11

SS-PT-1126

Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.11

SS-PT-1225

Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.12

SS-PT-1226

Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.12

SS-PT-1325

Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.13

SS-PT-1326

Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.13

SS-PT-1425

Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.14

SS-PT-1426

Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.14

SS-PT-1525

Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.15

SS-PT-1526

Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.15

SS-PT-1625

Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.16

SS-PT-1626

Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.16

SS-PT-2125

Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.21

SS-PT-2126

Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.21

SS-PT-2225

Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.22

SS-PT-2226

Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.22

SS-PT-2325

Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.23

SS-PT-2326

Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.23

SS-PT-2425

Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.24

SS-PT-2426

Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.24

SS-PT-2525

Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.25

SS-PT-2526

Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.25

SS-PT-2625

Pressure Transmitter - Downstream G.L. Choke Pressure Tree No.26

SS-PT-2626

Pressure Transmitter - Upstream G.L. Choke Pressure Tree No.26

SS-PT-1023

Pressure Transmitter - Gas Lift Header Pressure DCN

SS-PT-2023

Pressure Transmitter - Gas Lift Header Pressure DCS

Process variable from pressure transmitter is transmitted to the Subsea Control Unit (SCU) and Distributed Control System (DCS) with high and low alarm. Refer to section 6.0 for the alarm settings.

Temperature Monitoring

Gas lift manifold and the gas injection line of each X-Mass Tree of production wells are provided with the following temperature transmitter to alert the operator about the lift gas temperature.

Table Temperature Monitoring

Instrumentation Tag

Description

SS-TT-1125

Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.11

SS-TT-1126

Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.11

SS-TT-1225

Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.12

SS-TT-1226

Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.12

SS-TT-1325

Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.13

SS-TT-1326

Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.13

SS-TT-1425

Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.14

SS-TT-1426

Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.14

SS-TT-1525

Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.15

SS-TT-1526

Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.15

SS-TT-1625

Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.16

SS-TT-1626

Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.16

SS-TT-2125

Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.21

SS-TT-2126

Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.21

SS-TT-2225

Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.22

SS-TT-2226

Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.22

SS-TT-2325

Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.23

SS-TT-2326

Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.23

SS-TT-2425

Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.24

SS-TT-2426

Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.24

SS-TT-2525

Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.25

SS-TT-2526

Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.25

SS-TT-2625

Temperature Transmitter - Downstream G.L. Choke Temperature Tree No.26

SS-TT-2626

Temperature Transmitter - Upstream G.L. Choke Temperature Tree No.26

SS-TT-1023

Temperature Transmitter - Gas Lift Header Temperature DCN

SS-TT-2023

Temperature Transmitter - Gas Lift Header Temperature DCS

Process variable from temperature transmitter is transmitted to the Subsea Control Unit (SCU) and Distributed Control System (DCS) with high and low alarm. Refer to section 6.0 for the alarm settings.

Flow Monitoring

Each gas lift line is provided with a venturi flow meter upstream of the choke valve for monitoring the gas flow of individual gas lift line into the respective production X-Mass tree. The signal from the flow element transmitted to SCU & DCS for operator visigilence. The tag numbers of the venturi flow meters are listed below.

Table Flow Monitoring

Instrumentation Tag

Description

SS-FT-1113A

Flow Transmitter -1 Gas Lift Tree No. 11

SS-FT-1113B

Flow Transmitter -2 Gas Lift Tree No. 11

SS-FT-1213A

Flow Transmitter -1 Gas Lift Tree No. 12

SS-FT-1213B

Flow Transmitter -2 Gas Lift Tree No. 12

SS-FT-1313A

Flow Transmitter -1 Gas Lift Tree No. 13

SS-FT-1313B

Flow Transmitter -2 Gas Lift Tree No. 13

SS-FT-1413A

Flow Transmitter -1 Gas Lift Tree No. 14

SS-FT-1413B

Flow Transmitter -2 Gas Lift Tree No. 14

SS-FT-1513A

Flow Transmitter -1 Gas Lift Tree No. 15

SS-FT-1513B

Flow Transmitter -2 Gas Lift Tree No. 15

SS-FT-1613A

Flow Transmitter -1 Gas Lift Tree No. 16

SS-FT-1613B

Flow Transmitter -2 Gas Lift Tree No. 16

SS-FT-2113A

Flow Transmitter -1 Gas Lift Tree No. 21

SS-FT-2113B

Flow Transmitter -2 Gas Lift Tree No. 21

SS-FT-2213A

Flow Transmitter -1 Gas Lift Tree No. 22

SS-FT-2213B

Flow Transmitter -2 Gas Lift Tree No. 22

SS-FT-2313A

Flow Transmitter -1 Gas Lift Tree No. 23

SS-FT-2313B

Flow Transmitter -2 Gas Lift Tree No. 23

SS-FT-2413A

Flow Transmitter -1 Gas Lift Tree No. 24

SS-FT-2413B

Flow Transmitter -2 Gas Lift Tree No. 24

SS-FT-2513A

Flow Transmitter -1 Gas Lift Tree No. 25

SS-FT-2513B

Flow Transmitter -2 Gas Lift Tree No. 25

SS-FT-2613A

Flow Transmitter -1 Gas Lift Tree No. 26

SS-FT-2613B

Flow Transmitter -2 Gas Lift Tree No. 26

UMBILICAL

The main umbilical is provided for power/signal, hydraulics and chemicals. The umbilical is routed in a common corridor with the pipelines wherever possible. Physical separation between the umbilical and production pipeline shall be maintained where possible to avoid excessive thermal effects on the umbilical. The riser umbilical is interfaced with the FPSO through the external turret. The umbilical is secured on the external turret and interfaced with the topsides via a Topside Termination Umbilical Unit (TUTU) and Umbilical Junction Boxes.

Umbilical Description

The 203 mm (8") umbilical has the following items and their respective operating and design conditions are given in the table below :

Table Umbilical Summary

Description

Number

Size

Flow Rate

Operating Pressure

Design Pressure

Hp Hydraulic Control Line

2

3/4" Pipe

N/A

HOLD

690 Barg

Lp Hydraulic Control Line

2

1/2" Pipe

N/A

207 Barg

228 Barg

Methanol

3

1" Pipe

40 M3/D

310 Barg

345 Barg

Hp Scale Inhibitor

10

1/2" Tubing

0.14 M3/D

310 Barg

345 Barg

Demulsifier

10

1/2" Tubing

1 M3/D

310 Barg

345 Barg

Wax Inhibitor

4

1/2" Tubing

0.24 M3/D

310 Barg

345 Barg

Corrosion Inhibitor

4

1/2" Tubing

0.24 M3/D

310 Barg

345 Barg

START UP, OPERATING & SHUTDOWN PROCEDURES - SUBSEA RISERs

Cold Start-up Procedure Following a Planned Shutdown.

The following procedure details the steps to be undertaken to start-up the Subsea System following maintenance activities that may have involved piping intrusion works on part / all of the systems / subsystems.

The following conditions are assumed to exist in executing this procedure: -

No Permits to Work are in force on any part of the system that may prohibit, or hinder, the safe start-up of the equipment.

The Fire and Gas Detection System, ESD Systems and control facilities within the CCR are operational including all alarms, trips and controllers.

All vents, purge points and manual sample points are closed and blanked, or capped off, where necessary.

Ancillary system requirements

The following ancillary systems must be available for operation prior to commencement of this procedure: -

Power is available to the skid

Hydraulic power system is operational

Inlet heater and production separator ready to receive well fluid

Water injection system ready for start up as per Doc. No. 1072-MI20-OPM1-30

Heating medium system is operational

Flow line circulation system ready to start as described in Doc. No. 1072-MI20-OPM1-12

The instrument air system must be in operation.

The production separation system should also be ready for start up as described in Doc. No. 1072-MI20-OPM1-10

Cold Start-up Valve Checklist

Refer to the P&ID 's identified as pertaining to the relevant system whilst carrying out this procedure.

The system operator should check the system valves are in the positions detailed below.

Where valves are found to be out of position, the operator must satisfy himself it is safe to move the valve before doing so. This may involve referencing to an Isolation Permit or relevant Permit to Work.

