Activity Log

various


Activity Log

Monday, May 9 - USS

  • Met Dave Williams, Chad Klima
  • Met with team members, introduction
  • Set up Safety Meeting with Brad Fashbaugh for Wednesday May 11, 8:00 am ext. 2495
  • Friday 7:30 am safety meetings with Dave Williams and Chad.
  • Need to set RWP up as PMCI Safety Coordinator. May 19th safety meeting. Currently Wes.
  • IR report issues - Wes - Standardize on color code, Grey/White box color correction, fuse temp. (verify amp draw).
  • Skip hoist issues - found out that PMCI database sensitivity was incorrectly set at 1, should be 0.1. Scott Burkhardt went with Sorin to investigate issue. Scott corrected scaling (multiplier) for historic data. PMCI data indicates consistent with previous vendor history. Currently Priority 4 to monitor - gmf not increasing, continue trending for increases. B2 next outage scheduled for October. Customer has spare gear set available.
  • Work permit form needs to be filled out befor 16216c24q e starting work at all locations.
  • 11:00am Area Managers meeting - Jim XXX had issue with call out response time, claims it took 4 hours to respond?


  • Met Scott Buckiso, John Oszlewski - brief meeting on there way to Indiana (originally from MonValley)
  • Scott Buckiso: Harvey Guhman at CGL (4741) wants IR on Inductors and POT before July Outage. Schedule Wes for this.
  • Met with Paul Behnke. Main Contact. Purdue Grad.
    • Reviewed PMCI web-based Report Format - Paul wants more information (usability) from report before May 17th.
    • Reviewed USS Standardization (Best Practices) information from Andy. Needs to have presentation on this on May 17th.
    • May 18th, possibly web-based report format presentation.

Tuesday, May 10, 2005 - SeverStal

  • Submitted passes to Alan Hughes for signature approval on vehicle pass. Should be ready within two weeks.
  • Need to meet Keith Kahl
  • TOPS program - Alan Hughes
    • Need to get to know Program Managers

See if PMCI can be of assistance in documenting $$ savings, program stats, etc.

  • Bob Maciasz - Hot Mill TOPS - Need to provide him AK Steel IR information (Equipment under contract), RWP has hard copy and will present to Bob on Friday. Need information from Bob - "Electrical and Mechanical Delays" report. Detail as to cause of delay? (breakdown, ops, maintenance, etc).
  • Gary Higler - Blast Furnace TOPS Manager
  • Met Dennis Cogan 313 845 8048- briefly, need to meet with him in detail. Complimented team on Bursel IR catch.
  • MET THE FOLLOWING AT SEVERSTAL
    • ALAN (AL) HUGHES
    • BOB MACIASZ
    • SID HAYMOUR - HAVEN'T MET YET
    • MIKE BLANCHFIELD - WENT TO CHINA
    • SCOTT SANDER
    • RAY NEWSOME - NEED TO MEET
    • KAL LATHAM - NEED TO MEET
  • Get UPDATE SOFTWARE FROM HOME AND UPDATE USS AND SEVERSTAL
  • GET EMAIL FROM SEVERSTAL REGARDING DATABASE ERROR MSG AND LOOK INTO, ROGER AND ALLEN.
  • ALLEN CARR AND ROGER GREENE HAVE SIGNED OFF ON OSHA BOOKS, NEED TO GET JOE COPY.
  • LOOK INTO EARRING POLICY - SEVERSTAL/PMCI SAFETY?
  • SALES CALL
    • CABOT - STEVE BOYLE, 989 495-0030, EXT. 2107 MIDLAND
    • LOOKING FOR IR AND VIBRATION PROGRAM
    • HAD PROGRAM FROM CSI, TOO EXPENSIVE SINCE EMERSON BOUGHT THEM.
    • BEEN ONE YEAR SINCE LAST PROGRAM WITH ABOVE.
    • CALL ON Wednesday, MAY 11TH TO SET UP MEETING.
    • TRY TO SET MEETING FOR WEDNESDAY, MAY 18TH.
    • STEVE HAS Tuesday AND Thursday AFTERNOON MEETINGS AND IS OFF ON 5/13.
    • UTILIZE ANDY'S SALES BOOK. FOCUS ON PMCI WAY OF EXECUTION, REPORT FORMAT, CAPABILITIES, ETC.

May 11, 2005 - USS

  • 6:30am to 8:00am OSHA book distribution and sign-off
  • General Contractor Safety Meeting - Chad Fashbaugh 8:00am - 10:00 am.
  • 10:00 am - 11:00am Deal with Wes M. issue regarding USS standard procedure for IR Bottle Scan.
  • 11:00am - 12pm USS inventory update and pricing sent to Dave Williams. Dave says it needs to go to Paul Behnke. Need to deliver to Paul.
  • Greg Lexa to send 4 cables to RWP house, should arrive Friday 5/13/05.
  • Analysis review for Cleveland per Angela request
  • Tried to Contact Steve Boyle at Cabot - no answer 2pm
  • Confirmed CABOT CORP meeting for Wednesday, May 11, 2005 AT 8:00 AM.
  • Issue with Wes M. regarding inaccurate dates on AHR's and proper color coding.

May 12, 2005

  • Went to Zug Island to retake vibration readings on Furnace ID fan with Chris T. Met Bob Ford, Nathan Fields.
  • Need to set up monthly meeting dates with Nathan Fields at Zug Is.
  • Reviewed data for Zug Island.
  • Chris issued report.
  • Reviewed data w/in USS database - practice
  • Reviewed data with Sorin

May 13, 2005

  • Weekly safety meeting with Dave Williams, PMCI (Wes was on call out, did not attend).
  • Met with Tom Errer at CGL regarding data acquisition on the galvanized dip tank rolls. Set up database.
  • Met with Roger Greene at SeverStal, reviewed data from Chrysler CNC machine (spindle).
  • Dropped off 'AK Steel Hot Strip Mill IR Equipment List' to Bob Maciasz.

Document Info


Accesari: 1053
Apreciat: hand-up

Comenteaza documentul:

Nu esti inregistrat
Trebuie sa fii utilizator inregistrat pentru a putea comenta


Creaza cont nou

A fost util?

Daca documentul a fost util si crezi ca merita
sa adaugi un link catre el la tine in site


in pagina web a site-ului tau.




eCoduri.com - coduri postale, contabile, CAEN sau bancare

Politica de confidentialitate | Termenii si conditii de utilizare




Copyright © Contact (SCRIGROUP Int. 2024 )