CALCULUL VOLUMELOR DE LUCRARI

Arhitectura constructii


SECTIUNEA TEHNICO-ECONOMICA

CALCULUL VOLUMELOR DE LUCRARI

1.Terasamente



1.1.Decaparea stratului vegetal

S=150mp

1.2.Sapatura pentru fundatii

V= +6x0.4x1.27=85.2 mc

1.3.Imbunatatirea terenului de fundare:

V=+6x0.4x0.4=20.3 mc

2.Turnare betoane in infrastructura(fundatii placi cota -0.13)

V= 69x0.675mp= 46.6mc beton in fundatii c12/15

V=118x0.1=11.8mc beton in placa pardoseala cota -0.13

2.1.Cofrag fundatii

S = 69x2x1.25 =172 mp

2.2.Cofrag volume de beton si armature in sistem amvic pt pereti 818p152i :

S total = 23+34+63+37+30+19+16+32+32+30=322 mp

V total = 4.35+5+9.5+5.5+4.85+2.80+4.75+4.8+4.60+2.5=48.65mc c12/15

Gtotal = 265+257+26.4+15.1+473+66+267+123+58+14+68+50+111+51+111+109+53+349=2466.5 kg

CARCASA AXA A

SUPRAFETE

S total = 35mp

Sgoluri 3+3=6mp

S cofrag= 35-6=29 MP

VOLUME

V beton=29MP*15=4.35mc

rot. 4.35mc beton clasa C12/15

CARCASA AXA B

SUPRAFETE

S total = 67.3mp

Sgoluri 2.95+5.5+25=33.45mp

S cofrag= 67.3-33.5=33.85 mp

VOLUME

V BETON=33.90MP*.15=5.08MC

ROT.5.00MC BETON CLASA C12/15

CARCASA AXA C

SUPRAFETE

S total = 67.3mp

Sgoluri 0.64+0.64+2.8=4.08mp

S cofrag= 67.3-4.08 =63.22mp

VOLUME

V beton=63.2mp*0.15=9.48mc

rot. 9.5 mc beton clasa C12/15

CARCASA AXA B'

SUPRAFETE

S total =48mp

Sgoluri 9.26+2.1=11.35mp

S cofrag= 48-11.35 =36.65mp

VOLUME

V beton=36.65mp*0.15=5.49mc

rot. 5.50 mc beton clasa C12/15

CARCASA AXA1

SUPRAFETE

S total = 35mp

Sgoluri 3.03+1.04+1.04=5.11mp

S cofrag= 35-5.11 =29.90mp

VOLUME

V beton=29.90mp*0.15=4.85mc

rot. 4.90 mc beton clasa C12/15

CARCASA AXA2

SUPRAFETE

S total = 33.7mp

Sgoluri 6.98+4.35+3.52=14.85mp

S cofrag= 33.7-14.85 =18.85mp

VOLUME

V beton=18.85mp*0.15=2.80mc

rot. 2.8 mc beton clasa C12/15

CARCASA AXA3

SUPRAFETE

S total = 27.4mp

Sgoluri 10.8mp

S cofrag= 27.4-10.8 =16.6mp

VOLUME

V beton=16.6mp*0.15=2.5mc

rot. 2.5 mc beton clasa C12/15

CARCASA AXA4

SUPRAFETE

S total = 47mp

Sgoluri 2.4+6.13+7=15.50mp

S cofrag= 47-15.5 =31.5mp

VOLUME

V beton=31.5mp*0.15=4.75mc

rot. 4.80 mc beton clasa C12/15

CARCASA AXA 5

SUPRAFETE

S total = 36mp

Sgoluri 1.89+1.89=3.78mp

S cofrag= 36-3.78 =32.25mp

VOLUME

V beton=32.25mp*0.15=4.8mc

rot. 4.8 mc beton clasa C12/15

CARCASA AXA 6

SUPRAFETE

S total = 35mp

Sgoluri 3.04+1.28=4.32mp

S cofrag= 35-4.32 =30.70mp

VOLUME

V beton=30.70mp*0.15=4.60mc

rot. 4.60 mc beton clasa C12/15

2.3..Cofrag volume de beton si armature in sistem amvic pentru planseu :


Vbet= 7.8+2.7 =10mc

S cofrag=118mp

G total =451+964+138+60=1613kg

Lemn on sarpanta 5.8 mc calitatea 1 ecarisat

ANTEMASURATOARE

I. LUCRARI DE TERASAMENTE:

TSC01A1 - SCRIFICARE MECANICA A TERENURILOR CU SCARIFICATOR, TRACTOR PE SENILE DE 81-100CP PE ADANCIME DE 30 CM. TEREN CAT. 3 UM

1,5 100MP

TSA04E1 - SAPATURA MANUALA IN SPATII LIMITATE SUB 1 M CU SPRIJINIRI VERTICALE SI EVACUAREA MANUALA A PAMANTURILOR CU UMIDITATE NATURALA LA ADANCIMEA 0.5-3M TEREN MIJLOCIU

UM

8,00 MC

TSC03C1 - SAPATURA MECANICA CU EXCAVATOR DE 0.41-0.7 MC IN PAMANT CU UMIDITATE NATURALA CU DECARCARE IN DEPOZIT TEREN CAT. 3