Table Cold Start-up Valve Checklist

Cold start-up Valve Checklist

line # / vALVE spec

VALVE DESCRIPTION

POSITION

Production well heads & manifolds

(Refer to P&ID DWG No BAO-CNR-SU-PID-00187-01 , BAO-CNR-SU-PID-00187-02, BAO-CNR-SU-PID-00187-04 & BAO-CNR-SU-PID-00187-06)

XV-1112

SSSV on X mass tree no 11

open

XV-1101

Production master valve on tree no 11

open

XV-1102

Production wing valve on tree no 11

open 

PCV-1114

Production choke valve on tree no 11

closeD

xv-1109

Manifold production valve (MPV-11) to production riser no. 3

closed

xv-1110

Manifold production valve (MPV-12) to production riser no. 1

open

xv-1108

Manifold test valve (MTV-1) from production well 11.

closed

The valve status for other production tree No. 12,13,14,15,16,21,22,23,24,25 & 26 will be same as given above for tree No. 11

xv-1015

Pig valve (PV) on DCN

closed

xv-2015

Pig valve (PV) on DCS

closed

xv-1003

Flow meter inlet valve (FIV-1) to multiphase flow meter MFM-1051 at DCN

closed

xv-1004

Flow meter inlet valve (FIV-2) to multiphase flow meter MFM-1071 at DCN

closed

fov-1

Flow meter outlet valve (FOV-1) from multiphase flow meter MFM-1051 at DCN

closed

fov-2

Flow meter outlet valve (FOV-2) from multiphase flow meter MFM-1071 at DCN

closed

fov-3

Flow meter outlet valve (FOV-3) from multiphase flow meter MFM-1051/1071 to production riser 1 & 3 at DCN

closed

xv-1001

Manifold test valve (MTV-7) from multiphase flow meters outlet to production riser No. 3 at DCN

closed

xv-1002

Manifold test valve (MTV-8) from multiphase flow meters outlet to production riser No. 1 AT DCN

closed

xv-2003

Flow meter inlet valve (FIV-1) to multiphase flow meter MFM-2051 at DCS

closed

xv-2004

Flow meter inlet valve (FIV-2) to multiphase flow meter MFM-2071 at DCS

closed

fov-1

Flow meter outlet valve (FOV-1) from multiphase flow meter MFM-2051 at DCS

closed

fov-2

Flow meter outlet valve (FOV-2) from multiphase flow meter MFM-2071 at DCS

closed

fov-3

Flow meter outlet valve (FOV-3) from multiphase flow meter MFM-2051/2071 to production riser 1 & 3 at DCS

closed

xv-2001

Manifold test valve (MTV-7) from multiphase flow meters outlet to production riser No. 5 at DCS

closed

xv-2002

Manifold test valve (MTV-8) from multiphase flow meters outlet to production riser No. 3 at DCS

closed

FTA Valve

Flow line termination assembly isolation valves (Two No.) on riser no 1

open

FTA Valve

Flow line termination assembly isolation valves (Two No.) on riser no 3

close

FTA Valve

Flow line termination assembly isolation valves (Two No.) on riser no 5

open

For the line up rest of the valves from swivel manifold to topside up to IP separator refer section 5.1.2 of Doc. No. 1072-MI20-OPM1-12

Cold start-up Valve Checklist

Gas Lift System

(Refer to P&ID DWG No 1072-MI20-9020-0118,6219-PD-19-01-00001, BAO-CNR-SU-PID-00187-01 , BAO-CNR-SU-PID-00187-02, BAO-CNR-SU-PID-00187-04 & BAO-CNR-SU-PID-00187-06)

6"-pg-f1-1200/ 6" f2jfk

Upstream isolation valves of FT-2425-1 from 3rd stage booster gas compressor to gas lift header

CLOSED

6"-pg-f1-1200/ 6" f2jfk

Downstream isolation valves of FT-2425-1 from 3rd stage booster gas compressor to gas lift header

locked open

3" f2jrdk

FT-2425-1 bypass valve

locked close

1" f2zf

Bypass valve across the check valve on line no. 6"-PG-F-5801

locked close

6"-PG-F-5801/ SDV-0230-1

Shutdown valve downstream of gas lift swivel (TU-FAS-0816)

OPen

6"-pg-f-5801

Isolation valve downstream of SDV-0230-1 from turret to riser

open

fta valve

Flow termination assembly (FTA) isolation valves (Two No.)on gas lift riser No. 4

open

ISOLATION VALVE

Isolation valve from 6" subsea gas lift pipe line to DCN manifold

open

xv-1111

Gas lift valve (GLV-1) to production tree No. 11

open

pcv-1113

Choke valve at the inlet of production tree No. 11

closed

xv-1113

Annulus wing valve (AWV) down stream of choke valve of tree No.11

open

xv-1103

Annulus master valve (AMV) in the annulus line in production tree No. 11

open

xv-1107

XOV on tree no 11

closed

aiv,aav

Annulus insert & access valve on production tree No.11

closed

The valve status for gas lift system for the other production tree No. 12,13,14,15,16,21,22,23,24,25 & 26 will be same as given above for tree No. 11

Water Injection System

(Refer to P&ID DWG No 1072-MI20-9020-0146,6220-PD-20-01-00001, BAO-CNR-SU-PID-00186-01 & BAO-CNR-SU-PID-00186-02)

6"-wi-f-2117/  6" f2jrd

Sea water injection pump (PAT-3020A/B/C/D/E/F) discharge isolation valve

open

6"-wi-f-2117/  sdv-3020a

Sea water injection pump (PAT-3020A/B/C/D/E/F) discharge shutdown valve

open

12"-wi-f-2804/ 12" f2jfk

Isolation valve Downstream of water injection swivel (TU-FAT-0818) to water injection riser No. 12

open

pcv-3114

Choke valve in water injection line in the injection tree No. 31

closed

xv-3102

Injection wing valve (IWV) downstream of choke valve in the injection tree No. 31

open

xv-3101

Injection master valve downstream of choke valve in the injection tree No. 31

open

xov-3107

Cross over valve on injection tree No. 31

closed

aiv,aav

Annulus insert and access valve on injection tree no. 31

closed

The valve status for the other water injection tree Nos. 32,33,34,41,42,43 & 44 are the same as given above for tree No. 31

Cold Start-up Overrides

During the cold Start-up of the production wells, gas injection and water injection system the following inputs to the shutdown system may require to be overridden at the Shutdown Panel in the Central Control Room until steady operating conditions are established.refer also Doc. No. 1072-MI20-OPM1-10 for topside overrides :

Table Cold Start-up Overrides (Production Wells)

Switch

Function

Parent Equipment

PALL-0030-2

Production riser No. 5 pressure Low Low

TU-FAY-0030

PALL-0032-2

Production riser No. 3 pressure Low Low

TU-FAY-0032

PALL-0031-2

Production riser No. 1 pressure Low Low

TU-FAY-0031

Table Cold Start-up Overrides (Gas Lift)

Switch

Function

Parent Equipment

PALL-2410-3

3rd stage booster gas compressor discharge line (Gas import/export line)

Line No. 8"-PG-F1-1243

PALL-0230-2

Gas lift riser pressure Low Low

TU-FAS-0230

Table Cold Start-up Overrides (Water Injection)

Switch

Function

Parent Equipment

PALL-3020A/B/C/D/E/F-3

Sea water injection pump discharge pressure Low Low

PAT-3020A/B/C/D/E/F

Cold Start-up Procedure

Table Cold Start-up Procedure Following a Planned Shutdown (Production Wells)

Cold Start-up Procedure following a Planned Shutdown

STEP

DESCRIPTION

LOCAL

CCR

Confirm that all valves are aligned as per the Cold Start-up Valve Checklist and all overrides are on for production wells

Confirm that all controllers are in automatic mode and are set to control the process at the process set point.

Ensure that all control valves are at their process control set points and functional e.g., Instrument air regulators.

Confirm that flare systems are operational

The hydraulic power system is operational

Confirm that H.P. production separator ready to receive well fluids

Heating medium system is ready to supply heating fluid to inlet production heaters (HBG-1055A/B) and crude heater (HZZ-1115)

Fill up the I.P. separator by diesel from diesel storage tank by hose connection

Line up the IP separator to flow line circulation pump (PBE-1210) and start the flow line circulation pump.

The diesel will fill the production riser and subsea flowlines upto the choke valve of production X-Mass Tree. The diesel will circulated back to I.P. separator via H.P. separator

Open the inlet isolation valve of heating medium line to inlet production heater and crude heater and start heating of diesel

Gradually the diesel become hot and the hot diesel will be circulated by flow line circulation pump to fill the enteir subsea production flow lines upto IP separator by hot diesel. This will prevent the enteir pipe network from wax deposit or coagulation of crude due to low temperature may be occure due to crude oil flushing in the subsea lines.

When the hot diesel return temperature reaches around 40°C (maximum is 55°C) then stop the flow line circulation pump and isolate the flowline circulation system. Gradually open the choke valve from subsea control unit (SCU) and the crude from the well head will displace the hot diesel and move forward through the subsea production riser and finally at the H.P. production separator on topside.

When the crude reaches at IP separator the normal line up of IP separator crude to electrostatic treater should be established.

Observe the dry crude quality coming out from the crude/crude exchanger based on that the crude will send to either storage tanker at hull or off spec tank

Remove the overrides listed in cold start-up overrides.

When a stable operation is established, check the temperature and pressure in the subsea system from SCU and DCS

Monitor all temperatures and pressures in the system.

Table 18 Cold Start-up Procedure Following a Planned Shutdown (Gas LIft)

Cold Start-up Procedure following a Planned Shutdown

STEP

DESCRIPTION

LOCAL

CCR

Confirm that there is a requirement of gas lift to the production well. Check all valves are aligned as per the Cold Start-up Valve Checklist and all overrides are on for gas lift system

Confirm that all controllers are in automatic mode and are set to control the process at the process set point.

