UNIVERSITATEA TEHNICĂ CLUJ-NAPOCA

FACULTATEA DE CONSTRUCŢII



PROIECT LA MANAGEMENT

GARAJ CU 4 BOXE

N=14

STABILIREA PĂRŢILOR DE OBIECT ALE CONSTRUCŢIEI

a.       Infrastructura:

defrisare manuala

sapatura manuala

turnare bloc fundatie

cofrare cuzinet

turnare beton īn cuzinet

cofrare grinda de fundare

armare grinda de fundare

turnare beton īn grinda de fundare

armare placa

turnare placa

umplutura

b.      Suprastructura:

- cofrare stīlp

- armare stīlp

- turnare beton īn stīlp

- cofrare grinda

- armare grinda

- turnare brton īn grinda

- montare planseu prefabricat

- zidarie īn peretii :- longitudinali

- transveli

c.       Acoperis:

- beton de panta

- hidroizolatie

ANTEMĂSURĂTOARE

Nr.

crt.

Simbol articol

Denumire

Calcule

Total pe articole

INFRASTRUCTURĂ

TS C 18 B

- sapatura mecanica cu bulbozerul

se masoara la suta de mc.

12x10x0,1=12 mc

12 mc

TS A 02 E

sapatura manuala

se masoara īn mc.

1.40x1.40x0.97x9=17.12 mc

3.475x0.25x0.3x6+

2.475x0.25x0,3x2=1.935 mc

∑=19.06 mc

20.00 mc

CA 01 A marca B50

turnare beton simplu īn fundatie

1.40x1.40x0.67x9=11.82 mc

12.00 mc

CZ 01 02 A

preparare B50

11.82x1.008=11.92 mc

12.00 mc

CB 10 A

cofrare cuzinet si grinda cu panouri tego (mp.)

0.8x0.3x4x9+(3.475+1.2)x0.3x2x6+

(2.475+1.2)x0.3x2x2=29.88 mp

30.00 mp

CC 01 A

montarea armaturilor din otel beton kg

2.7x9=24.3  kg ų 6

4.6x9=41.9  kg ų 14

20x6=120  kg GF1 ų 6

14x2=28 kg GF2 ų 6

5.4x6=32.4  kg GF1 ų 10

3.8x2=7.6  kg GF2 ų 10

17.2x6=103.2 kg GF1 ų 12

12.2x2=24.4 kg GF2 ų 12

1.4x6=8.4  kg GF1 ų 14

1.0x2=2.0  kg GF2 ų 14

TOTAL/ų

Ų6 =172.3 kg

kg

Ų12=127.6kg

Ų14=51.8 kg

TOTAL= 391.7 kg

392 kg

CZ 03 01 A

Confectionare armatura ų6 OB 37

172,3 kg

172,3 kg

CZ 03 01 B

Confectionare armatura ų10-16 OB37

219.4 kg

219.4 kg

CA 02 A

Turnare beton īn cuzinet si grinda de fundare

0.8x0.8x0.3x9=1.73 mc

(3.475+1.2)x0.25x0.3x6=2.11 mc

(2.475+1.2)x0.25x0.3x2=0.55 mc

4.39 mc

4.50 mc

CZ 01 04 A

Preparare beton B100

4.39x1.008=4.42 mc

4.50 mc

TS D 01

Īmprastiere cu lopata

1.4x1.4x0.3-0.8x0.8x0.3=0.396 mc x 9 = 3.564 mc

3.6 mc

TS D 01

Compactarea cu maiul de māna

V=3.6 mc

3.6 mc

CC 01 C

Montarea armaturilor din OB37 (pardoseala) kg

1.7 kg ų6 1.7x83.64=142.19 kg

143.0 kg

CZ 03 01 G

Confectionare otel beton ų6 OB37

1.7 kg 1.7x83.64=142.19 kg

143.0 kg

CA 02 I

Turnare beton īn pardoseala [mc]

83.64x0.1=8.364 mc

8.4 mc

CZ 01 04 A

Preparare beton B100

8.364x1.008=8.43 mc

8.5 mc

SUPRASTRUCTURĂ

CB 04 B

Cofrare st lp[mp]

0,24x4x2,5=2,5 mpx9=22,5mp

22,5mp

CC 0,2 C

Montarea armaturii īn stālp [kg]