UM

0,72 100MC

TSD 16B1 - STRAT DE REART. DIN BALAST SUB PRISMA DE BALAST CF. CU PLACA VIBR. DE 7 T MOTOR CU A.I. <10CP

UM

12 MC

TSD01A1 - IMPRASTIEREA PAMANTULUI AFANAT STRAT DE 10 30 CM CU SFARAMAREA BULGARILOR

UM

30 MC

TSD05B1 - COMPACTAREA CU MAI MECANIC DE 150-200KG A UMPLUTURII DE PAMANT IN STRATURI DE 20-30 CM EXCLUSIV UDARE . PAMANT COEZIV

UM

0,3 100MC

TSH12B1 - UDAREA SUPRAFETELOR CU FURTUNUL DE LA CISTERNA

UM

1,00 100MP

DA06A1 - STRAT AGREGAT NATURAL CILINDRATE CU FUNCTII FILTRANT IZOLANTE AERISIRE SI ANTICAPILAR CU ASTERNERE MANUALA

UM

16,5 MC

TRA01A.. - TRANSPORTUL RUTIER AL MATERIALELOR CU AUTOBASCULANTA LA ..KM

UM

41,5 T

II. LUCRARI DE BETOANE

CC01C1 - MONTARE ARMATURI IN FUNDATII CONTINUE PLACI, RADIERE

UM

2300 KG

CA07F1 - TURNARE BETON ARMAT IN FUNDATII CONTINUE SI LA ADANCIME PANA LA 10 M CU POMPA

UM

60 MC

CZ0105J1 - PREPARARE BETON B150 C12/15

UM

60 MC

CZ0301A1 - FASONARE ARMATUA D6-8 OB 37

UM

793 KG

CZ0301D1 - FASONARE ARMATURA D6-8 PC52

UM

691 KG

CZ0301B1 - FASONARE ARMATURA D10-16 PC52

UM

817 KG

CB02A1 - COFRAJ PT BETON IN ELEVATII DIN PANOURI REFOLOSIBILE DIN SCANDURI DREPTE 0-3 M

UM

172 MP

TRA 06A10 - TRANSPORT BETON CU AUTOBETONIERA DE 5.5 MC

UM

126 T

TRA02A10 - TRANSPORTUL RUTIER AL MATERIALELOR SEMIFABRICATELOR CU AUTOCAMIONUL PE DISTANTA DE 10 KM

UM

2,3 T

XXXXXX - MONTAJ COFRAG AMVIC PERETI

UM

322 MP

XXXXXX - MOTAJ COFRAG AMVIC PLANSEU

UM

112 MP

TRA 02AXX - TRANSPORT RUTIER AL COFRAJELOR TIP AMVIC

UM

... T

CC02B1 - MONTARE ARMATURA LA CONSTRUCTI CU H<35M DIN BARE D<12MM IN PERETI DIAFRAGMECU DIST DIN PLASTIC

UM

2466 KG

CA07G1 - TURNARE BETON ARMAT CU POMPA LA CONSTRUCTII CU H<15M IN PERETI, DIAFRAGME CU GROSIMEA<30CM

UM

49 MC

CZ0105J1 - PREPARARE BETON B150 C12/15

UM

49 MC

CZ0301D1 - FASONARE ARMATURA D6-8 PC52

UM

2466 KG

TRA 06A10 - TRANSPORT BETON CU AUTOBETONIERA DE 5.5 MC

UM

T

TRA02A10 - TRANSPORTUL RUTIER AL MATERIALELOR SEMIFABRICATELOR CU AUTOCAMIONUL PE DISTANTA DE 10 KM

UM

2,5 T

CA07H1 - TURNARE BETON ARMAT CU POMPA LOA CONSTRUCTII CU H<15M IN PLANSEE GRINZI SI STALPI

UM

10 MC

CC02C1 - MONTAJ ARMATURA IN PLACI LA CONSTRUCTII CU H<35M D<10MM CU DIST DIN PLASTIC

UM

1613 KG

CZ0301D1 - FASONARE ARMATURA D6-8 PC52

UM

260 KG

CZ0301B1 - FASONARE ARMATURA D10-16 PC52

UM

1353 KG

CZ0105J1 - PREPARARE BETON B150 C12/15

UM

10 MC

TRA 06A10 - TRANSPORT BETON CU AUTOBETONIERA DE 5.5 MC

UM

T

TRA02A10 - TRANSPORTUL RUTIER AL MATERIALELOR SEMIFABRICATELOR CU AUTOCAMIONUL PE DISTANTA DE 10 KM

UM

1,63 T

III. LUCRARI INVELITOARE

CE17C1 - SARPANTA DIN LEMN EXECUTATA REZEMAT DIRECT PE ZIIDURI LA INVELITORI USOARE

UM

MP

LEMN ECARISAT 5.8MC

CE18A1 - ASTEREALA EXECUTATA DIN SCANDURA DE RASINOASE

UM

125 MP

CE04A1 - INVELITOARE DIN TABLA ZINCATA (ARTICOL ASIMILAT)

UM

125 MP

CE23A1 - PLASA DE SIGURANTA REFOLOSIBILA LA EXECUTAREA INVELITORII CONSTRUCTIEI

UM

MP

intocmit,


Document Info


Accesari: 18502
Apreciat: hand-up

Comenteaza documentul:

Nu esti inregistrat
Trebuie sa fii utilizator inregistrat pentru a putea comenta


Creaza cont nou

A fost util?

Daca documentul a fost util si crezi ca merita
sa adaugi un link catre el la tine in site


in pagina web a site-ului tau.




eCoduri.com - coduri postale, contabile, CAEN sau bancare

Politica de confidentialitate | Termenii si conditii de utilizare




Copyright © Contact (SCRIGROUP Int. 2024 )