Ensure that all control valves are at their process control set points and functional e.g., Instrument air regulators.

Confirm that flare systems are operational

The hydraulic power system is operational

Confirm that 3rd stage Booster Compressors are in normal operation

Open the inlet isolation valve of FE-2425-1

Observe the pressure developed upstream of choke valve through pressure transmitter in the gas lift line in production tree. If the required pressure is establish open the choke valve on gas lift line and observe the flow from venturi flowmeter upsrteam of choke valve.

Remove the overrides listed in cold start-up overrides.

When a stable operation is established, check the temperature, pressure and flow in the gas lift system from SCU and DCS

Monitor all temperatures and pressures in the system.

Table 19 Cold Start-up Procedure Following a Planned Shutdown (Water Injection)

Cold Start-up Procedure following a Planned Shutdown

STEP

DESCRIPTION

LOCAL

CCR

Confirm that there is a requirement of water injection to the injection well. Check all valves are aligned as per the Cold Start-up Valve Checklist and all overrides are on for water injection system

Confirm that all controllers are in automatic mode and are set to control the process at the process set point.

Ensure that all control valves are at their process control set points and functional e.g., Instrument air regulators.

The hydraulic power system is operational

Confirm that sea water lift and treatment system are in normal operation.

Start the sea water injection pump (PAT-3020A/B/C/D/E/F)

Observe the pressure developed upstream of choke valve through pressure transmitters in the water injection tree. If the required pressure is establish open the choke valve on the water injection line and observe the flow from venturi flowmeter upsrteam of choke valve.

Remove the overrides listed in cold start-up overrides.

When a stable operation is established, check the temperature, pressure and flow in the gas lift system from SCU and DCS

Monitor all temperatures, pressures and flows in the system.

Hot Start-up Procedure Following a Process Trip

The following hot start-up procedure details the steps to be taken to re-start the Subsea flow line and riser system facilities following a system trip.

The procedure assumes all the facilities listed below have been operating normally but have shutdown as a result of a system trip or by manual initiation.

The reason for the shutdown has been investigated and rectified and it is considered safe to re-start the system.

The pressures, temperatures and flow within the Subsea system are at or near normal conditions.

The following conditions are assumed to exist in executing this procedure: -

No Permits to Work are in force on any part of the system that may prohibit, or hinder, the safe start-up of the equipment.

The Fire and Gas Detection System, ESD Systems and control facilities within the CCR are operational including all alarms, trips and controllers.

It is assumed that in a short duration shutdown it is unlikely that spades or blinds would be moved, or drain and vent valves opened unless required to take corrective action on the cause of the shutdown. It is therefore unnecessary to recheck these items other than if they have been disturbed.

All vents, purge points and manual sample points are closed and blanked, or capped off, where necessary.

Communications have been established between all the personnel involved with the start-up procedure.

Safety/Briefing Meetings have been held with all directly concerned parties outlining the workscope and procedures.

The following Utility and Ancillary Systems are available:

Electrical Power Distribution

Instrument Air

Hydraulic power

Booster gas compressors

Sea water lift and treatment

Hot Start-up Procedure

During the Hot Start-up of the Subsea System there should be no requirement to have any input over-ride to the to the shutdown system.

Note-1: This procedure assumes that the temperature of the system has not dropped significantly so there is no requirements to hot oil circulation.

Table Hot Start-up Procedure Following a System Trip (Production Wells)

Hot Start-Up Procedure Following A System Trip

STEP

DESCRIPTION

LOCAL

cCR

Confirm that the valves are aligned as per Cold Start-up Valve checklist.

Confirm that all controllers are in automatic mode and are set to control at the process set point.

Start openning of the choke valve at the production tree

Ensure that well fluids are flowing to the HP separator by observing the level increased in HP separator.

Monitor all temperatures, pressures and flows in the system.

Table 21 Hot Start-up Procedure Following a System Trip (Gas Lift)

Hot Start-Up Procedure Following A System Trip

STEP

DESCRIPTION

LOCAL

cCR

Confirm that the valves are aligned as per Cold Start-up Valve checklist.

Confirm that all controllers are in automatic mode and are set to control at the process set point.

Confirm that Booster Gas Compressor is running

Observed the required pressure developed upstream of the choke valve through pressure transmitter on the gas lift line up stream of choke valve

Once the pressure is established start openning of the choke valve at the production tree of gas lift line

Ensure that gas is flowing to the production well by observing the flow meter upstream of choke valve on the gas lift line.

Monitor all temperatures, pressures and flows in the system.

Table 22 Hot Start-up Procedure Following a System Trip (Water Injection)

Hot Start-Up Procedure Following A System Trip

STEP

DESCRIPTION

LOCAL

cCR

Confirm that the valves are aligned as per Cold Start-up Valve checklist.

Confirm that all controllers are in automatic mode and are set to control at the process set point.

Start the sea water injection pump

Observed the required pressure developed upstream of the choke valve through pressure transmitter on the water injection line up stream of choke valve

Start openning of the choke valve at the injection tree

Ensure that water is injected to the injection well by observing the flow meter upstream of choke valve on the water injection line.

Monitor all temperatures, pressures and flows in the system.

Normal Operational Checks:

The normal operational conditions, together with alarm and trip set points for each item in the Subsea system are provided in section 6.0.

On a regular basis the field operator should conduct the following routine checks:

Check all pressures, temperatures and flows in the subsea system.

Planned Shutdown procedure

The following procedure details the steps to be taken to conduct a planned shutdown of the Subsea System as part of an overall shutdown of the FPSO process facilities in preparation for inspection / maintenance activities.

The following conditions are assumed to exist in executing this procedure: -

Safety / Briefing Meetings have been held with all directly concerned parties outlining the workscope and procedures.

Communications have been established between all persons involved in this procedure.

o        No operations or Permits to Work are in force that may prohibit the shutdown of the system.

Table Planned Shutdown Procedure (Production Wells)

Planned Shutdown Procedure

STEP

DESCRIPTION

LOCAL

CCR

Ensure that the due to some reason reservoir fluid should not come to the topside for processing

Close the individual choke valve of production tree

Observe that the level is decreasing in the HP separator

Close the inlet isolation valves of the HP separator before the Low Low liquid level achieved in the HP separator

If long term shutdown is required then line up the IP separator to flow line circulation pump. Start the flow line circulation pump and fill the entire subsea flow line with hot oil taking from IP separator. See Doc. No. 1072-MI20-OPM1-12 for flow line operation details

Table 24 Planned Shutdown Procedure (Gas LIft)

Planned Shutdown Procedure

STEP

DESCRIPTION

LOCAL

CCR

Ensure that there is no requirement of gas lift system.

Close the inlet isolation valve of FE-2425-1 on the gas lift line. Now all gas will be exported via gas import / export riser

*

Depressurised the gas lift header by opening the BDV-2425-4 to HP flare.

Observe that the gas pressure in the gas lift line decreasing by observing the pressure transmitter upstream of the choke valve in the gas lift line of the production tree.

Close the choke valve of the individual gas lift line in each production tree.

If some specific production well required to stop gas lift facility then close those specific choke valve of the gas lift line of the respective production tree and rest remain the same like normal operation. 

Table 25 Planned Shutdown Procedure (Water Injection)

Planned Shutdown Procedure

STEP

DESCRIPTION

LOCAL

CCR

Ensure that the water injection need not required for some reason or maintenance work required to do for this system so water injection system required to shut down.

Stop the sea water injection pumps

Observe that the pressure is decreasing in the water injection line down stream of choke valve on the injection tree.

Close the SDV-3020A-19 on the discharge line of the injection pump.

Emergency Controlled Shutdown Procedure

The following procedure details the steps to be taken to conduct an emergency controlled shutdown of the Gas Dehydration system.

Plant Status -The assumption is that an upset condition has occurred on the process or downstream facilities detected by the automatic shutdown systems, that requires the immediate controlled shutdown of the Gas Dehydration system by the ESD system. There should be no cause for intervention by operators.

Table 26 Emergency Controlled Shutdown Procedure

Emergency Controlled Shutdown Procedure

STEP

DESCRIPTION

LOCAL

CCR

The Subsea System is shutdown as part of the process shutdown systems onboard. As per the Cause & Effect listings for ASD, ESD & PSD.

After a Process trip occurs and the Facility has been confirmed as being in a safe condition, the operator in conjunction with the Control Room should confirm that outputs as listed in the C&E charts have effected as per the shutdown philosophy, prior to production restart.