12.6x9=113.4

18.9x9=170.1

283.5 kg

283.5 kg

CZ 03 02 G

Confectionare armatura īn stālp

113.4 kg

113.4 kg

CZ 03 02 H

Confectionare armatura īn stālp

170.1 kg

170.1 kg

CA 02 I

Turnarea betonului īn stālp

0.25x0.25x2.5x9=1.41 mc

1.41 mc

CZ 01 06 A

Prepararea B 200 stālpi

1.41x1.008=1.43 mc

2.49x1.008=2.51 mc - de la 02.16

3.96 mc

3.96 mc

CB 04 B

Cofrare grinzi [mp]

(0.15x2+0.3x2)x4.625x6=24.98 mp

(0.15x2+0.3x2)x3.625x6=19.58 mp

44.56 mp

44.56 mp

CC 02 C

Montarea armaturii īn grinda

G x

7.9x

12.4x

14x

G 19.3x

6.1x

9.7x6=58.2

11x6=66

TOTAL /

=293.4 kg

10=84kg

14=132.6 kg

16=150kg

TOTAL = 660 kg

660 kg

CZ 03 02 G [kg]

Confectionare

293.4 kg

293.4 kg

CZ 03 02 H [kg]

Confectionare

366.6 kg

366.6 kg

CA 02 I [mc]

Turnare beton īn grinda

G1=0.15x0.3x3.625x6=1.25 mc

G2= 0.15x0.3x4.625x6=0.98 mc

2.23 mc

2.23 mc

CZ 01 06 A [mc]

Preparare B 200 īn grinzi + monolitizare fāsii

2.33x1.008=2.247 mc

2.51 mc

4.737 mc

4.76 mc

CD 04 G

Zidarie din caramida

0.125 x2.20x4.625x6=7.63 mc

0.125 x2.20x3.625x2=1.81 mc

9,44 mc

9,44 mc

CZ 02 01

Preparare mortar pentru zidarie [mc]

0.18x9.44=1.70 mc

1.70 mc

CP 09 A

Montare fāsii prefabricate [buc

20 buc

FS

Procurare fāsii 20 buc

20 buc

CP 25 F

Monolitizare fāsii

2.49 mc

2.5 mc

CC 02 C

Montare armaturi īn centuri

C1  5x8.2=41 kg

10 1.2x8.2=9.84 kg

C2  7x10.2=71.4 kg

10 1.2x10.2=12.24 kg

TOTAL  6= 112.4 kg

10=22.08 kg

134.48 kg

134.48 kg

CZ 03 02 G

Confectionarea armaturi īn centuri

112.4 kg

112,4 kg

CZ 03 02 H

Confectionare armaturi īn century

10 22,8 kg

22,8 kg

CA 01 D

Turnare beton de panta

0.2x10.2=83.64x0.074=6.27 mc

6.27 mc

CZ 01 04 A

Preparare beton panta B 100

6.27x1.008=6.32 mc

6.4 mc

F4 b [mp]

Strat hidroizolant pentru acoperis

1.12x83.64x2=187.35 mc

carton bituminous

bitum  1.55x83.64x3=388.92 kg

83.64x5=418.5 mp

418.5 mp

TRANSPORT

TRA 02 A 14

Transport rutier al materialelor semiprefabricate si a armaturii cu autocamionul pe distanta de 14 km

13,65x20 273 KN - prefabricate

14.77 KN -armaturi

28,77 t

29,0 t

TRA 06 A 14

Transport rutier al betonului  cu autobetoniera de 5 mc pe distanta de 14 km

12+4.5+8.5+3.96+2.5+4.76+1.70+6.4=44.32 mc

44.32x2.5=110.80 t

111 t


Document Info


Accesari: 2062
Apreciat: hand-up

Comenteaza documentul:

Nu esti inregistrat
Trebuie sa fii utilizator inregistrat pentru a putea comenta


Creaza cont nou

A fost util?

Daca documentul a fost util si crezi ca merita
sa adaugi un link catre el la tine in site


in pagina web a site-ului tau.




eCoduri.com - coduri postale, contabile, CAEN sau bancare

Politica de confidentialitate | Termenii si conditii de utilizare




Copyright © Contact (SCRIGROUP Int. 2024 )