Alarm, Trip and PSV Settings

Table Alarm, Trip & Settings (Production Wells)

EQUIPMENT

production well

TAG NO

Alarm Type

DESCRIPTION

alarm/ TRIP set points

PSV set points

Production X-Mass Tree Pressure

SS-PT-1121

PAL

Pressure Alarm Low -Tree No. 11

200 bara

SS-PT-1121

PAH

Pressure Alarm High -Tree No. 11

250 bara

SS-PT-1122

PAL

Pressure Alarm Low -Tree No. 11

200 bara

SS-PT-1122

PAH

Pressure Alarm High -Tree No. 11

250 bara

SS-PT-1123

PAL

Pressure Alarm Low -Tree No. 11

200 bara

SS-PT-1123

PAH

Pressure Alarm High -Tree No. 11

250 bara

SS-PT-1124

PAL

Pressure Alarm Low -Tree No. 11

200 bara

SS-PT-1124

PAH

Pressure Alarm High -Tree No. 11

250 bara

SS-PT-1221

PAL

Pressure Alarm Low -Tree No. 12

200 bara

SS-PT-1221

PAH

Pressure Alarm High -Tree No. 12

250 bara

SS-PT-1222

PAL

Pressure Alarm Low -Tree No. 12

200 bara

SS-PT-1222

PAH

Pressure Alarm High -Tree No. 12

250 bara

SS-PT-1223

PAL

Pressure Alarm Low -Tree No. 12

200 bara

SS-PT-1223

PAH

Pressure Alarm High -Tree No. 12

250 bara

SS-PT-1224

PAL

Pressure Alarm Low -Tree No. 12

200 bara

SS-PT-1224

PAH

Pressure Alarm High -Tree No. 12

250 bara

SS-PT-1321

PAL

Pressure Alarm Low -Tree No. 13

200 bara

SS-PT-1321

PAH

Pressure Alarm High -Tree No. 13

250 bara

SS-PT-1322

PAL

Pressure Alarm Low -Tree No. 13

200 bara

SS-PT-1322

PAH

Pressure Alarm High -Tree No. 13

250 bara

SS-PT-1323

PAL

Pressure Alarm Low -Tree No. 13

200 bara

SS-PT-1323

PAH

Pressure Alarm High -Tree No. 13

250 bara

SS-PT-1324

PAL

Pressure Alarm Low -Tree No. 13

200 bara

SS-PT-1324

PAH

Pressure Alarm High -Tree No. 13

250 bara

SS-PT-1421

PAL

Pressure Alarm Low -Tree No. 14

200 bara

SS-PT-1421

PAH

Pressure Alarm High -Tree No. 14

250 bara

SS-PT-1422

PAL

Pressure Alarm Low -Tree No. 14

200 bara

SS-PT-1422

PAH

Pressure Alarm High -Tree No. 14

250 bara

SS-PT-1423

PAL

Pressure Alarm Low -Tree No. 14

200 bara

SS-PT-1423

PAH

Pressure Alarm High -Tree No. 14

250 bara

SS-PT-1424

PAL

Pressure Alarm Low -Tree No. 14

200 bara

SS-PT-1424

PAH

Pressure Alarm High -Tree No. 14

250 bara

SS-PT-1521

PAL

Pressure Alarm Low -Tree No. 15

200 bara

SS-PT-1521

PAH

Pressure Alarm High -Tree No. 15

250 bara

SS-PT-1522

PAL

Pressure Alarm Low -Tree No. 15

200 bara

SS-PT-1522

PAH

Pressure Alarm High -Tree No. 15

250 bara

SS-PT-1523

PAL

Pressure Alarm Low -Tree No. 15

200 bara

SS-PT-1523

PAH

Pressure Alarm High -Tree No. 15

250 bara

SS-PT-1524

PAL

Pressure Alarm Low -Tree No. 15

200 bara

SS-PT-1524

PAH

Pressure Alarm High -Tree No. 15

250 bara

SS-PT-1621

PAL

Pressure Alarm Low -Tree No. 16

200 bara

SS-PT-1621

PAH

Pressure Alarm High -Tree No. 16

250 bara

SS-PT-1622

PAL

Pressure Alarm Low -Tree No. 16

200 bara

SS-PT-1622

PAH

Pressure Alarm High -Tree No. 16

250 bara

SS-PT-1623

PAL

Pressure Alarm Low -Tree No. 16

200 bara

SS-PT-1623

PAH

Pressure Alarm High -Tree No. 16

250 bara

SS-PT-1624

PAL

Pressure Alarm Low -Tree No. 16

200 bara

SS-PT-1624

PAH

Pressure Alarm High -Tree No. 16

250 bara

SS-PT-1021

PAL

Pressure Alarm Low -Production Riser No. 3

200 bara

SS-PT-1021

PAH

Pressure Alarm High - Production Riser No. 3

250 bara

SS-PT-1022

PAL

Pressure Alarm Low -Production Riser No. 1

200 bara

SS-PT-1022

PAH

Pressure Alarm High - Production Riser No. 1

250 bara

SS-PT-2121

PAL

Pressure Alarm Low -Tree No. 21

200 bara

SS-PT-2121

PAH

Pressure Alarm High -Tree No. 21

250 bara

SS-PT-2122

PAL

Pressure Alarm Low -Tree No. 21

200 bara

SS-PT-2122

PAH

Pressure Alarm High -Tree No. 21

250 bara

SS-PT-2123

PAL

Pressure Alarm Low -Tree No. 21

200 bara

SS-PT-2123

PAH

Pressure Alarm High -Tree No. 21

250 bara

SS-PT-2124

PAL

Pressure Alarm Low -Tree No. 21

200 bara

SS-PT-2124

PAH

Pressure Alarm High -Tree No. 21

250 bara

SS-PT-2221

PAL

Pressure Alarm Low -Tree No. 22

200 bara

SS-PT-2221

PAH

Pressure Alarm High -Tree No. 22

250 bara

SS-PT-2222

PAL

Pressure Alarm Low -Tree No. 22

200 bara

SS-PT-2222

PAH

Pressure Alarm High -Tree No. 22

250 bara

SS-PT-2223

PAL

Pressure Alarm Low -Tree No. 22

200 bara

SS-PT-2223

PAH

Pressure Alarm High -Tree No. 22

250 bara

SS-PT-2224

PAL

Pressure Alarm Low -Tree No. 22

200 bara

SS-PT-2224

PAH

Pressure Alarm High -Tree No. 22

250 bara

SS-PT-2321

PAL

Pressure Alarm Low -Tree No. 23

200 bara

SS-PT-2321

PAH

Pressure Alarm High -Tree No. 23

250 bara

SS-PT-2322

PAL

Pressure Alarm Low -Tree No. 23

200 bara

SS-PT-2322

PAH

Pressure Alarm High -Tree No. 23

250 bara

SS-PT-2323

PAL

Pressure Alarm Low -Tree No. 23

200 bara

SS-PT-2323

PAH

Pressure Alarm High -Tree No. 23

250 bara

SS-PT-2324

PAL

Pressure Alarm Low -Tree No. 23

200 bara

SS-PT-2324

PAH

Pressure Alarm High -Tree No. 23

250 bara

SS-PT-2421

PAL

Pressure Alarm Low -Tree No. 24

200 bara

SS-PT-2421

PAH

Pressure Alarm High -Tree No. 24

250 bara

SS-PT-2422

PAL

Pressure Alarm Low -Tree No. 24

200 bara

SS-PT-2422

PAH

Pressure Alarm High -Tree No. 24

250 bara

SS-PT-2423

PAL

Pressure Alarm Low -Tree No. 24

200 bara

SS-PT-2423

PAH

Pressure Alarm High -Tree No. 24

250 bara

SS-PT-2424

PAL

Pressure Alarm Low -Tree No. 24

200 bara

SS-PT-2424

PAH

Pressure Alarm High -Tree No. 24

250 bara

SS-PT-2521

PAL

Pressure Alarm Low -Tree No. 25

200 bara

SS-PT-2521

PAH

Pressure Alarm High -Tree No. 25

250 bara

SS-PT-2522

PAL

Pressure Alarm Low -Tree No. 25

200 bara

SS-PT-2522

PAH

Pressure Alarm High -Tree No. 25

250 bara

SS-PT-2523

PAL

Pressure Alarm Low -Tree No. 25

200 bara

SS-PT-2523

PAH

Pressure Alarm High -Tree No. 25

250 bara

SS-PT-2524

PAL

Pressure Alarm Low -Tree No. 25

200 bara

SS-PT-2524

PAH

Pressure Alarm High -Tree No. 25

250 bara

SS-PT-2621

PAL

Pressure Alarm Low -Tree No. 26

200 bara

SS-PT-2621

PAH

Pressure Alarm High -Tree No. 26

250 bara

SS-PT-2622

PAL

Pressure Alarm Low -Tree No. 26

200 bara

SS-PT-2622

PAH

Pressure Alarm High -Tree No. 26

250 bara

SS-PT-2623

PAL

Pressure Alarm Low -Tree No. 26

200 bara

SS-PT-2623

PAH

Pressure Alarm High -Tree No. 26

250 bara

SS-PT-2624

PAL

Pressure Alarm Low -Tree No. 26

200 bara

SS-PT-2624

PAH

Pressure Alarm High -Tree No. 26

250 bara

SS-PT-2021

PAL

Pressure Alarm Low -Production Riser No. 5

200 bara

SS-PT-2021

PAH

Pressure Alarm High - Production Riser No. 5

250 bara

SS-PT-2022

PAL

Pressure Alarm Low -Production Riser No. 3

200 bara

SS-PT-2022

PAH

Pressure Alarm High - Production Riser No. 3

250 bara

TU-PI-0031-2

PALL

Pressure Alarm Low Low - production riser No. 1

(HOLD)

TU-PI-0031-2

PAHH

Pressure Alarm High High - production riser No. 1

(HOLD)

TU-PI-0032-2

PALL

Pressure Alarm Low Low - production riser No. 3

(HOLD)

TU-PI-0032-2

PAHH

Pressure Alarm High High - production riser No. 3

(HOLD)

TU-PI-0030-2

PALL

Pressure Alarm Low Low - production riser No. 5

(HOLD)

TU-PI-0030-2

PAHH

Pressure Alarm High High - production riser No. 5

(HOLD)

TU-PI-0810-1

PAH

Pressure Alarm High-Swivel Manifold Header (20"-PF-F1-5618)

(HOLD)

TU-PI-0810-2

PAH

Pressure Alarm High-Swivel Manifold Header (20"-PF-F1-5618)

(HOLD)

TU-PI-0811-1

PAH

Pressure Alarm High-Swivel Manifold Header (20"-PF-F1-5618)

(HOLD)

TU-PI-0812-1

PAH

Pressure Alarm High-Swivel Manifold Header (20"-PF-F1-5618)

(HOLD)

Production X-Mass Tree Temperature

SS-TT-1121

TAL

Temperature Alarm Low -Tree No. 11

50°C

SS-TT-1121

TAH

Temperature Alarm High -Tree No. 11

80°C

SS-TT-1122

TAL

Temperature Alarm Low -Tree No. 11

50°C

SS-TT-1122

TAH

Temperature Alarm High -Tree No. 11

80°C

SS-TT-1123

TAL

Temperature Alarm Low -Tree No. 11

50°C

SS-TT-1123

TAH

Temperature Alarm High -Tree No. 11

80°C

SS-TT-1124

TAL

Temperature Alarm Low -Tree No. 11

50°C

SS-TT-1124

TAH

Temperature Alarm High -Tree No. 11

80°C

SS-TT-1221

TAL

Temperature Alarm Low -Tree No. 12

50°C

SS-TT-1221

TAH

Temperature Alarm High -Tree No. 12

80°C

SS-TT-1222

TAL

Temperature Alarm Low -Tree No. 12

50°C

SS-TT-1222

TAH

Temperature Alarm High -Tree No. 12

80°C

SS-TT-1223

TAL

Temperature Alarm Low -Tree No. 12

50°C

SS-TT-1223

TAH

Temperature Alarm High -Tree No. 12

80°C

SS-TT-1224

TAL

Temperature Alarm Low -Tree No. 12

50°C

SS-TT-1224

TAH

Temperature Alarm High -Tree No. 12

80°C

SS-TT-1321

TAL

Temperature Alarm Low -Tree No. 13

50°C

SS-TT-1321

TAH

Temperature Alarm High -Tree No. 13

80°C

SS-TT-1322

TAL

Temperature Alarm Low -Tree No. 13

50°C

SS-TT-1322

TAH

Temperature Alarm High -Tree No. 13

80°C

SS-TT-1323

TAL

Temperature Alarm Low -Tree No. 13

50°C

SS-TT-1323

TAH

Temperature Alarm High -Tree No. 13

80°C

SS-TT-1324

TAL

Temperature Alarm Low -Tree No. 13

50°C

SS-TT-1324

TAH

Temperature Alarm High -Tree No. 13

80°C

SS-TT-1421

TAL

Temperature Alarm Low -Tree No. 14

50°C

SS-TT-1421

TAH

Temperature Alarm High -Tree No. 14

80°C

SS-TT-1422

TAL

Temperature Alarm Low -Tree No. 14

50°C

SS-TT-1422

TAH

Temperature Alarm High -Tree No. 14

80°C

SS-TT-1423

TAL

Temperature Alarm Low -Tree No. 14

50°C

SS-TT-1423

TAH

Temperature Alarm High -Tree No. 14

80°C

SS-TT-1424

TAL

Temperature Alarm Low -Tree No. 14

50°C

SS-TT-1424

TAH

Temperature Alarm High -Tree No. 14

80°C

SS-TT-1521

TAL

Temperature Alarm Low -Tree No. 15

50°C

SS-TT-1521

TAH

Temperature Alarm High -Tree No. 15

80°C

SS-TT-1522

TAL

Temperature Alarm Low -Tree No. 15

50°C

SS-TT-1522

TAH

Temperature Alarm High -Tree No. 15

80°C

SS-TT-1523

TAL

Temperature Alarm Low -Tree No. 15

50°C

SS-TT-1523

TAH

Temperature Alarm High -Tree No. 15

80°C

SS-TT-1524

TAL

Temperature Alarm Low -Tree No. 15

50°C

SS-TT-1524

TAH

Temperature Alarm High -Tree No. 15

80°C

SS-TT-1621

TAL

Temperature Alarm Low -Tree No. 16

50°C

SS-TT-1621

TAH

Temperature Alarm High -Tree No. 16

80°C

SS-TT-1622

TAL

Temperature Alarm Low -Tree No. 16

50°C

SS-TT-1622

TAH

Temperature Alarm High -Tree No. 16

80°C

SS-TT-1623

TAL

Temperature Alarm Low -Tree No. 16

50°C

SS-TT-1623

TAH

Temperature Alarm High -Tree No. 16

80°C

SS-TT-1624

TAL

Temperature Alarm Low -Tree No. 16

50°C

SS-TT-1624

TAH

Temperature Alarm High -Tree No. 16

80°C

SS-TT-1021

TAL

Temperature Alarm Low -Production Riser No. 3 (DCN)

50°C

SS-TT-1021

TAH

Temperature Alarm High - Production Riser No. 3 (DCN)

80°C

SS-TT-1022

TAL

Temperature Alarm Low -Production Riser No. 1

50°C

SS-TT-1022

TAH

Temperature Alarm High - Production Riser No. 1

80°C

SS-TT-2121

TAL

Temperature Alarm Low -Tree No. 21

50°C

SS-TT-2121

TAH

Temperature Alarm High -Tree No. 21

80°C

SS-TT-2122

TAL

Temperature Alarm Low -Tree No. 21

50°C

SS-TT-2122

TAH

Temperature Alarm High -Tree No. 21

80°C

SS-TT-2123

TAL

Temperature Alarm Low -Tree No. 21

50°C

SS-TT-2123

TAH

Temperature Alarm High -Tree No. 21

80°C

SS-TT-2124

TAL

Temperature Alarm Low -Tree No. 21

50°C

SS-TT-2124

TAH

Temperature Alarm High -Tree No. 21

80°C

SS-TT-2221

TAL

Temperature Alarm Low -Tree No. 22

50°C

SS-TT-2221

TAH

Temperature Alarm High -Tree No. 22

80°C

SS-TT-2222

TAL

Temperature Alarm Low -Tree No. 22

50°C

SS-TT-2222

TAH

Temperature Alarm High -Tree No. 22

80°C

SS-TT-2223

TAL

Temperature Alarm Low -Tree No. 22

50°C

SS-TT-2223

TAH

Temperature Alarm High -Tree No. 22

80°C

SS-TT-2224

TAL

Temperature Alarm Low -Tree No. 22

50°C

SS-TT-2224

TAH

Temperature Alarm High -Tree No. 22

80°C

SS-TT-2321

TAL

Temperature Alarm Low -Tree No. 23

50°C

SS-TT-2321

TAH

Temperature Alarm High -Tree No. 23

80°C

SS-TT-2322

TAL

Temperature Alarm Low -Tree No. 23

50°C

SS-TT-2322

TAH

Temperature Alarm High -Tree No. 23

80°C

SS-TT-2323

TAL

Temperature Alarm Low -Tree No. 23

50°C

SS-TT-2323

TAH

Temperature Alarm High -Tree No. 23

80°C

SS-TT-2324

TAL

Temperature Alarm Low -Tree No. 23

50°C

SS-TT-2324

TAH

Temperature Alarm High -Tree No. 23

80°C

SS-TT-2421

TAL

Temperature Alarm Low -Tree No. 24

50°C

SS-TT-2421

TAH

Temperature Alarm High -Tree No. 24

80°C

SS-TT-2422

TAL

Temperature Alarm Low -Tree No. 24

50°C

SS-TT-2422

TAH

Temperature Alarm High -Tree No. 24

80°C

SS-TT-2423

TAL

Temperature Alarm Low -Tree No. 24

50°C

SS-TT-2423

TAH

Temperature Alarm High -Tree No. 24

80°C

SS-TT-2424

TAL

Temperature Alarm Low -Tree No. 24

50°C

SS-TT-2424

TAH

Temperature Alarm High -Tree No. 24

80°C

SS-TT-2521

TAL

Temperature Alarm Low -Tree No. 25

50°C

SS-TT-2521

TAH

Temperature Alarm High -Tree No. 25

80°C

SS-TT-2522

TAL

Temperature Alarm Low -Tree No. 25

50°C

SS-TT-2522

TAH

Temperature Alarm High -Tree No. 25

80°C

SS-TT-2523

TAL

Temperature Alarm Low -Tree No. 25

50°C

SS-TT-2523

TAH

Temperature Alarm High -Tree No. 25

80°C

SS-TT-2524

TAL

Temperature Alarm Low -Tree No. 25

50°C

SS-TT-2524

TAH

Temperature Alarm High -Tree No. 25

80°C

SS-TT-2621

TAL

Temperature Alarm Low -Tree No. 26

50°C

SS-TT-2621

TAH

Temperature Alarm High -Tree No. 26

80°C

SS-TT-2622

TAL

Temperature Alarm Low -Tree No. 26

50°C

SS-TT-2622

TAH

Temperature Alarm High -Tree No. 26

80°C

SS-TT-2623

TAL

Temperature Alarm Low -Tree No. 26

50°C

SS-TT-2623

TAH

Temperature Alarm High -Tree No. 26

80°C

SS-TT-2624

TAL

Temperature Alarm Low -Tree No. 26

50°C

SS-TT-2624

TAH

Temperature Alarm High -Tree No. 26

80°C

SS-TT-2021

TAL

Temperature Alarm Low -Production Riser No. 5

50°C

SS-TT-2021

TAH

Temperature Alarm High - Production Riser No. 5

80°C

SS-TT-2022

TAL

Temperature Alarm Low -Production Riser No. 3 (DCS)

50°C

SS-TT-2022

TAH

Temperature Alarm High - Production Riser No. 3 (DCS)

80°C

TU-TI-0031-4

TAL

Temperature Alarm Low - production riser No. 1

(HOLD)

TU-TI-0031-4

TAH

Temperature Alarm High - production riser No. 1

(HOLD)

TU-TI-0032-4

TAL

Temperature Alarm Low - production riser No. 3

(HOLD)

TU-TI-0032-4

TAH

Temperature Alarm High - production riser No. 3

(HOLD)

TU-TI-0030-4

TAL

Temperature Alarm Low - production riser No. 5

(HOLD)

TU-TI-0030-4

TAH

Temperature Alarm High - production riser No. 5

(HOLD)

Table Alarm, Trip & Settings (Gas Lift)

EQUIPMENT

production Tree

TAG NO

Alarm Type

DESCRIPTION

alarm/ TRIP set points

PSV set points

Production X-Mass Tree gas Lift Pressure

SS-PT-1125

PAL

Pressure Alarm Low -Tree No. 11

200 bara

SS-PT-1125

PAH

Pressure Alarm High -Tree No. 11

250 bara

SS-PT-1126

PAL

Pressure Alarm Low -Tree No. 11

200 bara

SS-PT-1126

PAH

Pressure Alarm High -Tree No. 11

250 bara

SS-PT-1225

PAL

Pressure Alarm Low -Tree No. 12

200 bara

SS-PT-1225

PAH

Pressure Alarm High -Tree No. 12

250 bara

SS-PT-1226

PAL

Pressure Alarm Low -Tree No. 12

200 bara

SS-PT-1226

PAH

Pressure Alarm High -Tree No. 12

250 bara

SS-PT-1325

PAL

Pressure Alarm Low -Tree No. 13

200 bara

SS-PT-1325

PAH

Pressure Alarm High -Tree No. 13

250 bara

SS-PT-1326

PAL

Pressure Alarm Low -Tree No. 13

200 bara

SS-PT-1326

PAH

Pressure Alarm High -Tree No. 13

250 bara

SS-PT-1425

PAL

Pressure Alarm Low -Tree No. 14

200 bara

SS-PT-1425

PAH

Pressure Alarm High -Tree No. 14

250 bara

SS-PT-1426

PAL

Pressure Alarm Low -Tree No. 14

200 bara

SS-PT-1426

PAH

Pressure Alarm High -Tree No. 14

250 bara

SS-PT-1525

PAL

Pressure Alarm Low -Tree No. 15

200 bara

SS-PT-1525

PAH

Pressure Alarm High -Tree No. 15

250 bara

SS-PT-1526

PAL

Pressure Alarm Low -Tree No. 15

200 bara

SS-PT-1526

PAH

Pressure Alarm High -Tree No. 15

250 bara

SS-PT-1625

PAL

Pressure Alarm Low -Tree No. 16

200 bara

SS-PT-1625

PAH

Pressure Alarm High -Tree No. 16

250 bara

SS-PT-1626

PAL

Pressure Alarm Low -Tree No. 16

200 bara

SS-PT-1626

PAH

Pressure Alarm High -Tree No. 16

250 bara

SS-PT-1023

PAL

Pressure Alarm Low -Gas lift header DCN

200 bara

SS-PT-1023

PAH

Pressure Alarm High - Gas lift header DCN

250 bara

SS-PT-2125

PAL

Pressure Alarm Low -Tree No. 21

200 bara

SS-PT-2125

PAH

Pressure Alarm High -Tree No. 21

250 bara

SS-PT-2126

PAL

Pressure Alarm Low -Tree No. 21

200 bara

SS-PT-2126

PAH

Pressure Alarm High -Tree No. 21

250 bara

SS-PT-2225

PAL

Pressure Alarm Low -Tree No. 22

200 bara

SS-PT-2225

PAH

Pressure Alarm High -Tree No. 22

250 bara

SS-PT-2226

PAL

Pressure Alarm Low -Tree No. 22

200 bara

SS-PT-2226

PAH

Pressure Alarm High -Tree No. 22

250 bara

SS-PT-2325

PAL

Pressure Alarm Low -Tree No. 23

200 bara

SS-PT-2325

PAH

Pressure Alarm High -Tree No. 23

250 bara

SS-PT-2326

PAL

Pressure Alarm Low -Tree No. 23

200 bara

SS-PT-2326

PAH

Pressure Alarm High -Tree No. 23

250 bara

SS-PT-2425

PAL

Pressure Alarm Low -Tree No. 24

200 bara

SS-PT-2425

PAH

Pressure Alarm High -Tree No. 24

250 bara

SS-PT-2426

PAL

Pressure Alarm Low -Tree No. 24

200 bara

SS-PT-2426

PAH

Pressure Alarm High -Tree No. 24

250 bara

SS-PT-2525

PAL

Pressure Alarm Low -Tree No. 25

200 bara

SS-PT-2525

PAH

Pressure Alarm High -Tree No. 25

250 bara

SS-PT-2526

PAL

Pressure Alarm Low -Tree No. 25

200 bara

SS-PT-2526

PAH

Pressure Alarm High -Tree No. 25

250 bara

SS-PT-2625

PAL

Pressure Alarm Low -Tree No. 26

200 bara

SS-PT-2625

PAH

Pressure Alarm High -Tree No. 26

250 bara

SS-PT-2626

PAL

Pressure Alarm Low -Tree No. 26

200 bara

SS-PT-2626

PAH

Pressure Alarm High -Tree No. 26

250 bara

SS-TT-2023

PAH

Pressure Alarm High -Gas lift header at DCS

250 bara

SS-TT-2023

PAL

Pressure Alarm Low -Gas lift header at DCS

200 bara

TU-PI-0230-2

PALL

Pressure Alarm Low Low - gas lift riser No. 4

(HOLD)

TU-PI-0230-2

PAHH

Pressure Alarm High High - gas lift riser No. 4

(HOLD)

10M-PI-2410-3

PALL

Pressure Alarm Low Low - gas lift header

(HOLD)

Production X-Mass Tree gas Lift Temperature

SS-TT-1125

TAL

Temperature Alarm Low -Tree No. 11

50°C

SS-TT-1125

TAH

Temperature Alarm High -Tree No. 11

80°C

SS-TT-1126

TAL

Temperature Alarm Low -Tree No. 11

50°C

SS-TT-1126

TAH

Temperature Alarm High -Tree No. 11

80°C

SS-TT-1225

TAL

Temperature Alarm Low -Tree No. 12

50°C

SS-TT-1225

TAH

Temperature Alarm High -Tree No. 12

80°C

SS-TT-1226

TAL

Temperature Alarm Low -Tree No. 12

50°C

SS-TT-1226

TAH

Temperature Alarm High -Tree No. 12

80°C

SS-TT-1325

TAL

Temperature Alarm Low -Tree No. 13

50°C

SS-TT-1325

TAH

Temperature Alarm High -Tree No. 13

80°C

SS-TT-1326

TAL

Temperature Alarm Low -Tree No. 13

50°C

SS-TT-1326

TAH

Temperature Alarm High -Tree No. 13

80°C

SS-TT-1425

TAL

Temperature Alarm Low -Tree No. 14

50°C

SS-TT-1425

TAH

Temperature Alarm High -Tree No. 14

80°C

SS-TT-1426

TAL

Temperature Alarm Low -Tree No. 14

50°C

SS-TT-1426

TAH

Temperature Alarm High -Tree No. 14

80°C

SS-TT-1525

TAL

Temperature Alarm Low -Tree No. 15

50°C

SS-TT-1525

TAH

Temperature Alarm High -Tree No. 15

80°C

SS-TT-1526

TAL

Temperature Alarm Low -Tree No. 15

50°C

SS-TT-1526

TAH

Temperature Alarm High -Tree No. 15

80°C

SS-TT-1625

TAL

Temperature Alarm Low -Tree No. 16

50°C

SS-TT-1625

TAH

Temperature Alarm High -Tree No. 16

80°C

SS-TT-1626

TAL

Temperature Alarm Low -Tree No. 16

50°C

SS-TT-1626

TAH

Temperature Alarm High -Tree No. 16

80°C

SS-TT-1023

TAL

Temperature Alarm Low -Gas lift header DCN

50°C

SS-TT-1023

TAH

Temperature Alarm High - Gas lift header DCN

80°C

SS-TT-2125

TAL

Temperature Alarm Low -Tree No. 21

50°C

SS-TT-2125

TAH

Temperature Alarm High -Tree No. 21

80°C

SS-TT-2126

TAL

Temperature Alarm Low -Tree No. 21

50°C

SS-TT-2126

TAH

Temperature Alarm High -Tree No. 21

80°C

SS-TT-2225

TAL

Temperature Alarm Low -Tree No. 22

50°C

SS-TT-2225

TAH

Temperature Alarm High -Tree No. 22

80°C

SS-TT-2226

TAL

Temperature Alarm Low -Tree No. 22

50°C

SS-TT-2226

TAH

Temperature Alarm High -Tree No. 22

80°C

SS-TT-2325

TAL

Temperature Alarm Low -Tree No. 23

50°C

SS-TT-2325

TAH

Temperature Alarm High -Tree No. 23

80°C

SS-TT-2326

TAL

Temperature Alarm Low -Tree No. 23

50°C

SS-TT-2326

TAH

Temperature Alarm High -Tree No. 23

80°C

SS-TT-2425

TAL

Temperature Alarm Low -Tree No. 24

50°C

SS-TT-2425

TAH

Temperature Alarm High -Tree No. 24

80°C

SS-TT-2426

TAL

Temperature Alarm Low -Tree No. 24

50°C

SS-TT-2426

TAH

Temperature Alarm High -Tree No. 24

80°C

SS-TT-2525

TAL

Temperature Alarm Low -Tree No. 25

50°C

SS-TT-2525

TAH

Temperature Alarm High -Tree No. 25

80°C

SS-TT-2526

TAL

Temperature Alarm Low -Tree No. 25

50°C

SS-TT-2526

TAH

Temperature Alarm High -Tree No. 25

80°C

SS-TT-2625

TAL

Temperature Alarm Low -Tree No. 26

50°C

SS-TT-2625

TAH

Temperature Alarm High -Tree No. 26

80°C

SS-TT-2626

TAL

Temperature Alarm Low -Tree No. 26

50°C

SS-TT-2626

TAH

Temperature Alarm High -Tree No. 26

80°C

SS-TT-2023

TAL

Temperature Alarm High -Gas lift header at DCS

50°C

SS-TT-2023

TAH

Temperature Alarm Low -Gas lift header at DCS

80°C

Table Alarm, Trip & Settings (Water Injection)

EQUIPMENT

water injection Tree

TAG NO

Alarm Type

DESCRIPTION

alarm/ TRIP set points

PSV set points

Water Injection X-Mass Tree Pressure

09M-PI-3020A-3

PALL

Pressure Alarm Low Low-seawater injection pump discharge

(HOLD)

09M-PI-3020A-3

PAHH

Pressure Alarm High High-seawater injection pump discharge

(HOLD)

SS-PT-3121

PAL

Pressure Alarm Low -Tree No. 31

250 bara

SS-PT-3121

PAH

Pressure Alarm High -Tree No. 31

300 bara

SS-PT-3122

PAL

Pressure Alarm Low -Tree No. 31

250 bara

SS-PT-3122

PAH

Pressure Alarm High -Tree No. 31

300 bara

SS-PT-3123

PAL

Pressure Alarm Low -Tree No. 31

250 bara

SS-PT-3123

PAH

Pressure Alarm High -Tree No. 31

300 bara

SS-PT-3124

PAL

Pressure Alarm Low -Tree No. 31

250 bara

SS-PT-3124

PAH

Pressure Alarm High -Tree No. 31

300 bara

SS-PT-3221

PAL

Pressure Alarm Low -Tree No. 32

250 bara

SS-PT-3221

PAH

Pressure Alarm High -Tree No. 32

300 bara

SS-PT-3222

PAL

Pressure Alarm Low -Tree No. 32

250 bara

SS-PT-3222

PAH

Pressure Alarm High -Tree No. 32

300 bara

SS-PT-3223

PAL

Pressure Alarm Low -Tree No. 32

250 bara

SS-PT-3223

PAH

Pressure Alarm High -Tree No. 32

300 bara

SS-PT-3224

PAL

Pressure Alarm Low -Tree No. 32

250 bara

SS-PT-3224

PAH

Pressure Alarm High -Tree No. 32

300 bara

SS-PT-3321

PAL

Pressure Alarm Low -Tree No. 33

250 bara

SS-PT-3321

PAH

Pressure Alarm High -Tree No. 33

300 bara

SS-PT-3322

PAL

Pressure Alarm Low -Tree No. 33

250 bara

SS-PT-3322

PAH

Pressure Alarm High -Tree No. 33

300 bara

SS-PT-3323

PAL

Pressure Alarm Low -Tree No. 33

250 bara

SS-PT-3323

PAH

Pressure Alarm High -Tree No. 33

300 bara

SS-PT-3324

PAL

Pressure Alarm Low -Tree No. 33

250 bara

SS-PT-3324

PAH

Pressure Alarm High -Tree No. 33

300 bara

SS-PT-3421

PAL

Pressure Alarm Low -Tree No. 34

250 bara

SS-PT-3421

PAH

Pressure Alarm High -Tree No. 34

300 bara

SS-PT-3422

PAL

Pressure Alarm Low -Tree No. 34

250 bara

SS-PT-3422

PAH

Pressure Alarm High -Tree No. 34

300 bara

SS-PT-3423

PAL

Pressure Alarm Low -Tree No. 34

250 bara

SS-PT-3423

PAH

Pressure Alarm High -Tree No. 34

300 bara

SS-PT-3424

PAL

Pressure Alarm Low -Tree No. 34

250 bara

SS-PT-3424

PAH

Pressure Alarm High -Tree No. 34

300 bara

SS-PT-4121

PAL

Pressure Alarm Low -Tree No. 41

250 bara

SS-PT-4121

PAH

Pressure Alarm High -Tree No. 41

300 bara

SS-PT-4122

PAL

Pressure Alarm Low -Tree No. 41

250 bara

SS-PT-4122

PAH

Pressure Alarm High -Tree No. 41

300 bara

SS-PT-4123

PAL

Pressure Alarm Low -Tree No. 41

250 bara

SS-PT-4123

PAH

Pressure Alarm High -Tree No. 41

300 bara

SS-PT-4124

PAL

Pressure Alarm Low -Tree No. 41

250 bara

SS-PT-4124

PAH

Pressure Alarm High -Tree No. 41

300 bara

SS-PT-4221

PAL

Pressure Alarm Low -Tree No. 42

250 bara

SS-PT-4221

PAH

Pressure Alarm High -Tree No. 42

300 bara

SS-PT-4222

PAL

Pressure Alarm Low -Tree No. 42

250 bara

SS-PT-4222

PAH

Pressure Alarm High -Tree No. 42

300 bara

SS-PT-4223

PAL

Pressure Alarm Low -Tree No. 42

250 bara

SS-PT-4223

PAH

Pressure Alarm High -Tree No. 42

300 bara

SS-PT-4224

PAL

Pressure Alarm Low -Tree No. 42

250 bara

SS-PT-4224

PAH

Pressure Alarm High -Tree No. 42

300 bara

SS-PT-4321

PAL

Pressure Alarm Low -Tree No. 43

250 bara

SS-PT-4321

PAH

Pressure Alarm High -Tree No. 43

300 bara

SS-PT-4322

PAL

Pressure Alarm Low -Tree No. 43

250 bara

SS-PT-4322

PAH

Pressure Alarm High -Tree No. 43

300 bara

SS-PT-4323

PAL

Pressure Alarm Low -Tree No. 43

250 bara

SS-PT-4323

PAH

Pressure Alarm High -Tree No. 43

300 bara

SS-PT-4324

PAL

Pressure Alarm Low -Tree No. 43

250 bara

SS-PT-4324

PAH

Pressure Alarm High -Tree No. 43

300 bara

SS-PT-4421

PAL

Pressure Alarm Low -Tree No. 44

250 bara

SS-PT-4421

PAH

Pressure Alarm High -Tree No. 44

300 bara

SS-PT-4422

PAL

Pressure Alarm Low -Tree No. 44

250 bara

SS-PT-4422

PAH

Pressure Alarm High -Tree No. 44

300 bara

SS-PT-4423

PAL

Pressure Alarm Low -Tree No. 44

250 bara

SS-PT-4423

PAH

Pressure Alarm High -Tree No. 44

300 bara

SS-PT-4424

PAL

Pressure Alarm Low -Tree No. 44

250 bara

SS-PT-4424

PAH

Pressure Alarm High -Tree No. 44

300 bara

Water Injection X-Mass Tree Temperature

09M-TI-3020A-2

TAHH

Temperature Alarm High High - seawater injection pump discharge

(HOLD)

SS-TT-3121

TAL

Temperature Alarm Low -Tree No. 31

50°C

SS-TT-3121

TAH

Temperature Alarm High -Tree No. 31

80°C

SS-TT-3122

TAL

Temperature Alarm Low -Tree No. 31

50°C

SS-TT-3122

TAH

Temperature Alarm High -Tree No. 31

80°C

SS-TT-3123

TAL

Temperature Alarm Low -Tree No. 31

50°C

SS-TT-3123

TAH

Temperature Alarm High -Tree No. 31

80°C

SS-TT-3124

TAL

Temperature Alarm Low -Tree No. 31

50°C

SS-TT-3124

TAH

Temperature Alarm High -Tree No. 31

80°C

SS-TT-3221

TAL

Temperature Alarm Low -Tree No. 32

50°C

SS-TT-3221

TAH

Temperature Alarm High -Tree No. 32

80°C

SS-TT-3222

TAL

Temperature Alarm Low -Tree No. 32

50°C

SS-TT-3222

TAH

Temperature Alarm High -Tree No. 32

80°C

SS-TT-3223

TAL

Temperature Alarm Low -Tree No. 32

50°C

SS-TT-3223

TAH

Temperature Alarm High -Tree No. 32

80°C

SS-TT-3224

TAL

Temperature Alarm Low -Tree No. 32

50°C

SS-TT-3224

TAH

Temperature Alarm High -Tree No. 32

80°C

SS-TT-3321

TAL

Temperature Alarm Low -Tree No. 33

50°C

SS-TT-3321

TAH

Temperature Alarm High -Tree No. 33

80°C

SS-TT-3322

TAL

Temperature Alarm Low -Tree No. 33

50°C

SS-TT-3322

TAH

Temperature Alarm High -Tree No. 33

80°C

SS-TT-3323

TAL

Temperature Alarm Low -Tree No. 33

50°C

SS-TT-3323

TAH

Temperature Alarm High -Tree No. 33

80°C

SS-TT-3324

TAL

Temperature Alarm Low -Tree No. 33

50°C

SS-TT-3324

TAH

Temperature Alarm High -Tree No. 33

80°C

SS-TT-3421

TAL

Temperature Alarm Low -Tree No. 34

50°C

SS-TT-3421

TAH

Temperature Alarm High -Tree No. 34

80°C

SS-TT-3422

TAL

Temperature Alarm Low -Tree No. 34

50°C

SS-TT-3422

TAH

Temperature Alarm High -Tree No. 34

80°C

SS-TT-3423

TAL

Temperature Alarm Low -Tree No. 34

50°C

SS-TT-3423

TAH

Temperature Alarm High -Tree No. 34

80°C

SS-TT-3424

TAL

Temperature Alarm Low -Tree No. 34

50°C

SS-TT-3424

TAH

Temperature Alarm High -Tree No. 34

80°C

SS-TT-4121

TAL

Temperature Alarm Low -Tree No. 41

50°C

SS-TT-4121

TAH

Temperature Alarm High -Tree No. 41

80°C

SS-TT-4122

TAL

Temperature Alarm Low -Tree No. 41

50°C

SS-TT-4122

TAH

Temperature Alarm High -Tree No. 41

80°C

SS-TT-4123

TAL

Temperature Alarm Low -Tree No. 41

50°C

SS-TT-4123

TAH

Temperature Alarm High -Tree No. 41

80°C

SS-TT-4124

TAL

Temperature Alarm Low -Tree No. 41

50°C

SS-TT-4124

TAH

Temperature Alarm High -Tree No. 41

80°C

SS-TT-4221

TAL

Temperature Alarm Low -Tree No. 42

50°C

SS-TT-4221

TAH

Temperature Alarm High -Tree No. 42

80°C

SS-TT-4222

TAL

Temperature Alarm Low -Tree No. 42

50°C

SS-TT-4222

TAH

Temperature Alarm High -Tree No. 42

80°C

SS-TT-4223

TAL

Temperature Alarm Low -Tree No. 42

50°C

SS-TT-4223

TAH

Temperature Alarm High -Tree No. 42

80°C

SS-TT-4224

TAL

Temperature Alarm Low -Tree No. 42

50°C

SS-TT-4224

TAH

Temperature Alarm High -Tree No. 42

80°C

SS-TT-4321

TAL

Temperature Alarm Low -Tree No. 43

50°C

SS-TT-4321

TAH

Temperature Alarm High -Tree No. 43

80°C

SS-TT-4322

TAL

Temperature Alarm Low -Tree No. 43

50°C

SS-TT-4322

TAH

Temperature Alarm High -Tree No. 43

80°C

SS-TT-4323

TAL

Temperature Alarm Low -Tree No. 43

50°C

SS-TT-4323

TAH

Temperature Alarm High -Tree No. 43

80°C

SS-TT-4324

TAL

Temperature Alarm Low -Tree No. 43

50°C

SS-TT-4324

TAH

Temperature Alarm High -Tree No. 43

80°C

SS-TT-4421

TAL

Temperature Alarm Low -Tree No. 44

50°C

SS-TT-4421

TAH

Temperature Alarm High -Tree No. 44

80°C

SS-TT-4422

TAL

Temperature Alarm Low -Tree No. 44

50°C

SS-TT-4422

TAH

Temperature Alarm High -Tree No. 44

80°C

SS-TT-4423

TAL

Temperature Alarm Low -Tree No. 44

50°C

SS-TT-4423

TAH

Temperature Alarm High -Tree No. 44

80°C

SS-TT-4424

TAL

Temperature Alarm Low -Tree No. 44

50°C

SS-TT-4424

TAH

Temperature Alarm High -Tree No. 44

80°C

7.0 Valve List

Table 30 Valve List

PRODUCTION WELL

Valve

DESCRIPTION

Tag Number

Choke Valve

PCV-1114

Production Wing Valve

XV-1102

Production Master Valve

XV-1101

Subsea Surface Safety Valve

XV-1112

Annulus Access Valve

AAV

Annulus Insert Valve

AIV

Annulus Master Valve

XV-1103

The above valves are identical for all production X MAS Tree

Manifold Production Valves

XV-1110

XV-1109

Manifold Test Valve

XV-1108

The above valves are identical for all X MAS Tree to the Drill centre manifold North and South

Pig Valves

XV-1015

XV-2015

Shutdown Valves

TU-SDV-0030-1

TU-SDV-0032-1

TU-SDV-0031-1

GAS LIFT SYSTEM

Choke Valve

PCV-1113

Annulus Wing Valve

XV-1113

Cross Over Valve

XV-1107

The above valves are identical for all production X MAS Tree

Gas Lift Valve

XV-1111

The above valves are identical for all X MAS Tree to the Drill centre manifold North and South

Shutdown Valve

TU-SDV-0230-1

WATER INJECTION SYSTEM

Choke Valve

PCV-1114

Injection Wing Valve

XV-1102

Injection Master Valve

XV-1101

Annulus Access Valve

AAV

Annulus Insert Valve

AIV

Annulus Master Valve

XV-1103

Cross Over Valve

XV-1107

The above valves are identical for all water injection X MAS Tree

Shutdown Valve

09M-SDV-3020A-18

Acknowledgements

With my signature I do hereby acknowledge that I have read and understood the preceding document.

Signature

Date

Signature

Date


Document Info


Accesari: 4197
Apreciat: hand-up

Comenteaza documentul:

Nu esti inregistrat
Trebuie sa fii utilizator inregistrat pentru a putea comenta


Creaza cont nou

A fost util?

Daca documentul a fost util si crezi ca merita
sa adaugi un link catre el la tine in site


in pagina web a site-ului tau.




eCoduri.com - coduri postale, contabile, CAEN sau bancare

Politica de confidentialitate | Termenii si conditii de utilizare




Copyright © Contact (SCRIGROUP Int. 2024 )